Status Of Mechanical Work The CENTAURUS Shopping Mall

NO
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Activity
PPRC + UPVC Piping Acessories Installation PPRC + UPVC Piping Installation of pumps Installation of chillers Installation of piping Installation of Electrical panel Electrical & control work Testing & commissioning PPRC + UPVC Piping Installation Of Pumps Installation Of main line Cleaning of B-3 Lines Pipe riser connection Testing of FCUs Electrical & Control Connection of FCUS Installation of multisplit units( Lift Lobby) Testing & Commissioning Duct Risers Grills & Diffusers FCU Connections of ducts Duct in common areas Installation of pipe

Location
B- Mazznine B- Mazznine B-1 Plant Room B-1 Plant Room B-1 Plant Room B-1 Plant Room B-1 Plant Room B-1 Plant Room B-1 B-2 B-3 B-3 B-3

Level
B-M B-M B-1 B-1 B-1 B-1 B-1 B-1 B-1 B-2 B-3 B-3 B-3 G.F G.F G.F

Supervisor
M.Bilal M.Bilal M.Bilal Yousuf Ali Yousuf Ali Yousuf Ali By Electrical Dept. By Electrical Dept. Awais & Yousuf M.Bilal M.Bilal &Yousuf Ali Arshad Ahsan M.Ayaz Yousuf Ali Yousuf Ali Yousuf Ali

Contractor
Grace Engineers Grace Engineers Grace Engineers Mecatech Mecatech Mecatech Mecatech Mecatech Mecatech Grace Engineers Technofire/ Grace Engineers Grace Engineers

Completed%
100 60 80 0 0 0 0 0 0 80 0 0 0

Remaining %
0 40 20 100 100 100 100 100 100 20 100 100 100 60 100 100

Completion
Not Provided Not Provided Not Provided June 15 2012 June 23 2012 June 30 2012 June 23 2012 June 30 2012 July 15 2012 Not Provided Not Provided Not Provided Not Provided May 31 2012 June 15 2012 June 15 2012

Remarks
Completed Indian WC Flush Tank, Floor Drains, Padestle type wash basin still not received Pipe & wash room Accessories awaited Subjected of completion of foundations Subjected to arrival of chillers Subjected to route cleaning

Subjected to availability of gas and power Main line installation required Material procurment required Material procurment required Contractor required for work Work in progress Subjected to Provision of service doors in ceiling Subjected to Provision of service doors in ceiling

Mecatech Mecatech

40 0 0

Mecatech G.F G.F G.F G.F G.F G.F G.F Yousuf Ali Mecatech Yousuf Ali Yousuf Ali Yousuf Ali Yousuf Ali Yousuf Ali Arshad Ahsan Mecatech ATS ATS ATS ATS Mecatech 0 20 0 100 100 100 100 80 100 0 0 0 June 30 2012 Not Provided Not Provided Not Provided Not Provided Not Provided Subjected to arrival of chillers & installation of Cooling Towers ATS has not provided any data yet ATS has not provided any data yet Completed Completed Completed 0 100 June 30 2012 Not yet started

17 18 19 20 21 22 23

NO
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Activity
Installation of Sprinklers Installation of HRC Installation of Breeching inlet Installation of Valves PPRC + UPVC Piping Acessories Installation Installation of cooling Towers Pipe riser connection Testing of FCUs Electrical & Control Connection of FCUS Testing & Commissioning Duct Risers Grills & Diffusers FCU Connections of ducts Duct in common areas Installation of pipe Installation of Sprinklers Installation of HRC Installation of Breeching inlet Installation of Valves PPRC + UPVC Piping Acessories Installation

Location

Level
G.F G.F G.F G.F G.F G.F G.F

Supervisor
Arshad Ahsan Arshad Ahsan Arshad Ahsan Arshad Ahsan M.Bilal M.Bilal Yousuf Ali & M.Bilal

Contractor
Technofire Technofire Technofire Technofire Grace Engineers Grace Engineers Mecatech

Completed%
60 0 0 0 100 85 20

Remaining %
40 100 100 100 0 15 80

Completion
Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided June 15 2012

Remarks
Work in process Material Awaited Material Awaited Material Awaited Completed Indian WC Flush Tank, Floor Drains, Padestle type wash basin still not received Subjected to dismentling of scaff-folding

M-1 M-1 M-1

Yousuf Ali Yousuf Ali

Mechatech Mechatech

40 0 0

60 100 100 100 80 100 100 0 0 40 100 100 100 0 20

May 31 2012 June 15 2012 June 15 2012 June 30 2012 Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided

Work in progress Subjected to Provision of service doors in ceiling Subjected to Provision of service doors in ceiling Subjected to arrival of chillers & installation of Cooling Towers ATS has not provided any date of completion ATS has not provided any date of completion FCU connection ic Atriums Still pending due to insufficient duct material Completed Completed Work in process Material Awaited Material Awaited Material Awaited

Yousuf Ali M-1 Yousuf Ali M-1 Yousuf Ali M-1 Yousuf Ali M-1 M-1 Yousuf Ali

Mechatech Mechatech ATS ATS ATS ATS Mechatech Technofire Technofire Technofire Technofire Grace Engineers Grace Engineers 0 20 0 90 100 100 60 0 0 0 100 80

Yousuf Ali M-1 Arshad Ahsan M-1 Arshad Ahsan M-1 Arshad Ahsan M-1 M-1 M-1 M-1 Arshad Ahsan Arshad Ahsan M.Bilal M.Bilal

Indian WC Flush Tank, Floor Drains, Padestle type wash basin still not received Work in progress Subjected to Provision of service doors in ceiling Subjected to Provision of service doors in ceiling

Pipe riser connection Testing of FCUs Electrical & Control Connection of FCUS

M-2 M-2 M-2

Yousuf Ali Yousuf Ali

MECATECH MECATECH

40 0 0

60 100 100

May 31 2012 June 15 2012 June 15 2012

Yousuf Ali

MECATECH

NO
51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80

Activity
Testing & Commissioning Duct Risers Grills & Diffusers FCU Connections Duct in common areas Installation of pipe Installation of Sprinklers Installation of HRC Installation of Breeching inlet Installation of Valves PPRC + UPVC Piping Acessories Installation

Location

Level
M-2

Supervisor

Contractor
MECATECH ATS ATS ATS ATS MECATECH Technofire Technofire Technofire Technofire Grace Engineers Grace Engineers

Completed%
0 20 0 100 100 100 0 0 0 0 100 80

Remaining %
100 80 100 0 0 0 100 100 100 100 0 20

Completion
June 30 2012 Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided

Remarks
Subjected to arrival of chillers & installation of Cooling Towers ATS has not provided any date of completion ATS has not provided any date of completion Completed Completed Completed Work in process Material Awaited Material Awaited Material Awaited

Yousuf Ali M-2 Yousuf Ali M-2 Yousuf Ali M-2 Yousuf Ali M-2 Yousuf Ali M-2 Arshad Ahsan M-2 Arshad Ahsan M-2 Arshad Ahsan M-2 M-2 M-2 M-2 Arshad Ahsan Arshad Ahsan M.Bilal M.Bilal

Indian WC Flush Tank, Floor Drains, Padestle type wash basin still not received

Pipe riser connection Testing of FCUs Electrical & Control Connection of FCUS Testing & Commissioning Duct Risers Grills & Diffusers FCU Connections Duct in common areas Installation of pipe Installation of Sprinklers Installation of HRC Installation of Breeching inlet Installation of Valves PPRC + UPVC Piping Acessories Installation Pipe riser connection

M-3 M-3 M-3

Yousuf Ali Yousuf Ali

MECATECH MECATECH

40 0

60 100

May 31 2012 June 15 2012

Work in progress Subjected to Provision of service doors in ceiling

Yousuf Ali M-3 Yousuf Ali M-3 Yousuf Ali M-3 Yousuf Ali M-3 Yousuf Ali M-3 Yousuf Ali M-3 Arshad Ahsan M-3 Arshad Ahsan M-3 Arshad Ahsan M-3 M-3 M-3 M-3 Arshad Ahsan Arshad Ahsan M.Bilal M.Bilal

MECATECH MECATECH ATS ATS ATS ATS MECATECH Technofire Technofire Technofire Technofire Grace Engineers Grace Engineers

0 0 20 0 10 50 100 0 0 0 0 100 80 40

100 100 80 100 90 50 0 100 100 100 100 0 20 60

June 15 2012 June 30 2012 Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided

Subjected to Provision of service doors in ceiling Subjected to arrival of chillers & installation of Cooling Towers ATS has not provided any date of completion ATS has not provided any date of completion Incompleted Incompleted Completed Not yet started Material Awaited Material Awaited Material Awaited

Indian WC Flush Tank, Floor Drains, Padestle type wash basin still not received Work in progress

M-4

Yousuf Ali

MECATECH

May 31 2012

NO
81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107

Activity
Testing of FCUs Electrical & Control Connection of FCUS Testing & Commissioning Duct Risers Grills & Diffusers FCU Connections Duct in common areas Installation of pipe Installation of Sprinklers Installation of HRC Installation of Breeching inlet Installation of Valves PPRC + UPVC Piping Acessories Installation AHU piping Control Connections Testing & Commissioning Installation of FCUs Duct Connection of AHUs Duct Risers Installation of pipe Installation of Sprinklers Installation of HRC Installation of Breeching inlet Installation of Valves Rain water piping

Location

Level
M-4 M-4

Supervisor
Yousuf Ali

Contractor
MECATECH

Completed%
0 0

Remaining %
100 100 100 80 100 40 40 0 100 100 100 100 0 20 100 100 100 100 100 100 0 100 100 100 100 40

Completion
June 15 2012 June 15 2012 June 30 2012 Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided Not Provided June 30 2012

Remarks
Subjected to Provision of service doors in ceiling Subjected to Provision of service doors in ceiling Subjected to arrival of chillers & installation of Cooling Towers ATS has not provided any date of completion ATS has not provided any date of completion Testing of FCU connection still pending Testing and Installation still pending Completed Not yet started Material Awaited Material Awaited Material Awaited

Yousuf Ali M-4 Yousuf Ali M-4 Yousuf Ali M-4 Yousuf Ali M-4 Yousuf Ali M-4 Yousuf Ali M-4 Arshad Ahsan M-4 Arshad Ahsan M-4 Arshad Ahsan M-4 M-4 M-4 M-4 Arshad Ahsan Arshad Ahsan M.Bilal M.Bilal

MECATECH MECATECH ATS ATS ATS ATS MECATECH Technofire Technofire Technofire Technofire Nadeem Akhter & Bro Nadeem Akhter & Bro MECATECH MECATECH MECATECH MECATECH ATS ATS MECATECH TECHNOFIRE TECHNOFIRE TECHNOFIRE TECHNOFIRE Nadeem Akhter & Brother 0 20 0 60 60 100 0 0 0 0 100 80 0 0 0 0 0 0 100 0 0 0 0 60

Indian WC Flush Tank, Floor Drains, Padestle type wash basin still not received Not yet started Not yet started Not yet started Not yet started Not yet started Not yet started Completed Not yet started Material Awaited Material Awaited Material Awaited Materail arrived late

M-5 Yousuf Ali M-5 M-5 Yousuf Ali

Yousuf Ali M-5 Yousuf Ali M-5 Yousuf Ali M-5 Yousuf Ali M-5 Arshad Ahsan M-5 Arshad Ahsan M-5 Arshad Ahsan M-5 M-5 M-5 M.Bilal Arshad Ahsan Arshad Ahsan