You are on page 1of 60

Concrete Retaining Wall

Jonathan Fuller, Angela Hughey, Bryan Lunsford, Alan Stevenson, Chad Wise Auburn University Womens Softball Complex

Group Four
Table of Contents
Client Information Project Details Research Preconstruction Photos Model Drawings Takeoff & Estimate Donated Material Member Responsibility Schedule Safety Plan Photos Final Costs Conclusions Member Statements

Client Information
Organization: Auburn University (Womens Softball) Contact: Jan Swaim, Pete Dunnaway

Project Details
The structure needed was a concrete retaining wall to prevent further mud damage to the batting cages in the womens softball complex. The wall will connect to an existing series of retaining walls and stand about waist high.

Research
http://www.concretenetwork.com/concrete/poured_concrete_retai ning_walls/provisions.htm

Provisions for Joints in the Construction of Walls

This online article details the use of joints in concrete construction. We referenced it in designing our expansion joint. The article also shows key and roughened surface joints.

Preconstruction Photo

Preconstruction Photo

Design Sketches

Design Sketches

3D Modeling

3D Modeling

3D Modeling

Detail Documentation

Detail Documentation

Original Take off & Estimate


4x8x1/2 Plywood (15) -1 Drill bit Concrete: 9.77cu. yds. =about 10cu. yds. #4 Rebar=524 linear feet Spray form release Screws (2 and 3) Spray expansion foam gravel (.67 x 48 x 1 = 33 cu. Ft.) Drain pipe= 75 linear ft. Vapor barrier= 1 2x4x16 2x4x8 ($18 ea.)$270 Na ($56ea.)$560 786 $5 $10 $5 free 36 36 240 230 About $2168.00

Donated Material & Services


Tiebacks Pigs feet Fence moved 50ft Bobcat / backhoe rental Shovels AU and us Tools us Edger Trowel Rebar cutter Gutter moved

Group member responsibilities


Jonathan Fuller: Rebar delivery and placement Angela Hughey: On site organization Bryan Lunsford: Client communicator Alan Stevenson: Project drawing, Forms Chad Wise: Concrete delivery and placement/ Safety Manager

Project Schedule

Job Specific Project Safety Program All exposed footings must be roped off with caution tape and flagged. All power equipment must be used by a competent person. Safety glasses must be worn at all times. In cases of accident all personal must see Chad Wise Safety Manager. Cell Phone must be present at all times incase of emergency.

Final Costs
4x8x1/2 Plywood (14) 2x4x16 Pine 2x4x8 Pine Concrete: 15.5 cubic yards #4 Rebar= 28-20 pieces Chamfer strips Powder Actuated Nail Gun with 2 Pin and 27 Cal Strip Load Green Turnbuckle, form Silicon 1/2x4x8 Blue Board Cast Off (5Gal) Release Form Snap Tie Screws (2 and 3) gravel Drain pipe= 75 linear ft. $529.76 $184.50 $185.46 ($56ea.)$868.00 87.36 $36.00 $46.00 $46.00 $221.85 $21.88 $8.28 $29.79 $69.99 $Free $Free $36.00 Total $2370.87

Estimated $2168.00

Conclusions | Things we might have changed


Vibration should be systematic and even throughout the wall Use more caution during pour (chamfer strips) Dont assume anything. - Jan Swan (footing below)

We could have drawn more detailed drawings before construction instead of fast-tracking Pay attention to the politics in any job Have clear communication with everyone involved

Group Member Statements


Jonathan Fuller: Hands-on is the best way to learn. Angela Hughey: Building always takes longer than you think. Bryan Lunsford: Working with personnel is difficult. Alan Stevenson: Working in a group can be rewarding and challenging. Chad Wise: Prof. Hein is the greatest.

You might also like