You are on page 1of 13

ADDITIONAL WORKS Item Description Qty Unit Unit Rate Amount

CICO OFFICE
A B C D E F 100mm Screed on slab 100mm blocks partition Plaster for internal partition Supply & fixed & painted doors panel and doors frame Supply & apply water proofing FCU concrete base at roof a. Shuttering walls b. Mass concrete c. Supply & apply water proof Supply & fixed 18mm MDF on drop beam internal front elevation with aluminum angle 40x40mm Car park (supply & laying interlock and construction of car shade foundation Precast Kerbstone Supply & apply dust pfroofing and silcon sealant 1240 92 184 23 34 5 4 15 90 158 38 1240 m2 m2 m2 nos m2 m2 m3 m2 lm m2 lm m2 60.00 85.00 32.00 1,800.00 65.00 45.00 500.00 65.00 110.00 90.00 100.00 25.00 74,400.00 7,820.00 5,888.00 41,400.00 2,210.00 225.00 2,000.00 975.00 9,900.00 14,220.00 3,800.00 31,000.00

G H I J

OFFICES & SHOWROOMS

QATAR DECORATION OFFICES & SHOWROOMS Partition a. Supply & laying of 100mm, 200mm blocks Demolish & rebuild 100mm blocks a. Demolish b. Rebuild Plaster internal walls & ceiling a. Wall b. Ceiling Supply & fixed steel structure to cover stair & slab opening 2600x4700mm a. Demolish of concrete stair using cmpressor b. Demolish of internal walls c. Complete steel structure cover with insulation 2600x4700mm d. 100mm thk screed on top of steel structure 823 60 40 1726 661 m2 m2 m2 m2 m2 85.00 30.00 85.00 32.00 32.00 69,955.00 1,800.00 3,400.00 55,232.00 21,152.00

6 64 1 13

Days m2 LS m2

800.00 30.00 30,000.00 60.00

4,800.00 1,920.00 30,000.00 780.00

Page 1 of 13

e. Mesh laid on steel structure 300mm Stair extension (2 part) a. 300mm cut on slab (2part) b. Steel anchorage to concrete c. Reinforce concrete extension d. Formworks

13 2 200 50 5

m2 LS nos steps m2

18.00 4,000.00 50.00 50.00 85.00

234.00 8,000.00 10,000.00 2,500.00 425.00

STAIR AT G.L.19-20 LUMINARIES (SHOP 13-14) A B C D E F G H I K L M N O Breaking of slab on grade & mezzanine slab using compressor Excavation Polythene sheet 100mm thk concrete blinding Bitumen paint Footing & slab on grade reinforce concrete (SRC) Reinforce concrete on staircases (OPC) Supply & apply water proof Supply & Fixed steel structure I-beam, steel column & anchor bolt Backfill Footing & staircase steel Reinforcement Footing & staircase shuttering formworks 200mm blockworks Plaster SHOP 4-5(G.L 6-8/A-E) A B C D 100mm blocks Wall plaster Blocks filled with concrete and steel anchorage 80cm in height Breaking of stair & rebuil to modify a. breaking of stair using compressor b. Steel reinforcement & anchorage to concrete c. Formworks d. Reinforce concrete CONVERT SHOP 6-7 (G.L. 9-11/A-E) A C Supply & laying of 100mm, 200mm blocks Wall plaster BREAD TALK SHOP 8 (G.L 9-12/A-E) Page 2 of 13 21 42 m2 m2 85.00 32.00 1,785.00 4,232.00 198 396 14 2 100 5 2 m2 m2 m2 days kg m2 m3 85.00 32.00 115.00 800.00 3.75 85.00 700.00 16,830.00 12,672.00 1,610.00 1,600.00 375.00 425.00 1,400.00 6 15 35 10 21 6 7 11 1 13 624 30 155 310 Days m3 m2 m2 m2 m3 m3 m2 LS m3 kg m2 m2 m2 800.00 45.00 3.00 60.00 5.00 700.00 670.00 30.00 20,000.00 30.00 3.75 45.00 85.00 32.00 4,800.00 675.00 105.00 600.00 105.00 4,200.00 4,690.00 330.00 20,000.00 390.00 2,340.00 1,350.00 13,175.00 9,920.00

A B C D E F G H I J K L M N

Supply & laying of 100mm, 200mm blocks Plaster Breaking of slab on grade & mezzanine slab using compressor Excavation Polythene sheet 100mm thk concrete blinding Bitumen paint Footing & slab on grade reinforce concrete (SRC) Reinforce concrete on staircases (OPC) Supply & apply water proof Supply & Fixed steel structure I-beam, steel column & anchor bolt Backfill Footing & staircase steel Reinforcement Footing & staircase shuttering formworks PASCUCCI SHOP 9

211 422 6 15 35 10 21 6 7 11 1 13 624 30

m2 m2 Days m3 m2 m2 m2 m3 m3 m2 LS m3 kg m2

85.00 32.00 800.00 45.00 3.00 60.00 5.00 700.00 650.00 30.00 20,000.00 30.00 3.75 85.00

17,935.00 13,504.00 4,800.00 675.00 105.00 600.00 105.00 4,200.00 4,550.00 330.00 20,000.00 390.00 2,340.00 2,550.00

A B C D E F G H I J K L M N

Supply & laying of 100mm, 200mm blocks Plaster Breaking of slab on grade & mezzanine slab using compressor Excavation Polythene sheet 100mm thk concrete blinding Bitumen paint Footing & slab on grade reinforce concrete (SRC) Reinforce concrete on staircases (OPC) Supply & apply water proof Supply & Fixed steel structure I-beam, steel column & anchor bolt Backfill Footing & staircase steel Reinforcement Footing & staircase shuttering formworks RICKS SHOP 10

152 304 6 15 35 10 21 6 7 11 1 13 624 30

m2 m2 Days m3 m2 m2 m2 m3 m3 m2 LS m3 kg m2

85.00 32.00 800.00 45.00 3.00 60.00 5.00 700.00 670.00 30.00 20,000.00 30.00 3.75 85.00

12,920.00 9,728.00 4,800.00 675.00 105.00 600.00 105.00 4,200.00 4,690.00 330.00 20,000.00 390.00 2,340.00 2,550.00

A B C

Supply & laying of 200mm blocks to support stair landing 6 Plaster 12 Breaking of stair & rebuild to modify a. breaking of stair using compressor 2

m2 m2 days

85.00 32.00 800.00

510.00 384.00 1,600.00

Page 3 of 13

b. Steel reinforcement & anchorage to concrete c. Formworks d. Reinforce concrete

100 5 2

kg m2 m3

3.75 85.00 700.00

375.00 425.00 1,400.00

SHOP 1-3
A B C Supply & laying of 100mm, 200mm blocks Plaster DEMOLISH OF 40cm thk GRADE SLAB AND RECONCRETE SLAB ON GRADE (G.L 3-4/A-B) a.Breaking using compressor b.100mm thk blinding concrete c.Reinforce concrete (SRC) d.Mesh A252 4 33 7 33 Days m2 m3 m2 800.00 60.00 700.00 18.00 3,200.00 1,980.00 4,900.00 594.00 211 422 m2 m2 85.00 32.00 17,935.00 13,504.00

SEPTIC TANK
A B C D Excavation Blinding Reinforce concrete (SRC) foundation & walls Shuttering formworks a. Foundation b. Walls Steel reinforcement Manhole cover Step iron Polythene sheet Bitumen paint DEMOLISH & REBUILD OF EXISTING BOUNDARY WALL AT RIGHT ELAVATION A B C D Demolish using compressor 200mm blocks Plaster External paint RETAINING WALL 80mtrs LONG A Excavation 30 m3 45.00 1,350.00 2 36 72 72 Days m2 m2 m2 800.00 85.00 32.00 28.00 1,600.00 3,060.00 2,304.00 2,016.00 60 20 48 6 120 3600 1 10 80 80 m3 m2 m3 m2 m2 kg no nos m2 m2 45.00 60.00 700.00 45.00 85.00 3.75 1,000.00 50.00 3.00 5.00 2,700.00 1,200.00 33,600.00 270.00 10,200.00 13,500.00 1,000.00 500.00 240.00 400.00

E F G H I

Page 4 of 13

B C D E F G

Polythene sheet Blinding concrete 100mm thk Reinforce concrete Shuttering formworks Steel reinforcement Bitumen paint ELEVATOR

160 40 20 128 1640 80

m2 m2 m3 m2 kg m2

3.00 60.00 700.00 45.00 3.75 5.00

480.00 2,400.00 14,000.00 5,760.00 6,150.00 400.00

A B C D E

Supply & fixed I-beam 100x100x100mm Steel angle Anchor bolts Mass concrete(Elevator 1 & 2) Breaking of concrete for elevator opening and remove & refixing of marble

12 3 24 4 10

m m nos m3 m2

500.00 400.00 100.00 500.00 1,000.00

6,000.00 1,200.00 2,400.00 2,000.00 10,000.00

ENTRANCE CANOPY LEFT ELEVATION

Complete supply & fixed for canopy steel frame, composite panel, and complete accessories MAIN ENTRANCE MARBLE 3cm thk SUPPLY & FIXED

LS

15,000.00

15,000.00

A B C

Tread Riser Landing SUPPLY AND FIXED OF 3mm thk MARBLE WALL CLADDINNG AT END CURTAIN WALL WITH FIXING ACCESSORIES at COLUMN RELOCATION OF FIRE FIGHTING 150mm dia PIPE due to MIDMAC works ENTRANCE LOBBY ABOVE OPENING 1000x2500mm

7 7 3

lm lm m2

300.00 45.00 475.00

2,100.00 315.00 1,425.00

80

m2

750.00

60,000.00

LS

10,000.00

10,000.00

Supply & fixed steel cover ALUMINUM LOUVERS LEFT & RIGHT ELEVATION FIXED TO WALL

LS

3,000.00

3,000.00

Supply & fixed of aluminum louvers with complete accessories for fixing

160

m2

400.00

64,000.00

Page 5 of 13

ADDITIONAL I-BEAM AT EXPANSION JOINT & CLADDING A B Supply & fixed I-beam Supply & fixed 2mm stainless steel cladding EXTRA WALL MOUNTED RAIL 1st FLOOR INTERNAL FRONT ELEVATION A Supply & fixed stainless steel 27 lm 1,500.00 40,500.00 8 52 nos lm 2,500.00 1,700.00 20,000.00 88,400.00

STAIR SKIRTING (stair 1-stair 5) A Supply & fixed tile on stair 845 lm 20.00 16,900.00

GRAND TOTAL

1,136,339.00

Page 6 of 13

ADDITIONAL WORKS Item Description Qty Unit Unit Rate Amount

CICO OFFICE
A B C D E F 100mm Screed on slab 100mm blocks partition Plaster for internal partition Supply & fixed & painted doors panel and doors frame Supply & apply water proofing FCU concrete base at roof a. Shuttering walls b. Mass concrete c. Supply & apply water proof NDF supply & fixed on drop beam internal front elevation Car park (supply & laying interlock and construction of car shade foundation 1240 92 184 20 34 5 4 15 90 m2 m2 m2 nos m2 m2 m3 m2 m

G H

OFFICES & SHOWROOMS


QATAR DECORATION OFFICES & SHOWROOMS A Partition a. 200mm blocks b. 100mm blocks Demolish & rebuild 100mm blocks a. Demolish b. Rebuild Plaster internal walls & ceiling a. Wall b. Ceiling Supply & fixed steel structure to cover stair a. Demolish of concrete stair using cmpressor b. Demolish of internal walls c. complete steel structure cover with insulation d. 100mm thk scredd on top of steel structure e. Mesh laid on steel structure 300mm Stair extension (2 nos) a. 300mm cut on slab 6 64 Days m2 LS 13 13 8 m2 m2 m

538 285 60 40 1462 661

m2 m2 m2 m2 m2 m2

Page 7 of 13

b. Steel anchorage to concrete c. Reinforce concrete extension d. Formworks COFFEE SHOP A B 200mm blocks partition Plaster SEPTIC TANK A B C D Excavation Blinding Reinforce concrete (SRC) foundation & walls Shuttering formworks a. Foundation b. Walls Steel reinforcement Manhole cover Step iron Polythene sheet Bitumen paint DEMOLISH & REBUILD OF EXISTING BOUNDARY WALL AT RIGHT ELAVATION A B C D Demolish using compressor 200mm blocks Plaster External paint RETAINING WALL 80mtrs LONG A B C D E F G Excavation Polythene sheet Blinding concrete 100mm thk Reinforce concrete Shuttering formworks Steel reinforcement Bitumen paint ELEVATOR A B C Supply & fixed I-beam 100x100x100mm Steel angle Anchor bolts

200 50 5

nos steps m2

200 400

m2 m2

60 20 48 6 120 3600 1 10 80 80

m2 m2 m3 m2 m2 kg no nos m2 m2

E F G H I

2 36 72 72

Days m2 m2 m2

30 160 40 20 128 1640 80

m3 m2 m2 m3 m2 kg m2

12 3 24 Page 8 of 13

m m nos

D E

Mass concrete Breaking of concrete for elevator opening and remove & refixing of marble STAIR AT G.L.19-20 LUMINARIES (SHOP 1314)

4 10

m3 m2

A B C D E F G H I J K L M N

Breaking of slab on grade using compressor Excavation Polythene sheet 100mm thk concrete blinding Bitumen paint Footing reinforce concrete (SRC) Reinforce concrete slab on grade (SRC) Supply & apply water proof Supply & Fixed steel structure I-beam, steel column & anchor bolt Cutting of slab on grade using compressor Backfill Steel Reinforcement 200mm blockworks Plaster STAIRCASE LUMINARIES(Shop 13-14)

3 15 35 10 21 3 3 11

Days m3 m2 m2 m2 m3 m3 m2 LS

3 13 80 250 500

days m3 kg m2 m2

A B C D E F

Rebars shuttering formworks Reinforce concrete (OPC) 200mm Blocks Plaster Breaking of concrete slab using compressor ADDITIONAL I-BEAM AT EXPANSION JOINT & CLADDING

250 20 6.5 3 3 3

kg m2 m3 m2 m2 Days

A B

Supply & fixed I-beam Supply & fixed 2mm stainless steel cladding EXTRA WALL MOUNTED RAIL 1st floor internal front elevation

8 8

nos nos

Supply & fixed stainless steel

27 Page 9 of 13

STAIR SKIRTING (stair 1-stair 5) A Supply & fixed tile on stair 845 m

DEMOLISH OF 40cm thk GRADE SLAB AND RECONCRETE SLAB ON GRADE (G.L 3-4/A-B) A B C D Breaking using compressor 100mm thk blinding concrete Reinforce concrete (SRC) Mesh A252 RELOCATION OF FIRE FIGHTING 150mm dia PIPE due to MIDMAC works ENTRANCE LOBBY ABOVE OPENING 1000x2500mm A Supply & fixed steel cover SHOP 4-5(G.L 6-8/A-E) A B C D 100mm blocks Wall plaster Blocks filled with concrete and steel anchorage 80cm in height Breaking of stair & rebuil to modify a. breaking of stair using compressor b. Steel reinforcement & anchorage to concrete c. Formworks d. Reinforce concrete CONVERT SHOP 6-7 (G.L. 9-11/A-E) A C Supply & laying of 100mm, 200mm blocks Wall plaster m2 m2 21 42 120 268 14 2 100 5 2 m2 m2 m2 days kg m2 m3 LS 4 33 7 33 Days m2 m3 m2 LS

ALUMINUM LOUVERS LEFT & RIGHT ELEVATION FIXED TO WALL A Supply & fixed of aluminum louvers with complete accessories for fixing 160 m2

Page 10 of 13

ENTRANCE CANOPY AT LEFT ELEVATION Complete supply & fixed for canopy steel frame, composite panel, and complete accessories MAIN ENTRANCE MARBLE 3cm thk SUPPLY & FIXED A B C Traid Riser Landing 7 7 3 lm lm m2

LS

SUPPLY AND FIXED OF 3mm thk MARBLE WALL CLADDINNG AT END CURTAIN WALL WITH FIXING ACCESSORIES at COLUMN BREAD TALK SHOP 8 (G.L 9-12/A-E) A B 100mm blocks Plaster FOUNDATION & STEEL FRAMING TO SUPPORT SLAB A B C D E F G H I J K L

50

m2

Breaking of slab on grade using compressor Excavation Polythene sheet 100mm thk concrete blinding Bitumen paint Footing reinforce concrete (SRC) Reinforce concrete slab on grade (SRC) Supply & apply water proof Supply & Fixed steel structure I-beam, steel column & anchor bolt Cutting of slab on grade Backfill Steel Reinforcement BREAD TALK SHOP 8 (G.L 9-12/A-E) STAIR

3 15 35 10 21 3 3 11

Days m3 m 10m m2 m3 m3 m2 LS

13 80

LS m3 kg

A B

Steel reinforcement Shuttering formworks

250 20 Page 11 of 13

kg m2

C D E F

Reinforce concrete (OPC) 200mm Blocks Plaster Breaking of concrete slab using compressor PASCUCCI SHOP 9

6.5 3 3 3

m3 m2 m2 Days

A B

Supply & laying of 100mm, 200mm blocks Plaster

88 176

m2 m2

FOUNDATION & STEEL FRAMING TO SUPPORT SLAB A B C D E F G H I J K L Breaking of slab on grade using compressor Excavation Polythene sheet 100mm thk concrete blinding Bitumen paint Footing reinforce concrete (SRC) Reinforce concrete slab on grade (SRC) Supply & apply water proof Supply & Fixed steel structure I-beam, steel column & anchor bolt Cutting of slab on grade Backfill Steel Reinforcement PASCUCCI SHOP 9 STAIR A B C D E F Rebars shuttering formworks Reinforce concrete (OPC) 200mm Blocks Plaster Breaking of concrete slab using compressor RICKS SHOP 10 A B C Supply & laying of 200mm blocks to support stair landing 6 Plaster 12 Breaking of stair & rebuild to modify a. breaking of stair using compressor 2 b. Steel reinforcement & anchorage to 100 concrete Page 12 of 13 m2 m2 days kg 250 20 6.5 3 3 3 kg m2 m3 m2 m2 Days 3 15 35 10 21 3 3 11 Days m3 m 10m m2 m3 m3 m2 LS 13 80 LS m3 kg

c. Formworks d. Reinforce concrete

5 2

m2 m3

Page 13 of 13

You might also like