You are on page 1of 14

The District of Columbia Public Library Capital Construction Report May 23, 2012

Document #9C Board of Library Trustees Meeting May 23, 2012

Bellevue Library New Building Design

Contacts
Councilmember Ward 8 Marion Barry 202.724.8045 Architect Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Coakley-Williams

Progress

Furniture installation began on May 15th Opening Date is June 13th.

DCPL PM Firm

Jair Lynch Development Partners

Francis A. Gregory Library New Library

Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Hess Construction

Progress

Furniture Installation began on May 18th Opening Date is June 19th

Design of the new Francis Gregory Library will include community input on planning and programming phase. Project is fully funded.

DCPL PM Firm

Jair Lynch Development Partners

Mount Pleasant Interior Restoration

Contacts
Councilmember Ward 1 Jim Graham 202.724.8181

Progress

Architect

Core Architects

All zoning and legal issues have been resolved. Work is 95% Complete Furniture Installation to begin on June 30th Opening date will be the last full week in July.

Dale Stewart 202.466.6116 Project Manager Contractor Phase II of Mount Pleasant Renovation. Interior work will consist of total upgrade and modernization of all mechanical equipment as well as provide additional and functional library program space. Chris Wright 202.727.4913 T.B.D

DCPL Project Management

Smoot Construction

Northeast Library Design-Build Renovations

Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072
Bell/Vines Architects

Progress

Architect

David Bell Victor Vines Project Manager Design-Builder This project is a major interior renovation of the 1930s era library. Renovations will create a 21st Century library while maintaining the historic integrity of the buildings interior. Chris Wright 202.727.4913 Whiting-Turner Andrew Easter

Design-Builder selected. Conceptual Design Phase underway. 3rd Meeting with Northeast Friends May 21st Project is fully funded. Vertical transportation addition approved by HPRB.

West End Library Mixed Use Development

Contacts
Councilmember Ward 2 Jack Evans 202.724.8058

Progress

Architect

Ten Arquitectos

Erik Lang Project Manager Developer Kim Fuller 202.442.6069 EastBanc Joe Sternlieb 202.737.1000

New ground floor library will be part of mixed use development. Library designs are underway. Project has received preliminary PUD approval from DC Zoning Commission on February 13, 2012.

Woodridge Library Design

Contacts
Councilmember Ward 5 Harry Thomas Jr. (202) 724-8028

Progress

Architect

Wiencek + Assoc

Bing Thom Arch

Pre-design due diligence work includes a hazardous materials survey, a Phase 1 and Phase 2 Environmental Site Assessment, Existing Topographical Survey, Geotechnical Report and a Cost Benefit Analysis.

Project Manager Contractor

Kim Fuller 202.442.6069

Design contract to Weincek and Associates in partnership with Bing Thom Architects was approved by Council. Program Analysis underway.

MLK Jr. Library Business and Technology Reconfiguration

Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
The Freelon Group

Progress

Space planning for Business, Science and Technology Complete Project scope has increased to handle shifting of library collections on the 2nd Floor. Currently reviewing building code issues. MCN Build Selected as Construction Manager eBic and Book Store Plus have been removed.

Derek Jones 919-941-9790 Project Manager Contractor Kim Fuller 202-442-6069 MCN Build Joseph Kourney 202.333.3424 Improvements and upgrades to west reading room. Entire first floor is under the Historic Landmark Designation. The MLK Design Guidelines will be utilized.

Completed Projects
Anacostia Library New Building Construction Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect Freelon Group Philip Freelon 919.941.9790 Project Manager Dedric Boyd 202.727.1127 Contractor Forrester Construction Tom Willerton 301.816.1700 New State of the Art Library on Good Hope Road SE is open. DCPL PM Firm Hill International

Progress

Opened to the public April 26, 2010

Benning Library New Building Design

Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Davis, Brody, Bond & Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester Jon McGee 301.255.1750

Progress

Architect

Opened to the public April 5, 2010

New State of the Art Library located at 3935 Benning Road NE is open.

DCPL PM Firm

A-1 Consulting

Cleveland Park New Ceiling and Lighting

Contacts
Councilmember Ward 3 Mary Cheh 202.724.8062 Architect
N/A

Progress

Project Manager

Ed Hampton 202.442.6067

Project Complete

Contractor Project consists of installing a new ceiling and lighting system.

Eagle Construction

Deanwood New Community Center and Library

Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect EEK Sean ODonnell

Progress

Project Manager Contractor

Opened to the public June 25, 2010

Project is a partnership with the Department of Parks and Recreation to co-locate a 10,000 square foot library within a 54,000 square foot aquatic center and community center. Library and Community Center would share such space as computer lab, senior rooms, tutor rooms and community meeting rooms. Project location is 49th and Quarles St. NE

Energy Enhancement Projects Various Locations

Contacts
Councilmember Various

Progress

Architect

T.B.D

Project Manager Capitol View, Cleveland Park, Shepherd Park, Lamond Riggs, Palisades, Southwest, West End and Woodridge The Library has received Federal Stimulus Money for energy enhancements. Projects will take place at the above locations, focusing on window replacements, energy efficient lighting, and automated building heating and cooling controls Contractor

Ed Hampton 202.442.6067

Energy Efficient Lighting Projects are COMPLETE Window and Door work is complete

DCPL PM Firm

Francis A. Gregory Library Interim Library

Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect

Progress

Project Manager

Lisa Deanes 202.727.5181

Opened June 10, 2010

Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets

William Scotsman Greg Bichell

DCPL PM Firm

Georgetown Library Building Renovation

Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
Martinez & Johnson

Progress

Tom Johnson 202.333.4480 Project Manager Contractor Chris Wright 202.272.4913 N/A

Opened to the Public October 18, 2010

Renovation complete and Library open to the public. DCPL PM Firm Smoot Construction

Mount Pleasant Interim Library

Contacts
Councilmember Ward 1 Jim Graham 202.724.8181

Progress

Architect

Core Architects

Dale Stewart 202.466.6116 Project Manager Contractor Project consists of building a 3,600 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets Dedric Boyd 202.727.1127 MCN Build Bassem Boustany 202.333.3424

Opened to the public April 26, 2010 Re-opened to the public May 15, 2010

Northeast Library Exterior Restoration

Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072

Progress

Architect

Bell Architects

David Bell 202.548.7570 Project Manager Chris Wright 202.727.4913 Contractor Monarc Construction C. McDermott, Project consists of Exterior Improvements to windows, doors, security lighting, masonry restoration, landscaping and signage. 703.201.1747

Construction
Substantial completion May 15, 2010

Northwest One New Co-location Facility

Contacts
Councilmember Ward 6 Tommy Wells

Progress

Architect

Hord Cort Plan

Project Manager Contractor

Reagan Assoc

Library Open December 7, 2009 Open to the Public

Forrester

Project consists of 6,500 SQ FT Library facility as part of Elementary School and Recreation Center. This facility replaces the Sursum Corda kiosk.

10

Parklands-Turner New Storefront Library

Contacts
Councilmember Ward 8 Marion Barry 202.724.8045

Progress

Architect

Mood Nolan - DC

Patrick Williams 202.244. Project Manager Contractor Project to fit out approximately 5,000 Sq Ft of storefront space to replace the existing Parklands-Turner kiosk. The storefront library is similar in size, scope, computers, and collections to the Georgetown Interim and Tenley-Friendship Interim Libraries. Dedric Boyd 202.727.1129 Lexx Group Ken Postell 202.393.

Ribbon Cutting October 5, 2009 OPEN TO THE PUBLIC

Petworth Library Interim Library

Contacts
Councilmember Ward 4 Muriel Bowser 202.724.8052 Architect N/A

Progress

Project Manager Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets

Lisa Deanes 202.727.5181 Sigal Construction Sarah Norman

Opened to public on January 11, 2010 Closed February 5, 2011

DCPL PM Firm

11

Petworth Interior Renovations

Contacts
Councilmember Councilmember Ward 4 Architect Muriel Bowser 202.724.8052
Frank and Loshen

Progress

Fletcher Farr Anoyte Project Manager Contractor Project updates the interior of the Petworth Library to be a fully functional state of the art 21st Century Library, while still being respectful of the buildings historic character.

Chris Wright 202.727.4913 Sigal Construction Sarah Norman

Open February 28, 2011

DCPL PM Firm

McKissack and McKissack

Tenley Friendship New Building

Contacts
Councilmember Ward 3 Mary Cheh 202.724.8062 Architect Freelon Group Philip Freelon 919.941.9790 Project Manager Contractor Dedric Boyd 202.727.1113 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm Hill International

Progress

Opened January 24, 2011

Design of the new Tenley Branch Library will include community input on planning and programming phase. Design and construction is fully funded.

12

Washington Highlands Interim Library

Contacts
Councilmember Ward 8 Marion Barry 202.724.8045 Architect Cooper Carry

Progress

Project Manager Contractor Project consists of building a 5,000 square foot interim library for the Washington Highlands Community; the interim will have 20 computers, books on CD as well as traditional collection material for all age sets.

Lisa Deanes 202.727.5181 MCN Build

Open to the public December 21, 2009

DCPL PM Firm

Jair Lynch Development

Watha T. Daniel / Shaw New Building Design

Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Davis, Brody Bond & Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm A-1 Construction

Progress

Architect

Opened to the public August 2, 2010

Project complete and Library is open to the public. .

13

Martin Luther King Jr. Library New Teen Spot and College Information Center

Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
Sorg Associates

Progress

Suman Sorg Project Manager New Teen Spot and College Information Center is a destination for teens. It provides stimulating learning opportunities that support their success in life. This destination provides opportunities to meet their need for homework help, exam preparation, and using computers and software applications. High quality program events are a key to the success of the library in assisting teens. Contractor

Kim Fuller 202.442.6070 Bennett Group Kolar Bowen 202. 625.3330

Project Complete

14

You might also like