Definition Industrialised Building System (IBS)


The Industrialised Building Systems (IBS) is a construction process that utilises techniques, products, components, or building systems which involve prefabricated components and on-site oninstallation.

Introduction
All building components such as wall, floor slab, beam, column and staircases are mass produced either in factory or at site under strict quality control and minimal on site activities Mechanisaton of the building processes Eg of completed building in Malaysia HUKM, university Hospital, Selayang Hospital, Kuala Lumpur Tower< IKEA Damansara

Structural Category of IBS


Based on CIDB: Group 1: Pre-cast Concrete Framing, 1: PrePanel and Box Systems Includes precast concrete columns, beams, slabs, walls 3 D components eg balconies, staircases, toilets, lift chambers, refuse chambers Lightweight precast concrete and permanent concrete formworks
4

Group 1

PrePre- cast Concrete Components

Balcony

Beams
5 6

22/10/2010

Structural Category of IBS


Group 2: 2: Steel Formwork Systems

Group 2

eg tunnel forms, tilt-up system tiltbeams/columns moulding and permanent formworks

Tilt-up system
7 8

Structural Category of IBS


Group 3: 3: Steel Framing Systems

Structural Category of IBS


Group 4: Prefabricated Timber Framing Systems Prefabricated timber framing systems consists of prefabricated timber trusses, beams and columns

Steel framing system eg steel trusses, columns, beams and portal frame system

10

Structural Category of IBS


Group 5: 5: Block Work Systems

PrePre-cast Concrete
Concrete cast into desired shapes prior to placement in a structure

Blockwork system includes interlocking concrete masonry unit (CMU) Lightweight concrete blocks

11

12

22/10/2010

PrePre-cast Concrete

Prestressed Concrete

13

14

Erection
The assembly of parts put together in different ways to form the total building fabric The parts meet at joints or connections Joint refers to the space between components whether or not they are in contact

Frame Joints

15

16

Precast Frame Joints

Advantages of Pre-cast concrete Presystem (1)


High level mechanisation thus precision No delay due to bad weather and manpower Application of modular design in standardising dimensions Work done concurrently at factory and at site thus speed up construction Low site workers requirement due to simplified construction methods Quality controlled and highly aesthetic end products Reduction of construction materials at sites Save costs

17

18

22/10/2010

Advantages of Pre-cast concrete Presystem (2)


Reduction / elimination of conventional timber formworks Reduction / elimination of props Reduction of construction wastes Cleaner sites safer construction sites Faster completion of construction projects Cheaper total construction costs made possible due to all of the above
19

Modular Coordination (MC)


Is a concept of coordination of dimensions and space in which building and components are dimensioned and positioned in terms of basic units or modules known as 1M = 100mm MS 1064: 2001 Malaysian Standard for modular coordination
20

Why MC
Provide a coherent method for coordinating the position and dimension of components in the planning and design of buildings Improve productivity in building industry. MC facilitate achievement of industrilisation Provide guide to component sizes thus reduce work on site eg trimming and shaping hence reduce wastage and labour Standardisation simplify site operation by rationalising setting out, positioning and assembly of building components
21

Examples: IBS
The construction of Police Station in Senawang Negeri Sembilan: Comprises of 1 unit of Police Station Office Block, 4 units of Class F Quarters and 2 Units of Class G Quarters and the External works

22

THE CONSTRUCTION OF QUARTERS G

NUMBERS OF PANELS USED


Precast Wall Precast Slab Block Block Block Block G2 G1 G2 G1 91 94 94 94 1 468 91 94 94 94 1 468 0 102 102 102 0 408 0 102 102 102 0 408
24

The Block comprises of 5 Storey Building as shown in the picture Level

QUARTERS G

1 2 3 4 Upper Roof
23

22/10/2010

CONSTRUCTION PROCESS USING PRECAST PANELS


PILING PILE CAP cast insitu cast insitu cast insitu cast insitu

STUMP GROUND BEAM FLOOR SLAB COLUMN

PILING WORK FOR FOUNDATION

precast

INSTALLATION OF CONCRETE WALL PANEL


PROCESS REPEATED FOR SUCCESIVE FLOOR

precast cast insitu

INSTALLATION OF FLOOR SLAB CONCRETE PANEL

CONCRETE TOPPING ON FLOOR SLAB

25

26

PREPARATION OF PILE CAP (CAST INSITU)

PREPARATION OF COLUMN STUMP (CAST INSITU)


27 28

29

30

22/10/2010

CONSTRUCTION OF GROUND BEAM (CAST INSITU)

Dowel Bar

INSTALLATION OF 300 MM x 25 MM DIA.- DOWEL BAR AT GROUND BEAM


31 32

MOULD FOR THE PRECAST CONCRETE PANEL WAS FABRICATED IN THE FACTORY ACCORDING TO THE DESIGN SPECIFICATIONS INCLUDING REQUIREMENTS FOR ELECTRICAL INSTALLATION

MOULD FOR THE PRECAST CONCRETE PANEL

33

34

CASTING PROCESS IN A FACTORY

35

36

22/10/2010

WORK ON CASTING IN PROGRESS IN A FACTORY

37

38

COMPLETED WALL PANELS

PANELS TO BE TRANSPORTED TO CONSTRUCTION SITES


39 40

THE USE OF FULL TIME CRANE FOR THE HOISTING AND INSTALLATION OF PANELS
41 42

22/10/2010

CAST IN SITU COLUMNS READY FOR PANEL INSTALLATION

COLUMNS ARE READY FOR THE INSTALLATION OF SUCCESSIVE PANELS


43

ONE CRANE AND 5 SKILLED WORKERS WERE USED FOR THE INSTALLATION OF THE PRECAST CONCRETE PANELS
44

WORKS ON INSTALLATION OF WALL PANELS USING A CRANE

Installation of Precast Panels

DOWEL BARS WERE SLOT TO THE HOLE SLOT UNDERNEATH THE PANEL FOR CONNECTION
45 46

TEMPORARY SUPPORT WRE USED IN WALL INSTALLATION FOR VERTICAL ALIGNMENT

PANELS WERE HOIST THROUGH PROPER HOOKS AND FIXED THROUGH THE PANEL CONNECTION SLOTS

47

48

22/10/2010

THE USE OF PANEL-SUPPORT IS TO ENSURE THE VERTICALITY IN POSITIONING OF PANELS

49

50

CONCRETE JOINTS BETWEEN COLUMN AND WALL PANELS

CROSS-SECTION OF PANEL JOINT DETAIL

CONCRETING OF THE JOINTS USING CONCRETE CHIPPING OF GRADE 25

51

52

GROUTING OF THE JOINTS BETWEEN WALL AND COLUMN


53

COMPLETED COLUMN/PANEL JOINT

54

22/10/2010

INSTALLATION OF PRECAST FLOOR SLAB PANEL

GROUTING IN PROGRESS USING GROUTING MATERIALEMCRETE S

55

56

PREPARATION OF FLOOR SLAB CONCRETE TOPPING (CAST INSITU)

FLOOR SLAB PANELS FIXED TO POSITION

ELECTRICAL CONDUITS AND RETICULATION PIPES ARE INSTALLED AND FIXED INTO POSITION BEFORE CONCRETE TOPPING WERE CARRIED OUT

57

58

BOTTOM VIEW

COMPLETED FLOOR SLAB

ROOF TRUSS OF QUARTERS G

59

60

10

22/10/2010

FINISHING AND FINAL TOUCH- UP

QUARTERS G NEARLY COMPLETION

PAINTINGS

61

62

INTERNAL VIEW OF QUARTERS G

LOUNGE

OTHER EXAMPLE OF PRECAST CONCRETE PANELS CONSTRUCTION Construction of Quarters in Audit Academy in Negeri Sembilan

DINING

More Types of Precast Panels were used in the construction

KITCHEN
63 64

Components delivered for this project are as below:


Hollow Core Slab Precast Plank Precast Balcony Precast Beam Precast Column Precast Staircase (Flight & Landing Elements) Precast Parapet & Load Bearing Walls 1927.0 m2 291.0 m2 16 nos. 136 nos. 63 nos. 12 nos. 200 nos.
65

SOME COMPLETED PROJECT PHOTOS USING PRECAST CONCRETE STRUCTURE


-Commercial Building Category

66

11

22/10/2010

SOME COMPLETED PROJECT PHOTOS USING PRECAST CONCRETE STRUCTURE


-Public Building Category

67

68

12

You might also like