TITAN Project - T
Contents
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Construction Activity Summary Weather Record Safety Control Status Quality Control Status Construction Progress Summary Quantitative Construction Progress Status Three Weeks Construction Schedule Construction Manpower Status Material Delivery Status Pending Matters --> Status of Pending Items Areas of Concern
1.
** **
Last Week
Major Activities 1) Civil * * * * 2) Structure * * 3) Mechanical * * 4) Piping Prepare Site ITP for Steel Stucture Site Visit to Precast Concrete Supplier/Vendor 13-10-2011 10-11-2011
1.
Status
This Week
Highlight ** ** Major Activities 1) Civil * * Prepare Bill of Quantity/Work Volume for Civil Works Prepare & Update Work Breakdown Schedule for Civil Structure Work
Due Date
Status
Ongoing Ongoing
2.
Weather Record
Description
Sun 10/9 Mon 10/10 Morning- clear Evening-cloudy Tue 10/11 Morning- clear Evening-cloudy Wed 10/12 Morning- clear Evening-storm Thu 10/13 Morning- cloudy Evening-clear
2.1
Weather Condition
a. Clear b. Cloudy c. Rainy * Morning * Afternoon * Evening ** Total (mm) d. Windy
2.2
Temperature (C)
a. Highest b. Lowest
2.3
Remarks
EA
0 0
0 0
0 0
HR EA
960 0 0
0 0 0
960 0 0
Others 0 0 0
Total 0 0 0
Remarks
0 0 0
2.
1) 2) 3) 4) 5)
: : : : :
11-10-17
Civil
Stl-Str.
Equip.
Piping
Elect.
I&C
14 of 22
Paint'g
Insul.
Total
15 of 22
7.
319 Days
This Week
* Project Period :
5/24/2011
~
Next Week
8/24/2012
Tue
10/11
Wed
10/12
Thu
10/13
Fri
10/14
Sat
10/15
Sun
10/16
Mon
10/17
Tue
10/18
Wed
10/19
Thu
10/20
Fri
10/21
Sat
10/22
Sun
10/23
Mon
10/24
Tue
10/25
Wed
10/26
Thu
10/27
Fri
10/28
Sat
10/29
Sun
10/30
Remarks
Civil
1 2 3 4 5 6 7 8 9
1/12 1/16 1/8 1/20 1/18 1/9 9 3 2 EA m m 96 39 63 63 48 12/24 1/14 1/17 d 25
#VALUE!
50% 100% -
Piping
1 2 3 4 5
20% 100% 100% 100% 100% 1/16 12/30 1/11 1/9 1/22 1/22 1/22 1/22 1/22 1/21 1/3 1/14 1/11 1/29 1/29 1/29 1/29 1/29 6 5 4 3 8 8 8 8 8 m m m m m m m m m 177 51 130 130 260 261 262 263 264 51 51 130 29% 100% 100% <Note>
Electrical
1 2 3 4 5
Discipline
Remarks
Last Week
1 2 3 5 7 8 9 10 11
Temp. Fac. Civil Stl-Str. Equipment Piping Electrical I&C Painting Insulation Total
Action By
PD PD PCM/PE
Due Date
Overall / General
14-Oct-11
** Project Coordination Procedure_R1 * Main Text * Construction Weekly Report (Form) * Submit to TITAN Engg ** ** RFQ/PO Pending Items * Field Fab Tanks * Mixer & Ejector * Fire-Fighting Eqt * Gas Detection Sys. * E&I Cable/Wire * Piping Mat'l (2nd) * Piping Special Parts (1st) * Butterfly Valve RFQ
14/06/11 10/08/11 19/09/11 27/07/11 08/09/11 12/10/11
PD PD PE(HO)
B/C
23/06/11 19/08/11 28/09/11 24/10/11 29/09/11
TBE
Nego
PO
SRD
Proc
** Additionally Required Material for U/G Piping * PE Coated Pipe ( ?" x ??m) * Heat-Shrink Sleeve/Wrapping Materials for PE Coated Piping - Option-1 : CO for Subcontractor - Option-2 : Use Wrapped Pipes for a certain Section ** Delay in CC Concern on Demurrage of Containers Write eMail to TITAN stating Demurrage Rate ** Construction Planning * Prepare Work Volume Distribution Plan (Preliminary)
DCM/PCM
HJS
06-Oct-11
Const
** ITP * Reflect TITAN Comment and include Site/Field ITP * Detail ITP for Civil Works * Detail ITP for Steel Str. Works
[ Legend ]
U : Urgent,
A/B/C : Priority
H : Holding
ding Items
As of : 2011-10-15
Prio -rity
A U H
Status/ Forecast
Reference / Remarks
* Sent Expediting e-Mail to TITAN on 10-Oct. * Be ready for Approval Processing * Construction Team to review T&C and SOW
ETA(Site)
Done
Completed