PROCEDURE FOR EXECUTION

ABOUT: TEST STATIC LOAD ON PILES

Contents: 1. Scope of Work 2. Attached drawings and specifications 3. Methods and sequence of work 4. Responsible-site technical manager 5. Equipment needed 6. Technical Safety: Analysis of possible hazards Safety measures to eliminate or reduce hazardous situations 7. Quality: Quality Manager or Quality Officer Quality Controllers Inspection and test plan Maintain document records 8. Applications Prepared by the contractor / name of the author / Checked by Manager of Safety: checked by Environment Manager: Verified / Prepared by Manager checked by Manager of Quality Assurance Approved by the Project Manager

1. Scope of work
1.1 The methodology is related to conducting static load test piles as follows: - Pilot piles with load 250% of the workload or reaction / sinking or destruction / - Work pilots, load 150% of the workload. 1.2 The responsible manager has an obligation to distribute a copy of the methodology to all participants and monitor the work to be done pursuant thereto.

2. Attached drawings and specifications


2.1 Trial static load of pilots is done with a set of facilities generally shown in the scheme-Appendix1. 2.2 Implementation of the load is carried out according to the applied hydraulic circuit -Annex2. 2.3 The location of the pilot - tested and base, and their parameters are determined by the technical design.

3. Used methods and consequence of work


3.1Installation of the loading structure. 3.2 Stepwise compressive loading in the Technical Specification - generally shown in the table below.
Period % Workload 0 25 50 75 100 75 50 25 0 0 25 75 100 125 150 125 100 75 0 Minimum retention time after loading / unloading / [min] 0 60 60 60 180 10 10 10 60 0 10 10 60 60 720 10 10 10 60

I to 100 %

II to 150 %

4. Responsible-site technical manager.


By the subcontractor - project-Chief ................................... By the subcontractor - Technical Manager - ......................

5. Necessary technical resources and personnel.


2

5.1 Staff. 5.1.1 installers - welders - 2 5.1.2 Mechanics - 2 5.1.3 Testers - 2 5.2 Equipment 5.2.1 Cargo design - according to Annex 1. 5.2.2 Hydraulic system - according to Annex 2. 5.2.3 Assembly crane with capacity Q 30 tons. 5.2.4 Diesel power unit and electric welding 2 pieces. 5.2.5 Three indicators of the number of clock accuracy 0.01 mm and 25 mm range.

6. Technical Safety.
6.1 Analysis of possible hazards 6.2 Measures to prevent risk 6.3 Complete program to ensure safe working conditions

7. Quality
7.1 Responsible for the Quality Control Responsible for QC by the subcontractor - ............................ Site engineer in charge of QC - ............................................ .... 7.2 Performance of the test in accordance with: The technical specification for the site Norms for design of pile foundation, BAS, 1993 BS EN 1997 1: 2004 / E / t.7.5.Izpitvane pilots to test workload. 7.3 Processing received results / tabular and graphical / Recording of results during the static test will be carried out in the attached table below. Table reports from clock indicators.
Date Degree Hour Instrument I1 I2 I3 In/3 Remarks:

Report

Report

Report

Report

Report

Diagram to be submitted are: - Curve s = f(P); - Curve s = f(t) in the given step for loading / unloading where : s (mm) subsidence of the pilot for the applied load condition (kN) applied level of loading.

Aplication 1:

Aplication 2: