sTaGE 3 Ground floor slab is poured and formed sTaGE 4a BELow GrounD sLaB The Basement will then be excavated to 6m below ground level in sequence with the aid of Ground anchors. sTaGE 4B aBoVE GrounD sLaB Tower construction commences with the installation of the jump form system for the lift cores. sTaGE 5a BELow GrounD sLaB Excavation continues from beneath the ground floor slab with the aid of a gantry crane to load the trucks with excavated material. The installation of ground anchors continues in sequence. once the excavation is complete to the bottom, each ground slab is poured one level at a time to the ground floor. sTaGE 5B aBoVE GrounD sLaB simultaneously with the basement works, activity continues above ground level with the tower construction.