You are on page 1of 30

NAME OF THE WORK: PROPOSED CONSTRUCTION OF RESIDENTIAL APARTMENTS "APARNA

Date: 23.05.12

SUBJECT: BOQ FOR SHELL & CORE WORKS FOR A-I BLOCKS -

Item no

Description of Item

Unit

C1.1.1
C1.1.2

SALEABLE AREA IN SFT


FOR FOUNDATIONS EXCAVATION
Excavation in all types of soil including dense soil, disintegrated/
weathered/ soft rock for footings of columns, Retaining walls, Core walls,
catchpits, Lift pits, trenches for drains, etc., by mechanical means (Using
JCB, Poclain etc.) including manual excavation for levelling, dressing the
edges, with all leads and lifts including back filling in layers of 150mm
with watering and compaction. De-watering of both ground and surface
water, removal of slurry generated while excavation and keeping the area
free of water with necessary shoring, strutting, required for keeping earth
in position etc., (Tenderer to mention the de-watering system proposed
by him using pumps of required Horse power) Rate to include disposing
the excess earth and spreading in layers to the required levels within the
site wherever specified and carting away out side the site to the
designated areas identified by the local authorities. Note: Authorised
working space shall be considered as per IS 1200. (Provision of slopes if
required for execution shall not be paid separately; depths for
excavations shall be measured for formed ground level after mass
excavation)
Earth Work Excavation For Footings
Cum
Earth Work Excavation For Retaining Wall
Cum

C1.2

Disposing of excess earth within the dist of 7Km outside the site and
levelling the same of excavated earth generated in Item no. 001 above at
Cum
area designated by the Client.

C1

C1.1

C1.3

C1.4

Block -I
Quantity
162235

5690.63

R/O

Excavation in hard rock/ boulders by Controlled Blasting using


explosives and trimming to required level for General excavation to the
required depth as specified including disposal and levelling (dooze) within
the site of 1km radius and as directed by Engineer in charge etc all
complete and as detailed in specification and conforming to safety rules
of authority from time to time and Explosives rules1940 or as amended. Cum
Mode of payment : The Contractor shall be paid only for the excavation
as per the plan area of excavation X excavation depth.
Blasting shall be carried out through licensed operator having valid
blasting licence.

Excavation in hard rock / boulders by chieseling and trimming (with


out blasting) to required level and depth as specified for General
excavation to the required depth as specified including disposal and
levelling (dooze) within the site of 1km radius and as directed by Engineer
in charge etc all complete and as detailed in specification and conforming Cum
to safety rules of authority from time to time and Explosives rules1940 or
as amended. Mode of payment : The Contractor shall be paid only for the
excavation as per the plan area of excavation X excavation depth.

7/6/2012,Shell Core Boq

R/O

All Blocks Qty


B to I
1297880

OH %

Estimated
Rate in Rs.

96.00
96.00

25%
25%

120.00
120.00

R/O

110.00

25%

137.50

247.00

25%

308.75

1,633.00

25%

45,525.03

R/O

(L+M) Rate

Amount in

Rs.

Remarks

5,463,003.21
-

2041.25

1 of 30

Item no

C1.5

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

Cum
Cum
Cum

4177.81
R/O
R/O

33,422.46
R/O
R/O

(L+M) Rate

OH %

Estimated
Rate in Rs.

25%
25%
25%

75.00
-

Amount in

Rs.

Remarks

Filling the area wherever specified with approved good quality filling
materials in plinths, area development etc. wherever specified in layers
of not exceeding 150 mm thick including breaking clods, storing,
transportation ,double handling, watering, compacting each layer with
vibratory compactor and at inaccessible places with wooden/steel
rammers to achieve 95% proctor density at optimum moisture content, all
leads and lifts, bailing/ pumping out of water to keep site dry while
backfilling; cost shall include conveyance of all materials, labour,
machinery etc. complete as directed.The rate to includes loading,
unloading, hire and fuel charges for tools and plants and other incidental
charges etc., complete.

C1.5.1
C1.5.2
C1.5.3

With excavated earth stored and available at site


With approved quality earth brought from outside.
Approved quality river sand

C1.6

Providing and laying in position 150mm thick soling with sand cushion of
50mm thick including the cost of sand cushion, Base preparation by
Mechanical compaction, using granite hand broken metal/ Rubble and Sqm
smaller pebbles for void filling, moorum for binding as directed by the
Engineer-in-charge including watering, packing, compaction etc.,

R/O

C1.7

Providing Anti termite treatment in accordance with stipulations laid down


by IS 6313 - part II by approved agency with min of 10 years of guarantee
including the cost of chemical, precautionary measures etc.complete as Sqm
specified by consultants (treatment for floor is not required and agency
shall be approved by consultants / project managers)

3564.30

C1.8

Fixing / operating / maintaining suitable rated capacity pump for


dewatering the ground water encountered during excavation. Please note
that the rate quoted should include transporting to & fro of the pump to
any where it is required and its accessories, hiring charges of the pump,
cost of operator, fuel and other consumables/power etc and all other
incidental expenses . Water to be drained to the nearest drain in the HP
vicinity for which no additional charges are payable. The contractor to Hour
visit the site, study the topography and should indicate in his quote the
methodology of dewatering proposal indicating the horse power rate,
pumping capacity and method of disposing pumped water to the nearest
drain. The pump used should atleast operate at 90% efficiency for the
respective head of water.

R/O

R/O

C1.9

Same as EXV - 1 & 2 but for slush soil including carting away from the
site and disposing it at locations approved by local authorities. The Cum
measurement shall be on Sqm basis with depth of slush varying upto 6"

R/O

R/O

C1

Total For Foundation Excavation Works..

7/6/2012,Shell Core Boq

60.00

R/O

28,514.40

2,506,684.58
-

R/O

50.00

25%

62.50

1,782,150.00

90.00

25%

112.50

9751837.79

2 of 30

Item no

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

R/O

R/O

OH %

Estimated
Rate in Rs.

2,497.00

25%

3,121.25

(L+M) Rate

Amount in

Rs.

C2

PLAIN & REINFORCED CEMENT CONCRETE WORKS

C2.1

Providing and laying Plum concrete 1: 5: 10. wherever specified using


river sand, 40mm and down size metal and boulders of 150mm
(proportion 60: 40 for concrete : boulder) including sub grade preparation, Cum
leveling, all leads and lifts, rough finishing at the top surface, curing, and
shuttering if necessary etc., complete.

C2.2

Providing and laying P.C.C. 1:4:8 of specified thickness wherever


specified using river sand, 40mm and down size metal including subgrade preparation, levelling, all leads and lifts, rough finishing at the top
surface, curing, and shuttering if necessary etc.,

C2.2.1
C2.2.1.1
C2.2.1.2
C2.2.1.3
C2.2.1.4

PODIUM
Footing
Below Plinth Beams
Below Grade Slab
For Retaining Wall

Cum
Cum
Cum
Cum

52.88
40.36
275.26

423.04
322.88
2,202.11

2,655.00
2,655.00
2,655.00
2,655.00

25%
25%
25%
25%

3,318.75
3,318.75
3,318.75
3,318.75

1,403,950.73
1,071,552.29
7,308,252.56
-

C2.2.2
C2.2.2.1
C2.2.2.2
C2.2.2.3
C2.2.2.4

TOWER
Footings
Lift Pits
Below Plinth Beams
Below Grade Slab

Cum
Cum
Cum
Cum

79.96
7.69
11.43
83.60

639.66
61.51
91.48
668.80

2,655.00
2,655.00
2,655.00
2,655.00

25%
25%
25%
25%

3,318.75
3,318.75
3,318.75
3,318.75

2,122,876.20
204,123.04
303,589.96
2,219,564.07

C2.3

C2.4

Providing and laying P.C.C. 1:3:6 of specified thickness wherever


specified using river sand, 20mm and down size metal including base
Cum
preparation, Compaction, levelling, all leads and lifts, curing and
shuttering if necessary etc., complete.
Providing and laying PCC 1:2:4 for Cills/Coping or at places wherever
specified using river sand, 20mm and downsize metal including shuttering Cum
etc., complete at all heights

C2

Total for Plain Cement Concrete Works.

C3

READY MIX CONCRETE / CONTROLLED CONCRETE

C3.1

Providing, batching, mixing, transporting through transit mixers, pumping


and laying controlled Reinforced Cement Concrete of specified grade at
all levels and heights specified below using ordinary Portland cement of
grade 53 from approved manufacturer, river sand, 20mm and down size
coarse aggregates, necessary admixtures approved by Consultants
(elkem and Conplast SP 430SRV from Fosroc or equivalent), including all
leads and lifts, pumping using line pump or boom placer, vibrating/
compaction, scaffolding wherever necessary, curing as directed,
excluding cost of shuttering and reinforcement works.

C3.1.1
C3.1.1.1
C3.1.1.2

PODIUM
Below Plinth Level
M20 Grade for Footings
M30 Grade for Pedastals

7/6/2012,Shell Core Boq

Cum
Cum

R/O

R/O

2,949.00

25%

3,686.25

R/O

R/O

3,695.00

25%

4,618.75

4,409.46

309.22
11.78

2,473.72
94.23

Remarks

14,633,908.85

3,878.00
4,537.00

25%
25%

4,847.50
5,671.25

11,991,374.73
534,401.89

3 of 30

4,537.00
3,658.00
3,658.00

25%
25%
25%

Estimated
Rate in Rs.
5,671.25
4,572.50
4,572.50

3,878.00

25%

4,847.50

653.99
1,100.17
5,953.33

4,537.00
3,658.00
3,658.00

25%
25%
25%

5,671.25
4,572.50
4,572.50

3,708,963.47
5,030,504.65
27,221,578.85

81.75
137.52
744.17

653.99
1,100.17
5,953.33
473.76

4,537.00
3,658.00
3,658.00
3,658.00

25%
25%
25%
25%

5,671.25
4,572.50
4,572.50
4,572.50

3,708,963.47
5,030,504.65
27,221,578.85
2,166,267.60

Cum
Cum
Cum
Cum
Cum
Cum
Cum

877.97
14.99
33.19
22.79
R/O
88.89
6.54

7,023.72
119.90
265.51
182.32
R/O
711.14
52.32

3,878.00
4,925.00
4,925.00
3,658.00
3,658.00
3,878.00
4,211.00

25%
25%
25%
25%
25%
25%
25%

4,847.50
6,156.25
6,156.25
4,572.50
4,572.50
4,847.50
5,263.75

34,047,493.84
738,129.45
1,634,528.70
833,650.88
3,447,270.54
275,399.40

Above Plinth level (Sub Cellar)


M40 Grade for Columns
M25 Grade for Lift Core Walls
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
M20 Grade for Staircases

Cum
Cum
Cum
Cum
Cum

91.27
14.39
79.21
47.71
7.06

730.14
115.10
633.69
381.69
56.46

4,925.00
4,211.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%

6,156.25
5,263.75
4,572.50
4,572.50
5,147.50

4,494,953.93
605,878.68
2,897,536.00
1,745,263.52
290,636.09

C3.1.6
C3.1.6.1
C3.1.6.2
C3.1.6.3
C3.1.6.4
C3.1.6.5

Cellar Floor
M40 Grade for Columns
M25 Grade for Lift Core Walls
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
M20 Grade for Staircases

Cum
Cum
Cum
Cum
Cum

110.63
17.44
79.21
47.71
7.06

885.02
139.52
633.69
381.69
56.46

4,925.00
4,211.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%

6,156.25
5,263.75
4,572.50
4,572.50
5,147.50

5,448,429.00
734,398.40
2,897,536.00
1,745,263.52
290,636.09

C3.1.7
C3.1.7.1
C3.1.7.2
C3.1.7.3
C3.1.7.4
C3.1.7.5
C3.1.7.6

Ground Floor
M40 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,925.00
4,058.00
4,118.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%
25%

6,156.25
5,072.50
5,147.50
4,572.50
4,572.50
5,147.50

2,734,541.24
524,593.89
280,161.13
3,118,783.37
1,375,421.72
98,535.50

C3.1.8

1st Floor

Item no

Description of Item

Unit

Block -I
Quantity
29.73
40.22
R/O

C3.1.1.3
C3.1.1.4
C3.1.1.5
C3.1.1.6
C3.1.1.6.1

M30 Grade for Columns


M20 Grade for Plinth Beams
M20 Grade for Grade Slab
Retaining Wall
M20 Grade For Footings

C3.1..2
C3.1..2.1
C3.1..2.2
C3.1..2.3

Above Plinth Level (Sub Cellar - 1 )


M30 Grade for Columns
M20 Grade for Waffle Beams
M20 Grade for Waffle Slab

Cum
Cum
Cum

81.75
137.52
744.17

C3.1.3
C3.1.3.1
C3.1.3.2
C3.1.3.3
C2.2.1.4

Cellar Floor
M30 Grade for Columns
M20 Grade for Waffle Beams
M20 Grade for Waffle Slab
M20 Grade Concrete for Ramp

Cum
Cum
Cum
Cum

C3.1.4
C3.1.4.1
C3.1.4.2
C3.1.4.3
C3.1.4.4
C3.1.4.5
C3.1.4.6
C3.1.4.7

TOWER
Below Plinth Level
M20 Grade for Footings
M40 Grade for Pedastals
M40 Grade for Columns
M20 Grade for Plinth Beams
M20 Grade for Grade Slab
M20 Grade for Lift Raft
M25 Grade for Lift Walls

C3.1.5
C3.1.5.1
C3.1.2.3
C3.1.2.4
C3.1.2.5
C3.1.2.6

7/6/2012,Shell Core Boq

Cum
Cum
Cum

All Blocks Qty


B to I
237.82
321.76
R/O

Cum

(L+M) Rate

OH %

Amount in

Rs.

Remarks

1,348,713.99
1,471,228.70
-

4 of 30

C3.1.8.1
C3.1.8.2
C3.1.8.3
C3.1.8.4
C3.1.8.5
C3.1.8.6

M40 Grade for Columns


M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

Block -I
Quantity
55.52
12.93
6.80
85.26
37.60
2.39

4,925.00
4,058.00
4,118.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%
25%

Estimated
Rate in Rs.
6,156.25
5,072.50
5,147.50
4,572.50
4,572.50
5,147.50

C3.1.9
C3.1.9.1
C3.1.9.2
C3.1.9.3
C3.1.9.4
C3.1.9.5
C3.1.9.6

2nd Floor
M40 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,925.00
4,058.00
4,118.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%
25%

6,156.25
5,072.50
5,147.50
4,572.50
4,572.50
5,147.50

2,734,541.24
524,593.89
280,161.13
3,118,783.37
1,375,421.72
98,535.50

C3.1.10
C3.1.10.1
C3.1.10.2
C3.1.10.3
C3.1.10.4
C3.1.10.5
C3.1.10.6

3rd Floor
M35 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,721.00
4,058.00
4,118.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%
25%

5,901.25
5,072.50
5,147.50
4,572.50
4,572.50
5,147.50

2,621,272.93
524,593.89
280,161.13
3,118,783.37
1,375,421.72
98,535.50

C3.1.11
C3.1.11.1
C3.1.11.2
C3.1.11.3
C3.1.11.4
C3.1.11.5
C3.1.11.6

4th Floor
M35 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,721.00
4,058.00
4,118.00
3,658.00
3,658.00
4,118.00

25%
25%
25%
25%
25%
25%

5,901.25
5,072.50
5,147.50
4,572.50
4,572.50
5,147.50

2,621,272.93
524,593.89
280,161.13
3,118,783.37
1,375,421.72
98,535.50

C3.1.12
C3.1.12.1
C3.1.12.2
C3.1.12.3
C3.1.12.4
C3.1.12.5
C3.1.12.6

5th Floor
M30 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,537.00
4,088.00
4,118.00
3,688.00
3,688.00
4,118.00

25%
25%
25%
25%
25%
25%

5,671.25
5,110.00
5,147.50
4,610.00
4,610.00
5,147.50

2,519,109.36
528,472.11
280,161.13
3,144,361.14
1,386,701.83
98,535.50

C3.1.13
C3.1.13.1
C3.1.13.2
C3.1.13.3
C3.1.13.4
C3.1.13.5
C3.1.13.6

6 th Floor
M30 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,537.00
4,088.00
4,118.00
3,688.00
3,688.00
4,118.00

25%
25%
25%
25%
25%
25%

5,671.25
5,110.00
5,147.50
4,610.00
4,610.00
5,147.50

2,519,109.36
528,472.11
280,161.13
3,144,361.14
1,386,701.83
98,535.50

C3.1.14
C3.1.14.1
C3.1.14.2

7th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls

Cum
Cum

55.52
12.93

444.19
103.42

4,241.00
4,088.00

25%
25%

5,301.25
5,110.00

2,354,759.27
528,472.11

Item no

Description of Item

7/6/2012,Shell Core Boq

Unit

All Blocks Qty


B to I
444.19
103.42
54.43
682.07
300.80
19.14

(L+M) Rate

OH %

Amount in

Rs.

Remarks

2,734,541.24
524,593.89
280,161.13
3,118,783.37
1,375,421.72
98,535.50

5 of 30

C3.1.14.3
C3.1.14.4
C3.1.14.5
C3.1.14.6

M20 Grade for Staircases


M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum

Block -I
Quantity
6.80
91.72
40.63
2.39

4,118.00
3,688.00
3,688.00
4,118.00

25%
25%
25%
25%

Estimated
Rate in Rs.
5,147.50
4,610.00
4,610.00
5,147.50

C3.1.15
C3.1.15.1
C3.1.15.2
C3.1.15.3
C3.1.15.4
C3.1.15.5
C3.1.15.6

8th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,241.00
4,088.00
4,118.00
3,688.00
3,688.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,110.00
5,147.50
4,610.00
4,610.00
5,147.50

2,354,759.27
528,472.11
280,161.13
3,144,361.14
1,386,701.83
98,535.50

C3.1.16
C3.1.16.1
C3.1.16.2
C3.1.16.3
C3.1.16.4
C3.1.16.5
C3.1.16.6

9th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
91.72
40.63
2.39

444.19
103.42
54.43
733.73
325.06
19.14

4,241.00
4,118.00
4,118.00
3,718.00
3,718.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,147.50
5,147.50
4,647.50
4,647.50
5,147.50

2,354,759.27
532,350.33
280,161.13
3,410,024.12
1,510,702.41
98,535.50

C3.1.17
C3.1.17.1
C3.1.17.2
C3.1.17.3
C3.1.17.4
C3.1.17.5
C3.1.17.6

10th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,241.00
4,118.00
4,118.00
3,718.00
3,718.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,147.50
5,147.50
4,647.50
4,647.50
5,147.50

2,354,759.27
532,350.33
280,161.13
3,169,938.92
1,397,981.94
98,535.50

C3.1.18
C3.1.18.1
C3.1.18.2
C3.1.18.3
C3.1.18.4
C3.1.18.5
C3.1.18.6

11th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
91.72
40.63
2.39

444.19
103.42
54.43
733.73
325.06
19.14

4,241.00
4,118.00
4,118.00
3,718.00
3,718.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,147.50
5,147.50
4,647.50
4,647.50
5,147.50

2,354,759.27
532,350.33
280,161.13
3,410,024.12
1,510,702.41
98,535.50

C3.1.19
C3.1.19.1
C3.1.19.2
C3.1.19.3
C3.1.19.4
C3.1.19.5
C3.1.19.6

12th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,241.00
4,118.00
4,118.00
3,718.00
3,718.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,147.50
5,147.50
4,647.50
4,647.50
5,147.50

2,354,759.27
532,350.33
280,161.13
3,169,938.92
1,397,981.94
98,535.50

C3.1.20
C3.1.20.1
C3.1.20.2
C3.1.20.3
C3.1.20.4

13th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs

Cum
Cum
Cum
Cum

55.52
12.93
6.80
91.72

444.19
103.42
54.43
733.73

4,241.00
4,148.00
4,118.00
3,748.00

25%
25%
25%
25%

5,301.25
5,185.00
5,147.50
4,685.00

2,354,759.27
536,228.55
280,161.13
3,437,539.11

Item no

Description of Item

7/6/2012,Shell Core Boq

Unit

All Blocks Qty


B to I
54.43
733.73
325.06
19.14

(L+M) Rate

OH %

Amount in

Rs.

Remarks

280,161.13
3,382,509.13
1,498,512.77
98,535.50

6 of 30

C3.1.20.5
C3.1.20.6

M20 Grade for Roof Beams


Lintels & Chejjas

Cum
Cum

Block -I
Quantity
40.63
2.39

3,748.00
4,118.00

25%
25%

Estimated
Rate in Rs.
4,685.00
5,147.50

C3.1.21
C3.1.21.1
C3.1.21.2
C3.1.21.3
C3.1.21.4
C3.1.21.5
C3.1.21.6

14th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,241.00
4,148.00
4,118.00
3,748.00
3,748.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,185.00
5,147.50
4,685.00
4,685.00
5,147.50

2,354,759.27
536,228.55
280,161.13
3,195,516.69
1,409,262.06
98,535.50

C3.1.22
C3.1.22.1
C3.1.22.2
C3.1.22.3
C3.1.22.4
C3.1.22.5
C3.1.22.6

15th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
91.72
40.63
2.39

444.19
103.42
54.43
733.73
325.06
19.14

4,241.00
4,148.00
4,118.00
3,748.00
3,748.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,185.00
5,147.50
4,685.00
4,685.00
5,147.50

2,354,759.27
536,228.55
280,161.13
3,437,539.11
1,522,892.05
98,535.50

C3.1.23
C3.1.23.1
C3.1.23.2
C3.1.23.3
C3.1.23.4
C3.1.23.5
C3.1.23.6

16th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,241.00
4,148.00
4,118.00
3,748.00
3,748.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,185.00
5,147.50
4,685.00
4,685.00
5,147.50

2,354,759.27
536,228.55
280,161.13
3,195,516.69
1,409,262.06
98,535.50

C3.1.24
C3.1.24.1
C3.1.24.2
C3.1.24.3
C3.1.24.4
C3.1.24.5
C3.1.24.6

17th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
91.72
40.63
2.39

444.19
103.42
54.43
733.73
325.06
19.14

4,241.00
4,178.00
4,118.00
3,778.00
3,778.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,222.50
5,147.50
4,722.50
4,722.50
5,147.50

2,354,759.27
540,106.77
280,161.13
3,465,054.09
1,535,081.68
98,535.50

C3.1.25
C3.1.25.1
C3.1.25.2
C3.1.25.3
C3.1.25.4
C3.1.25.5
C3.1.25.6

18th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
91.72
40.63
2.39

444.19
103.42
54.43
733.73
325.06
19.14

4,241.00
4,178.00
4,118.00
3,778.00
3,778.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,222.50
5,147.50
4,722.50
4,722.50
5,147.50

2,354,759.27
540,106.77
280,161.13
3,465,054.09
1,535,081.68
98,535.50

C3.1.26
C3.1.26.1
C3.1.26.2
C3.1.26.3
C3.1.26.4
C3.1.26.5
C3.1.26.6

19th Floor
M25 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for Roof Slabs
M20 Grade for Roof Beams
Lintels & Chejjas

Cum
Cum
Cum
Cum
Cum
Cum

55.52
12.93
6.80
85.26
37.60
2.39

444.19
103.42
54.43
682.07
300.80
19.14

4,241.00
4,178.00
4,118.00
3,778.00
3,778.00
4,118.00

25%
25%
25%
25%
25%
25%

5,301.25
5,222.50
5,147.50
4,722.50
4,722.50
5,147.50

2,354,759.27
540,106.77
280,161.13
3,221,094.47
1,420,542.17
98,535.50

Item no

Description of Item

7/6/2012,Shell Core Boq

Unit

All Blocks Qty


B to I
325.06
19.14

(L+M) Rate

OH %

Amount in

Rs.

Remarks

1,522,892.05
98,535.50

7 of 30

Item no

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

C3.1.27
C3.1.27.1
C3.1.27.2
C3.1.27.3
C3.1.27.4
C3.1.27.5

Above Terrace Floor


M20 Grade for Columns
M20 Grade for Lift Core Walls
M20 Grade for Staircases
M20 Grade for LMR & SHR Slab & Beams
RCC Parapet Wall at all level of specified thickness

Cum
Cum
Cum
Cum
Cum

11.10
12.93
6.80
9.12
63.83

88.84
103.42
54.43
72.94
510.61

4,241.00
4,178.00
4,118.00
3,778.00
3,778.00

25%
25%
25%
25%
25%

5,301.25
5,222.50
5,147.50
4,722.50
4,722.50

470,951.85
540,106.77
280,161.13
344,478.04
2,411,353.84

C3.1.28
C3.1.28.1
C3.1.28.2

Special ELEVATION FEATURES


Elevantion Features (Pergola Beams, Cornices, Gutters etc.)
Above Terrace Floor

Cum
Cum

125.15
31.95

1,001.23
255.64

4,118.00
4,118.00

25%
25%

5,147.50
5,147.50

5,153,825.25
1,315,886.31

C3.1.29
C3.1.29.1
C3.1.29.2

Over Head Tank


Wall -M20
Top slab -M20

Cum
Cum

11.10
9.12

88.84
72.94

4,178.00
3,778.00

25%
25%

5,222.50
4,722.50

463,955.87
344,478.04

C3.2

SITE MIX CONCRETE

C3.2.1

Providing and laying Reinforced cement concrete of the following grade


at all levels and heights using river sand, 20mm and down size coarse
aggregates, including all leads and lifts, vibrating, scaffolding wherever
necessary, curing and hacking as directed, etc., but excluding cost of
shuttering, centering etc., complete. at all levels.

C3.2.1.1
C3.2.1.1.1
C3.2.1.1.2
C3.2.1.1.3
C3.2.1.1.4
C3.2.1.1.5
C3.2.1.1.6
C3.2.1.1.7
C3.2.1.1.8
C3.2.1.1.9

For Sub Cellar Floor


Footings for columns M20
Pedestals M20
Pedestals M25
Columns M20
Columns M25
Staircase M20
Lift Core walls M20
Roof Slabs & beams M20
Ramp slabs & beams M20

Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Cum

R/O
R/O
R/O
R/O
R/O
R/O
R/O
R/O
R/O

R/O
R/O
R/O
R/O
R/O
R/O
R/O
R/O
R/O

25%
25%
25%
25%
25%
25%
25%
25%
25%

C3.2.1.2
C3.2.1.2.1
C3.2.1.2.2
C3.2.1.2.3
C3.2.1.2.4
C3.2.1.2.5
C3.2.1.2.6
C3.2.1.2.7

For Cellar Floor


Columns - M20
Columns - M25
Staircase M20
Lift Core walls M20
Roof Slabs & beams M20
Lintels M20
Chajjas M20

Cum
Cum
Cum
Cum
Cum
Cum
Cum

R/O
R/O
R/O
R/O
R/O
R/O
R/O

R/O
R/O
R/O
R/O
R/O
R/O
R/O

25%
25%
25%
25%
25%
25%
25%

C3.2.1.2
C3.2.1.2.1
C3.2.1.2.2
C3.2.1.2.3
C3.2.1.2.4
C3.2.1.2.5
C3.2.1.2.6

For Ground Floor


Columns - M20
Columns - M25
Staircase M20
Lift Core walls M20
Roof Slabs & beams M20
Lintels M20

Cum
Cum
Cum
Cum
Cum
Cum

R/O
R/O
R/O
R/O
R/O
R/O

R/O
R/O
R/O
R/O
R/O
R/O

25%
25%
25%
25%
25%
25%

7/6/2012,Shell Core Boq

Remarks

8 of 30

C3.2.1.2.7

Chajjas M20

Cum

Block -I
Quantity
R/O

C3.2.2

Over and above item no 3, extra for upper floors per floor

Cum

R/O

C3

Total for Reinforced Cement Concrete Works.

Item no

Description of Item

Unit

All Blocks Qty


B to I
R/O
R/O

(L+M) Rate

OH %

25%
25%

Estimated
Rate in Rs.
-

66,246.00

Amount in

Rs.

Remarks

323,882,826.16

0.05
C4

FORM WORK

C4.1

Providing, fabricating and erecting FORM WORK at all levels and places
wherever needed/specified as per drawing including striking with 20mm
Plastic coated, marine resistant waterproof ply/Smooth finished MS plates
with adjustable steel props of acceptable Staging system and with
sufficient bracing as approved by consultant. Cost to include designing of
proper form work and staging system to suit the requirements,
Submission of design calculations and shop drawings for approval,
sealing the joints with heavy duty brown self adhesive tape, aligning to
line and levels including M.S. Ties, PVC Spacer, Providing openings/
cutouts/ pockets, applying deshuttering chemical, Deshuttering as
approved by the consultant etc., complete at all levels, double/triple
heights and profiles.

C4.1.1
C4.1.1.1
C4.1.1.2
C4.1.1.3
C4.1.1.4

PODIUM
Below Plinth Level
Footings
Pedastals
Columns
PlinthBeams

Sqm
Sqm
Sqm
Sqm

240.10
64.62
205.20
541.87

1,920.78
516.96
1,641.60
4,334.97

199.06
199.06
199.06
199.06

25%
25%
25%
25%

248.83
248.83
248.83
248.83

477,939.08
128,632.57
408,471.12
1,078,650.10

C4.1..2
C4.1..2.1
C4.1..2.2
C4.1..2.3

AbovePlinthLevel(SubCellar-1)
Columns
WaffleBeams
WaffleSlab

Sqm
Sqm
Sqm

564.30
366.72
2168.28

4,514.40
2,933.77
17,346.23

199.06
199.06
700.00

25%
25%
25%

248.83
248.83
875.00

1,123,295.58
729,996.18
15,177,948.24

C4.1.3
C4.1.3.1
C4.1.3.2
C4.1.3.3
C4.1.3.5

CellarFloor
Columns
WaffleBeams
WaffleSlab
Ramp

Sqm
Sqm
Sqm
Sqm

564.30
366.72
2168.28

4,514.40
2,933.77
17,346.23
3,158.40

199.06
199.06
700.00
199.06

25%
25%
25%
25%

248.83
248.83
875.00
248.83

1,123,295.58
729,996.18
15,177,948.24
785,888.88

C4.1.4
C4.1.4.1
C4.1.4.2
C4.1.4.3
C4.1.4.4
C4.1.4.5
C4.1.4.6

TOWER
BelowPlinthLevel
Footings
Pedastals
Columns
PlinthBeams
Lift Raft
LiftWalls

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

518.34
78.23
266.62
153.52
76.44
66.60

4,146.76
625.87
2,132.93
1,228.18
611.52
532.80

199.06
199.06
199.06
199.06
199.06
199.06

25%
25%
25%
25%
25%
25%

248.83
248.83
248.83
248.83
248.83
248.83

1,031,816.56
155,732.60
530,725.81
305,600.89
152,161.46
132,573.96

C4.1.5
C4.1.5.1
C4.1.2.3
C4.1.2.4

AbovePlinthlevel(SubCellar)
Columns
LiftCoreWalls
RoofSlabs

Sqm
Sqm
Sqm

733.19
146.52
528.07

5,865.55
1,172.16
4,224.58

199.06
199.06
199.06

25%
25%
25%

248.83
248.83
248.83

1,459,495.98
291,662.71
1,051,181.91

7/6/2012,Shell Core Boq

9 of 30

C4.1.2.5
C4.1.2.6

RoofBeams
Staircases

Sqm
Sqm

Block -I
Quantity
332.44
54.38

199.06
199.06

25%
25%

Estimated
Rate in Rs.
248.83
248.83

C4.1.6
C4.1.6.1
C4.1.6.2
C4.1.6.3
C4.1.6.4
C4.1.6.5

CellarFloor
Columns
LiftCoreWalls
RoofSlabs
RoofBeams
Staircases

Sqm
Sqm
Sqm
Sqm
Sqm

888.72
177.60
528.07
332.44
54.38

7,109.76
1,420.80
4,224.58
2,659.55
435.02

199.06
199.06
199.06
199.06
199.06

25%
25%
25%
25%
25%
25%

248.83
248.83
248.83
248.83
248.83

1,769,086.03
353,530.56
1,051,181.91
661,763.28
108,242.86

C4.1.7
C4.1.7.1
C4.1.7.2
C4.1.7.3
C4.1.7.4
C4.1.7.5
C4.1.7.6

Ground Floor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
27.60

5,038.63
1,053.17
414.67
5,301.48
3,078.35
220.80

199.06
199.06
199.06
199.06
199.06
199.06

25%
25%
25%
25%
25%
25%

248.83
248.83
248.83
248.83
248.83
248.83

1,253,737.21
262,054.53
103,179.37
1,319,140.76
765,970.44
54,940.56

C4.1.8
C4.1.8.1
C4.1.8.2
C4.1.8.3
C4.1.8.4
C4.1.8.5
C4.1.8.6

1stFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

215.20
215.20
215.20
215.20
215.20
215.20

25%
25%
25%
25%
25%
25%

269.00
269.00
269.00
269.00
269.00
269.00

1,355,391.58
283,302.19
111,545.26
1,426,098.12
828,076.15
68,657.41

C4.1.9
C4.1.9.1
C4.1.9.2
C4.1.9.3
C4.1.9.4
C4.1.9.5
C4.1.9.6

2ndFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

215.20
215.20
215.20
215.20
215.20
215.20

25%
25%
25%
25%
25%
25%

269.00
269.00
269.00
269.00
269.00
269.00

1,355,391.58
283,302.19
111,545.26
1,426,098.12
828,076.15
68,657.41

C4.1.10
C4.1.10.1
C4.1.10.2
C4.1.10.3
C4.1.10.4
C4.1.10.5
C4.1.10.6

3rdFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

223.27
223.27
223.27
223.27
223.27
223.27

25%
25%
25%
25%
25%
25%

279.09
279.09
279.09
279.09
279.09
279.09

1,406,218.76
293,926.02
115,728.21
1,479,576.80
859,129.01
71,232.06

C4.1.11
C4.1.11.1
C4.1.11.2
C4.1.11.3
C4.1.11.4
C4.1.11.5
C4.1.11.6

4thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

231.34
231.34
231.34
231.34
231.34
231.34

25%
25%
25%
25%
25%
25%

289.18
289.18
289.18
289.18
289.18
289.18

1,457,045.95
304,549.86
119,911.16
1,533,055.48
890,181.86
73,806.71

Item no

Description of Item

7/6/2012,Shell Core Boq

Unit

All Blocks Qty


B to I
2,659.55
435.02

(L+M) Rate

OH %

Amount in

Rs.

Remarks

661,763.28
108,242.86

10 of 30

Item no

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

C4.1.12
C4.1.12.1
C4.1.12.2
C4.1.12.3
C4.1.12.4
C4.1.12.5
C4.1.12.6

5thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

239.41
239.41
239.41
239.41
239.41
239.41

25%
25%
25%
25%
25%
25%

299.26
299.26
299.26
299.26
299.26
299.26

1,507,873.13
315,173.69
124,094.10
1,586,534.16
921,234.72
76,381.37

C4.1.13
C4.1.13.1
C4.1.13.2
C4.1.13.3
C4.1.13.4
C4.1.13.5
C4.1.13.6

6thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

247.48
247.48
247.48
247.48
247.48
247.48

25%
25%
25%
25%
25%
25%

309.35
309.35
309.35
309.35
309.35
309.35

1,558,700.31
325,797.52
128,277.05
1,640,012.84
952,287.57
78,956.02

C4.1.14
C4.1.14.1
C4.1.14.2
C4.1.14.3
C4.1.14.4
C4.1.14.5
C4.1.14.6

7thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
721.04
419.17
31.90

5,038.63
1,053.17
414.67
5,768.35
3,353.39
255.23

255.55
255.55
255.55
255.55
255.55
255.55

25%
25%
25%
25%
25%
25%

319.44
319.44
319.44
319.44
319.44
319.44

1,609,527.50
336,421.35
132,460.00
1,842,627.94
1,071,199.80
81,530.67

C4.1.15
C4.1.15.1
C4.1.15.2
C4.1.15.3
C4.1.15.4
C4.1.15.5
C4.1.15.6

8thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

263.62
263.62
263.62
263.62
263.62
263.62

25%
25%
25%
25%
25%
25%

329.53
329.53
329.53
329.53
329.53
329.53

1,660,354.68
347,045.19
136,642.95
1,746,970.20
1,014,393.28
84,105.32

C4.1.16
C4.1.16.1
C4.1.16.2
C4.1.16.3
C4.1.16.4
C4.1.16.5
C4.1.16.6

9thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
721.04
419.17
31.90

5,038.63
1,053.17
414.67
5,768.35
3,353.39
255.23

271.69
271.69
271.69
271.69
271.69
271.69

25%
25%
25%
25%
25%
25%

339.61
339.61
339.61
339.61
339.61
339.61

1,711,181.87
357,669.02
140,825.89
1,959,004.44
1,138,854.52
86,679.98

C4.1.17
C4.1.17.1
C4.1.17.2
C4.1.17.3
C4.1.17.4
C4.1.17.5
C4.1.17.6

10thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

279.76
279.76
279.76
279.76
279.76
279.76

25%
25%
25%
25%
25%
25%

349.70
349.70
349.70
349.70
349.70
349.70

1,762,009.05
368,292.85
145,008.84
1,853,927.56
1,076,499.00
89,254.63

C4.1.18
C4.1.18.1

11thFloor
Columns

Sqm

629.83

5,038.63

287.83

25%

359.79

1,812,836.24

7/6/2012,Shell Core Boq

Remarks

11 of 30

C4.1.18.2
C4.1.18.3
C4.1.18.4
C4.1.18.5
C4.1.18.6

LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm

Block -I
Quantity
131.65
51.83
721.04
419.17
31.90

287.83
287.83
287.83
287.83
287.83

25%
25%
25%
25%
25%

Estimated
Rate in Rs.
359.79
359.79
359.79
359.79
359.79

C4.1.19
C4.1.19.1
C4.1.19.2
C4.1.19.3
C4.1.19.4
C4.1.19.5
C4.1.19.6

12thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

295.90
295.90
295.90
295.90
295.90
295.90

25%
25%
25%
25%
25%
25%

369.88
369.88
369.88
369.88
369.88
369.88

1,863,663.42
389,540.51
153,374.73
1,960,884.92
1,138,604.71
94,403.94

C4.1.20
C4.1.20.1
C4.1.20.2
C4.1.20.3
C4.1.20.4
C4.1.20.5
C4.1.20.6

13thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
721.04
419.17
31.90

5,038.63
1,053.17
414.67
5,768.35
3,353.39
255.23

303.97
303.97
303.97
303.97
303.97
303.97

25%
25%
25%
25%
25%
25%

379.96
379.96
379.96
379.96
379.96
379.96

1,914,490.60
400,164.35
157,557.68
2,191,757.45
1,274,163.97
96,978.59

C4.1.21
C4.1.21.1
C4.1.21.2
C4.1.21.3
C4.1.21.4
C4.1.21.5
C4.1.21.6

14thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

312.04
312.04
312.04
312.04
312.04
312.04

25%
25%
25%
25%
25%
25%

390.05
390.05
390.05
390.05
390.05
390.05

1,965,317.79
410,788.18
161,740.63
2,067,842.27
1,200,710.42
99,553.24

C4.1.22
C4.1.22.1
C4.1.22.2
C4.1.22.3
C4.1.22.4
C4.1.22.5
C4.1.22.6

15thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
721.04
419.17
31.90

5,038.63
1,053.17
414.67
5,768.35
3,353.39
255.23

320.11
320.11
320.11
320.11
320.11
320.11

25%
25%
25%
25%
25%
25%

400.14
400.14
400.14
400.14
400.14
400.14

2,016,144.97
421,412.01
165,923.58
2,308,133.95
1,341,818.69
102,127.89

C4.1.23
C4.1.23.1
C4.1.23.2
C4.1.23.3
C4.1.23.4
C4.1.23.5
C4.1.23.6

16thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
662.69
384.79
31.90

5,038.63
1,053.17
414.67
5,301.48
3,078.35
255.23

328.18
328.18
328.18
328.18
328.18
328.18

25%
25%
25%
25%
25%
25%

410.23
410.23
410.23
410.23
410.23
410.23

2,066,972.16
432,035.84
170,106.52
2,174,799.63
1,262,816.13
104,702.55

C4.1.24
C4.1.24.1
C4.1.24.2
C4.1.24.3

17thFloor
Columns
LiftCoreWalls
Staircases

Sqm
Sqm
Sqm

629.83
131.65
51.83

5,038.63
1,053.17
414.67

336.25
336.25
336.25

25%
25%
25%

420.31
420.31
420.31

2,117,799.34
442,659.68
174,289.47

Item no

Description of Item

7/6/2012,Shell Core Boq

Unit

All Blocks Qty


B to I
1,053.17
414.67
5,768.35
3,353.39
255.23

(L+M) Rate

OH %

Amount in

Rs.

Remarks

378,916.68
149,191.79
2,075,380.95
1,206,509.24
91,829.28

12 of 30

C4.1.24.4
C4.1.24.5
C4.1.24.6

RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm

Block -I
Quantity
721.04
419.17
31.90

336.25
336.25
336.25

25%
25%
25%

Estimated
Rate in Rs.
420.31
420.31
420.31

C4.1.25
C4.1.25.1
C4.1.25.2
C4.1.25.3
C4.1.25.4
C4.1.25.5
C4.1.25.6

18thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
721.04
419.17
31.90

5,038.63
1,053.17
414.67
5,768.35
3,353.39
255.23

344.32
344.32
344.32
344.32
344.32
344.32

25%
25%
25%
25%
25%
25%

430.40
430.40
430.40
430.40
430.40
430.40

2,168,626.52
453,283.51
178,472.42
2,482,698.70
1,443,300.78
109,851.85

C4.1.26
C4.1.26.1
C4.1.26.2
C4.1.26.3
C4.1.26.4
C4.1.26.5
C4.1.26.6

19thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

629.83
131.65
51.83
721.04
419.17
31.90

5,038.63
1,053.17
414.67
5,768.35
3,353.39
255.23

352.39
352.39
352.39
352.39
352.39
352.39

25%
25%
25%
25%
25%
25%

440.49
440.49
440.49
440.49
440.49
440.49

2,219,453.71
463,907.34
182,655.37
2,540,886.95
1,477,128.14
112,426.51

C4.1.27
C4.1.27.1
C4.1.27.2
C4.1.27.3
C4.1.27.4
C4.1.27.5

Above Terrace Floor


Columns
Lift Core Walls
Staircases
LMR & SHR Slab & Beams
RCC Parapet Wall at all level of specified thickness

Sqm
Sqm
Sqm
Sqm
Sqm

125.97
131.65
51.83
86.39
638.26

1007.72608
1053.168
414.6664
691.12
5106.096

360.46
360.46
360.46
360.46
360.46

25%
25%
25%
25%
25%

450.58
450.58
450.58
450.58
450.58

454,056.18
474,531.17
186,838.31
311,401.39
2,300,679.21

C4.1.28
C4.1.28.1
C4.1.28.2

Special ELEVATION FEATURES


Elevantion Features (Pergola Beams, Cornices, Gutters etc.)
Above Terrace Floor

Sqm
Sqm

375.46
95.86

3003.6864
766.908

360.46
360.46

25%
25%

450.58
450.58

1,353,386.00
345,549.57

C4.1.29
C4.1.29.1
C4.1.29.2

Over Head Tank


Wall
Top slab

Sqm
Sqm

125.97
86.39

1,007.73
691.12

360.46
360.46

25%
25%

450.58
450.58

454,056.18
311,401.39

C4

Total for Formworks.

C5

STEEL WORKS
REINFORCEMENT STEEL.

Item no

C5.1

Description of Item

Unit

All Blocks Qty


B to I
5,768.35
3,353.39
255.23

423,119.80

(L+M) Rate

OH %

Amount in

Rs.

Remarks

2,424,510.45
1,409,473.42
107,277.20

159,767,955.80

Providing, straightening, cutting, bending and tying in position


reinforcement for RCC work with high yield strength ribbed cold twisted
tor steel (HSD) bar of various diameters and grade of steel as specified
below conforming to IS or equivalent BS specification including cutting
and waste, bending, hoisting, fabricating and placing in position according
to drawings and binding the reinforcement with galvanised annealed
binding wire of double fold of 18 gauge and providing PVC cover blocks
for placing the reinforcements in position and for maintaining the cover
specified and/or according to relevant IS or equivalent BS code.

7/6/2012,Shell Core Boq

13 of 30

Item no

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

Remarks

Note : Unless noted otherwise the measurements in accordance with IS


1200 or equivalent BS. However reinforcement shall be measured only in
lengths of bars as actually placed in position on standard weight basis, no
allowance being made in the weight for rolling margin. Authorised laps
and splices only will be measured. Chairs of any shape & profile, Spacer
bar of any shape & profile, cover block, wastage and binding wire will not
be measured and shall be included in the quoted rates.Quoted rate shall
be deemed to have considered the above stipulation.Quoted rate to
include lead, lift, placing at all levels and as directed.
C5.1.1
C5.1.1.1
C5.1.1.2
C5.1.1.3
C5.1.1.4
C5.1.1.5

PODIUM
Below Plinth Level
Footings
Pedastals
Columns
PlinthBeams
Retaining Wall Raft & Core Walls

MT
MT
MT
MT
MT

15.38

C5.1..2
C5.1..2.1
C5.1..2.2
C5.1..2.3

AbovePlinthLevel(SubCellar-1)
Columns
WaffleBeams
WaffleSlab

MT
MT
MT

C5.1.3
C5.1.3.1
C5.1.3.2
C5.1.3.3
C5.1.3.4

CellarFloor
Columns
WaffleBeams
WaffleSlab
Ramps

C5.1.4
C5.1.4.1
C5.1.4.2
C5.1.4.3
C5.1.4.4
C5.1.4.5
C5.1.4.6

123.02
47.20
R/O

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%

55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
-

12.92

103.36
-

48,261.00
48,261.00
48,261.00

15%
15%
15%

MT
MT
MT
MT

14.93

119.44
140.00

48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%

TOWER & Podium


BelowPlinthLevel
Footings
Pedastals
Columns
PlinthBeams
LiftShaft
LiftWalls

55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
-

MT
MT
MT
MT
MT
MT

32.66
3.89
3.72
2.47
2.97
1.64

261.27
31.15
29.76
19.76
23.76
13.12

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.5
C5.1.5.1
C5.1.2.3
C5.1.2.4
C5.1.2.5
C5.1.2.6

AbovePlinthlevel(SubCellar)
Columns
LiftCoreWalls
RoofSlabs
RoofBeams
Staircases

MT
MT
MT
MT
MT

17.01
1.64
3.71
32.89
0.54

136.08
13.12
29.68
263.12
4.32

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%

C5.1.6
C5.1.6.1
C5.1.6.2
C5.1.6.3
C5.1.6.4
C5.1.6.5

CellarFloor
Columns
LiftCoreWalls
RoofSlabs
RoofBeams
Staircases

MT
MT
MT
MT
MT

23.72
1.64
4.32
47.60
0.54

189.76
13.12
34.56
380.80
4.32

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%

7/6/2012,Shell Core Boq

5.90

55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00

6,827,832.00
2,619,600.00
5,736,480.00
6,628,920.00
7,770,000.00
14,500,596.00
1,728,936.00
1,651,680.00
1,096,680.00
1,318,680.00
728,160.00
7,552,440.00
728,160.00
1,647,240.00
14,603,160.00
239,760.00
10,531,680.00
728,160.00
1,918,080.00
21,134,400.00
239,760.00

14 of 30

Item no

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

C5.1.7
C5.1.7.1
C5.1.7.2
C5.1.7.3
C5.1.7.4
C5.1.7.5
C5.1.7.6

TOWER
Ground Floor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
7.54
105.28
1.05

170.96
11.20
3.12
60.32
842.24
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.8
C5.1.8.1
C5.1.8.2
C5.1.8.3
C5.1.8.4
C5.1.8.5
C5.1.8.6

1stFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
4.17
5.93
1.05

170.96
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.9
C5.1.9.1
C5.1.9.2
C5.1.9.3
C5.1.9.4
C5.1.9.5
C5.1.9.6

2ndFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
4.17
5.93
1.05

170.96
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.10
C5.1.10.1
C5.1.10.2
C5.1.10.3
C5.1.10.4
C5.1.10.5
C5.1.10.6

3rdFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
4.17
5.93
1.05

170.96
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.11
C5.1.11.1
C5.1.11.2
C5.1.11.3
C5.1.11.4
C5.1.11.5
C5.1.11.6

4thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
4.17
5.93
1.05

170.96
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.12
C5.1.12.1
C5.1.12.2
C5.1.12.3
C5.1.12.4
C5.1.12.5
C5.1.12.6

5thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
4.17
5.93
1.05

170.96
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

7/6/2012,Shell Core Boq

Estimated
Rate in Rs.
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
-

Amount in

Rs.

Remarks

9,488,280.00
621,600.00
173,160.00
3,347,760.00
46,744,320.00
467,443.20
9,488,280.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
9,488,280.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
9,488,280.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
9,488,280.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
9,488,280.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
-

15 of 30

Item no

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

C5.1.13
C5.1.13.1
C5.1.13.2
C5.1.13.3
C5.1.13.4
C5.1.13.5
C5.1.13.6

6thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

21.37
1.40
0.39
4.17
5.93
1.05

170.96
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.14
C5.1.14.1
C5.1.14.2
C5.1.14.3
C5.1.14.4
C5.1.14.5
C5.1.14.6

7thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

19.31
1.40
0.39
4.17
5.93
1.05

154.48
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.15
C5.1.15.1
C5.1.15.2
C5.1.15.3
C5.1.15.4
C5.1.15.5
C5.1.15.6

8thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

19.31
1.40
0.39
4.17
5.93
1.05

154.48
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.16
C5.1.16.1
C5.1.16.2
C5.1.16.3
C5.1.16.4
C5.1.16.5
C5.1.16.6

9thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintel&Chejjasatalllevels

MT
MT
MT
MT
MT
MT

17.25
1.40
0.39
4.17
5.93
1.05

138.00
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.17
C5.1.17.1
C5.1.17.2
C5.1.17.3
C5.1.17.4
C5.1.17.5
C5.1.17.6

10thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

17.25
1.40
0.39
4.17
5.93
1.05

138.00
11.20
3.12
33.36
47.44
8.42
-

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%
15%

C5.1.18
C5.1.18.1
C5.1.18.2
C5.1.18.3
C5.1.18.4
C5.1.18.5
C5.1.18.6

11thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

15.89
1.40
0.39
4.17
5.93
1.05

127.12
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.19
C5.1.19.1

12thFloor
Columns

MT

15.89

127.12

48,261.00

15%

7/6/2012,Shell Core Boq

Estimated
Rate in Rs.
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00

Amount in

Rs.

Remarks

9,488,280.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
8,573,640.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
8,573,640.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
7,659,000.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
7,659,000.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
7,055,160.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
7,055,160.00

16 of 30

C5.1.19.2
C5.1.19.3
C5.1.19.4
C5.1.19.5
C5.1.19.6

LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT

Block -I
Quantity
1.40
0.39
4.17
5.93
1.05

C5.1.20
C5.1.20.1
C5.1.20.2
C5.1.20.3
C5.1.20.4
C5.1.20.5
C5.1.20.6

13thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

13.05
1.40
0.39
4.17
5.93
1.05

C5.1.21
C5.1.21.1
C5.1.21.2
C5.1.21.3
C5.1.21.4
C5.1.21.5
C5.1.21.6

14thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

C5.1.22
C5.1.22.1
C5.1.22.2
C5.1.22.3
C5.1.22.4
C5.1.22.5
C5.1.22.6

15thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

C5.1.23
C5.1.23.1
C5.1.23.2
C5.1.23.3
C5.1.23.4
C5.1.23.5
C5.1.23.6

Item no

Description of Item

Unit

All Blocks Qty


B to I
11.20
3.12
33.36
47.44
8.42

(L+M) Rate

OH %

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%

104.40
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

13.05
1.40
0.39
4.17
5.93
1.05

104.40
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

MT
MT
MT
MT
MT
MT

11.32
1.40
0.39
4.17
5.93
1.05

90.56
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

16thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

11.32
1.40
0.39
4.17
5.93
1.05

90.56
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.24
C5.1.24.1
C5.1.24.2
C5.1.24.3
C5.1.24.4
C5.1.24.5
C5.1.24.6

17thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

10.28
1.40
0.39
4.17
5.93
1.05

82.24
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

C5.1.25
C5.1.25.1
C5.1.25.2
C5.1.25.3

18thFloor
Columns
LiftCoreWalls
Staircases

MT
MT
MT

10.28
1.40
0.39

82.24
11.20
3.12

48,261.00
48,261.00
48,261.00

15%
15%
15%

7/6/2012,Shell Core Boq

Estimated
Rate in Rs.
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00

Amount in

Rs.

Remarks

621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
5,794,200.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
5,794,200.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
5,026,080.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
5,026,080.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
4,564,320.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
4,564,320.00
621,600.00
173,160.00

17 of 30

C5.1.25.4
C5.1.25.5
C5.1.25.6

RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT

Block -I
Quantity
4.17
5.93
1.05

C5.1.26
C5.1.26.1
C5.1.26.2
C5.1.26.3
C5.1.26.4
C5.1.26.5
C5.1.26.6

19thFloor
Columns
LiftCoreWalls
Staircases
RoofSlabs
RoofBeams
Lintels&Chejjas

MT
MT
MT
MT
MT
MT

9.83
1.40
0.39
4.17
5.93
1.05

C5.1.27
C5.1.27.1
C5.1.27.2
C5.1.27.3
C5.1.27.4
C5.1.27.5

Above Terrace Floor


Columns
Lift Core Walls
Staircases
LMR & SHR Slab & Beams
RCC Parapet Wall at all level of specified thickness

MT
MT
MT
MT
MT

1.40
0.39
5.93
3.83

C4.1.28
C4.1.28.1
C4.1.28.2

Special ELEVATION FEATURES


Elevantion Features (Pergola Beams, Cornices, Gutters etc.)
Above Terrace Floor

Sqm
Sqm

7.51
3.20

C5.1.15
C5.1.15.1
C5.1.15.2

Over Head Tank


Wall
Top slab

MT
MT

5.93
4.17

C5.1.4

Providing, straightening, cutting and tying in position high strength weld


mesh reinforcement of grade Fe 480 and 6mm thick @ 150mm c/c
(weight @ 2.966 Kg/Sqm) with an overlap of 75 mm (confirming to IS
432/1982 Part-1) for slab including cutting, placing in position according
to drawings.

C5

Total for Steel Works.

Item no

Description of Item

Unit

All Blocks Qty


B to I
33.36
47.44
8.42

(L+M) Rate

OH %

48,261.00
48,261.00
48,261.00

15%
15%
15%

78.64
11.20
3.12
33.36
47.44
8.42

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%
15%

11.20
3.12
47.44
30.64

48,261.00
48,261.00
48,261.00
48,261.00
48,261.00

15%
15%
15%
15%
15%

48,261.00
48,261.00

15%
15%

48,261.00
48,261.00

15%
15%

60.073728
25.5636

47.44
33.36

MT

Estimated
Rate in Rs.
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00
55,500.00

55,500.00
55,500.00
55,500.00
55,500.00
-

Amount in

Rs.

Remarks

1,851,480.00
2,632,920.00
467,443.20
4,364,520.00
621,600.00
173,160.00
1,851,480.00
2,632,920.00
467,443.20
621,600.00
173,160.00
2,632,920.00
1,700,329.97

3,334,091.90
1,418,779.80
2,632,920.00
1,851,480.00
-

R/O

7,801.13

432,962,709.67

6.01
C6
C6.1

STRUCTURE STEEL & METAL WORKS


STRUCTURAL STEEL

C6.1.1

Providing, fabricating and erecting Structural steel members in position at


all levels and at all heights as specified Detailed in the drawings made out
of standard MS sections as Per Direction of Engineer incharge.

MT

2.00

16.00

65,217.50

15%

75,000.00

1,200,000.00

C6.1.2

Providing, Fabricating and erecting in position structural steel conforming


to IS 800 as corner angles(50x50x6MM) for columns etc complete

MT

2.00

16.00

65,217.50

15%

75,000.00

1,200,000.00

C6.1.3

Providing and fixing in position M.S.chequered plate 5mm thick with


necessary supports such as M.S. angles / M.S. flats et complete

MT

C6.1.4
C6.1.4.1
C6.1.4.2

Providing and anchoring in position high strength anchor bolts.


25mm dia (heavy duty)
20mm dia (heavy duty)

7/6/2012,Shell Core Boq

Nos
Nos

R/O
R/O

R/O
R/O

15%
15%

18 of 30

C6.1.4.3

16mm dia (heavy duty)

Nos

Block -I
Quantity
R/O

C6.1.5

Providing, fabricating and installing inserts in concrete in the form of M.S.


angles, flats, plates, holding bolts, angle frames, for edge protection
angles in driveways, for fixing of lintels etc. (Note: the cost of embeded
bars / lugs shall be measured separately for payment)

MT

R/O

Item no

C6.2

C6.2.1

C6.2.1.1

C6.3

C6.3.1

C6.4

C6.4.1

C6.5

C6.5.1

Description of Item

Unit

All Blocks Qty


B to I
R/O

R/O

(L+M) Rate

OH %

15%

Estimated
Rate in Rs.
-

Amount in

Rs.

Remarks

15%

METAL WORK
Fabricating, supplying and installing in position Railing to Stair cases,
etc. consisting of MS pipe handrail of 50mm dia. welded to vertical
supports using MS square and MS flat sections of approximately 14 kgs
per Rmt as per detailed drawing with necessary cutting, welding,
grinding, and one metal primer with necessary putty as per the
Specifications & as directed by Engineer- in- Charge. All MS sections to
be TATA MEDIUM/ Equivalent class.
For All floors

Rmt

300.96

2,407.68

994.00

10%

1,093.40

2,632,557.31

Rmt

936.12

7,488.92

852.00

10%

937.20

7,018,615.82

Rmt

152.40

1,219.20

450.00

10%

495.00

603,504.00

Rmt

R/O

640.00

10%

704.00

Fabricating, supplying and installing in position Railing to Balconies/ Sit


outs , etc. consisting of MS pipe handrail of 50mm dia. welded to vertical
supports using MS box section 25mm x 25mm and MS flat sections of
approximately 12 kgs per Rmt as per detailed drawing with necessary
cutting, welding, grinding, and one coat of metal primer with necessary
putty as per the Specifications & as directed by Engineer- in- Charge. All
MS sections to be TATA MEDIUM / Equivalent class.
For All floors
Fabricating, supplying and installing in position Railing to Utilities etc.
consisting of MS pipe handrail of 50mm dia. welded to vertical supports
using MS box section 25mm x 25mm and MS flat sections of
approximately 5 kgs per Rmt as per detailed drawing with necessary
cutting, welding, grinding, and one coat of metal primer with necessary
putty as per the Specifications & as directed by Engineer- in- Charge. All
MS sections to be TATA MEDIUM/ Equivalent class.
For All floors
Fabricating, supplying and installing in position Railing to Corridors ,
etc. consisting of MS pipe handrail of 50mm dia. welded to vertical
supports using MS box section 25mm x25mm and MS flat sections of
approximately 5 kgs per Rmt as per detailed drawing with necessary
cutting, welding, grinding, and one coat of metal primer with necessary
putty as per the Specifications & as directed by Engineer- in- Charge. All
MS sections to be TATA MEDIUM/ Equivalent class.
For All floors

7/6/2012,Shell Core Boq

R/O

19 of 30

Description of Item

Unit

Block -I
Quantity

Providing and fixing MS door for service ducts/ other locations as called
for, using MS sections and angles and shutters with hinges and locking
arrangements and with necessary materials as per design and drawings
including fixtures and fitting charges fitting with CC 1:2:4 and one coat of
metal primer complete with all lead and lift and as directed by the
architect.
For Fire Duct Doors
For Communication/Electrical Duct Doors
For utility doors
For FRD doors

No's
No's
Nos
Nos

22.00
88.00
80.00
20.00

Item no

C6.6

C6.6.1
C6.6.2
C6.6.3
C6.6.4

C6.7

Proving and fixing MS grating in lengths not exceeding 1.50 Mts using
removable frame in ISA 75 x 75 x 10 mm with 20mm round bars spaced
at 50mm c/c and braced 25mm MS round bars 200 c/c over external
Sqm
framework of ISA 75 x 75 x 10 mm grouted to masonry in CC 1:2:4, for
drains 450mm wide .The rate quoted shall include the cost of one coat of
metal primer.

C6.8

Providing and fixing MS Louveres at locations indicated in the drawings


or as directed to fix at all heights and levels, using necessary fastners
finished neat as per the drawings to the satisfaction of engineer incharge.
for External Shafts

C6.8.1

External Shafts

C6.9

Fabricating, supplying and fixing in position security grills to fabricated


out of 10mm MS square bars of MS bars with 6mm X 20mm MS Flat
outer frame cut to precise lengths including welding and grinding as
approved( Approximately 7.50 kgs / Sqm as per the detailed drawing) .
Allow for anchoring to side supports in approved manner, and including
one coat of metal primer with necessary putty as per the Specifications &
as directed by Engineer-in Charge. All MS sections to be TATA MEDIUM
/ Equivalent class.

C6.9.1
C6.9.2

Windows All Floors


Sitout For Ground And 1st Floor

C6

Total for Metal Works.

C7

MASONRY

C7.1

Providing
and
constructing
Size
stone
masonry
for
foundation/Superstructure using size stones in CM 1:6 with necessary
quoin, through bond stone and Header stone at regular intervals including
Cum
dressing the stone and edge poking by chissel/hammer true to the
required shape & size, curing, scaffolding, racking out joints, staging,
leads and lifts at all levels

7/6/2012,Shell Core Boq

All Blocks Qty


B to I

176.00
704.00
640.00
160.00

(L+M) Rate

6,050.00
4,850.00
4,850.00
17,727.27

OH %

Estimated
Rate in Rs.

10%
10%
10%
10%

6,655.00
5,335.00
5,335.00
19,500.00

R/O

R/O

10%

Sqm

R/O

R/O

10%

Sqm
Sqm

1278.84
109.70

10,230.72
877.60
#VALUE!

681.82
681.82

10%
10%

750.00
750.00

1,510.44

Amount in

Rs.

Remarks

1,171,280.00
3,755,840.00
3,414,400.00
3,120,000.00

7,673,040.00
658,199.10
32,447,436.24

0.01

R/O

R/O

2,405.00

25%

3,006.25

20 of 30

Item no

C7.2

C7.2.1
C7.2.2
C7.2.3
C7.2.4
C7.2.5
C7.2.6
C7.2.7
C7.2.8
C7.2.9
C7.2.10
C7.2.11
C7.2.12
C7.2.13
C7.2.14
C7.2.15
C7.2.16
C7.2.17
C7.2.18
C7.2.19
C7.2.20
C7.2.21
C7.2.22
C7.2.23

Description of Item

Unit

Providing and constructing 200mm thick Solid Concrete block work at


all levels in walls, piers and architectural features using approved solid
blocks of strength 35kg/sqcm in cement mortar 1:6 with minimum
crushing strength of 35kg/sq.cm. including curing, scaffolding, staging,
leads and lifts etc. complete.
Sub-Cellar
Cellar Floor
Ground fLOOR
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor
Parapet Wall & Terrace Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

Block -I
Quantity

89.60
89.60
353.19
359.83
359.83
359.83
359.83
359.83
359.83
366.99
359.83
366.99
359.83
366.99
359.83
366.99
359.83
366.99
359.83
366.99
366.99
359.83

All Blocks Qty


B to I

716.82
716.82
2,825.51
2,878.67
2,878.67
2,878.67
2,878.67
2,878.67
2,878.67
2,935.95
2,878.67
2,935.95
2,878.67
2,935.95
2,878.67
2,935.95
2,878.67
2,935.95
2,878.67
2,935.95
2,935.95
2,878.67
-

OH %

Estimated
Rate in Rs.

591.00
591.00
591.00
591.00
591.00
591.00
591.00
601.00
601.00
601.00
601.00
611.00
611.00
611.00
611.00
621.00
621.00
621.00
621.00
631.00
631.00
631.00
631.00

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

738.75
738.75
738.75
738.75
738.75
738.75
738.75
751.25
751.25
751.25
751.25
763.75
763.75
763.75
763.75
776.25
776.25
776.25
776.25
788.75
788.75
788.75
788.75

529,550.78
529,550.78
2,087,348.91
2,126,614.95
2,126,614.95
2,126,614.95
2,126,614.95
2,162,598.28
2,162,598.28
2,205,629.88
2,162,598.28
2,242,329.22
2,198,581.62
2,242,329.22
2,198,581.62
2,279,028.55
2,234,564.95
2,279,028.55
2,234,564.95
2,315,727.88
2,315,727.88
2,270,548.28
-

497.00
497.00
497.00
497.00
497.00
507.00
507.00
507.00
507.00
517.00
517.00
517.00
517.00
527.00
527.00

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

621.25
621.25
621.25
621.25
621.25
633.75
633.75
633.75
633.75
646.25
646.25
646.25
646.25
658.75
658.75

152,191.34
152,191.34
152,191.34
152,191.34
152,191.34
155,253.54
155,253.54
155,253.54
155,253.54
158,315.74
158,315.74
158,315.74
158,315.74
161,377.94
161,377.94

(L+M) Rate

Amount in

Rs.

Remarks

59354.78
C7.3

Same as item MAS-002 - 150mm thick solid concrete block wall at all
levels, etc. complete as per the item above, cement mortar 1:6 with
minimum crushing strength of 35kg/sq.cm.

C7.3.1
C7.3.2
C7.3.3
C7.3.4
C7.3.5
C7.3.6
C7.3.7
C7.3.8
C7.3.9
C7.3.10
C7.3.11
C7.3.12
C7.3.13
C7.3.14
C7.3.15
C7.3.16
C7.3.17

Sub-Cellar
Cellar Floor
Ground fLOOR
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor

7/6/2012,Shell Core Boq

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

R/O
R/O
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62
30.62

R/O
R/O
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98
244.98

21 of 30

Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor
Parapet Wall & Terrace Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

Block -I
Quantity
30.62
30.62
30.62
30.62
30.62
R/O

Providing and constructing 100mm thick solid concrete block wall at


all levels including a concrete band of 75mm thick with 2-nos of 8mm dia
reinforcement rod (RI Steel shall be measured in relevant steel item) at
every fifth course with M15 grade concrete mix incl. shuttering, staging,
curing, etc., in cement mortar of 1:4 with minimum crushing strength of
35kg/sq.cm.
Sub-Cellar
Cellar Floor
Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor
Parapet Wall & Terrace Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

R/O
R/O
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
299.28
R/O

Item no
C7.3.18
C7.3.19
C7.3.20
C7.3.21
C7.3.22
C7.3.23

C7.4

C7.4.1
C7.4.2
C7.4.3
C7.4.4
C7.4.5
C7.4.6
C7.4.7
C7.4.8
C7.4.9
C7.4.10
C7.4.11
C7.4.12
C7.4.13
C7.4.14
C7.4.15
C7.4.16
C7.4.17
C7.4.18
C7.4.19
C7.4.20
C7.4.21
C7.4.22
C7.4.23

Description of Item

Unit

C7.5

Providing & Constructing 230mm thick burnt brick masonry using first
class table moulded bricks in cement mortar 1:6 with minimum crushing
Cum
strength of 45kg/sq.cm. with all necessary scaffolding , curing etc ,
complete as per the drawings and specifications

C7.6

Providing & Constructing 150mm thick burnt brick masonry at all levels
including a concrete band of 75mm thick with 2-nos of 8mm dia
reinforcement rod (RI Steel shall be measured in relevant steel item) at
Sqm
every fifth course with M15 grade concrete mix incl. shuttering, staging,
curing, etc., in cement mortar of 1:4 with minimum crushing strength of
45kg/sq.cm.

C7

Total for Masonary Works.

R/O

All Blocks Qty


B to I
244.98
244.98
244.98
244.98
244.98
R/O
2449.76

R/O
R/O
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
2,394.25
R/O
47884.98

R/O

527.00
527.00
537.00
537.00
537.00
537.00

25%
25%
25%
25%
25%
25%

Estimated
Rate in Rs.
658.75
658.75
671.25
671.25
671.25
671.25

479.00
479.00
479.00
479.00
479.00
479.00
479.00
489.00
489.00
489.00
489.00
499.00
499.00
499.00
499.00
509.00
509.00
509.00
509.00
519.00
519.00
519.00
519.00

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

598.75
598.75
598.75
598.75
598.75
598.75
598.75
611.25
611.25
611.25
611.25
623.75
623.75
623.75
623.75
636.25
636.25
636.25
636.25
648.75
648.75
648.75
648.75

3,477.00

25%

4,346.25

(L+M) Rate

OH %

Amount in

Rs.

Remarks

161,377.94
161,377.94
164,440.14
164,440.14
164,440.14
-

1,433,556.47
1,433,556.47
1,433,556.47
1,433,556.47
1,433,556.47
1,463,484.58
1,463,484.58
1,463,484.58
1,463,484.58
1,493,412.69
1,493,412.69
1,493,412.69
1,493,412.69
1,523,340.80
1,523,340.80
1,523,340.80
1,523,340.80
1,553,268.91
1,553,268.91
1,553,268.91
-

7/6/2012,Shell Core Boq

R/O

R/O

4,989.00

25%

6,236.25

78,059,955.04

22 of 30

Item no
C8

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

Remarks

PLASTERING
Note: The rate quoted shall include for providing drip moulds for projected
concrete surfaces, providing and fixing Arpitha Galvanised Iron (GI)
plaster mesh 200mm wide at junctions of RCC slabs, beams, columns,
walls with necessary centering, scaffolding, curing for the specified
period, at all levels, etc. complete.

C8.1

Preparing the surface and plaster the ceilings, in cement mortar 1:4,
upto 12mm thick with smooth finish to line and level at all levels including
lead and lift of materials, hydrating the lime 24 hours before starting of
work with necessary scaffolding, curing, etc., complete as per the
specifications , drawings and as directed by Engineer-in Charge.

C8.1.1
C8.1.2
C8.1.3
C8.1.4
C8.1.5
C8.1.6
C8.1.7
C8.1.8
C8.1.9
C8.1.10
C8.1.11
C8.1.12
C8.1.13
C8.1.14
C8.1.15
C8.1.16
C8.1.17
C8.1.18
C8.1.19
C8.1.20
C8.1.21
C8.1.22
C8.1.23

Sub- Cellar Floor


Cellar Floor
Ground/ Stilt Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor
Terrace Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

619.65
619.65
619.65
619.65
619.65
619.65
619.65
619.65
619.65
615.97
619.65
615.97
619.65
615.97
619.65
615.97
619.65
615.97
619.65
615.97
615.97
619.65
61.97

4,957.21
4,957.21
4,957.21
4,957.21
4,957.21
4,957.21
4,957.21
4,957.21
4,957.21
4,927.78
4,957.21
4,927.78
4,957.21
4,927.78
4,957.21
4,927.78
4,957.21
4,927.78
4,957.21
4,927.78
4,927.78
4,957.21
495.72

153.00
153.00
153.00
153.00
153.00
153.00
153.00
163.00
163.00
163.00
163.00
173.00
173.00
173.00
173.00
183.00
183.00
183.00
183.00
193.00
193.00
193.00
193.00
109,348.29

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

191.25
191.25
191.25
191.25
191.25
191.25
191.25
203.75
203.75
203.75
203.75
216.25
216.25
216.25
216.25
228.75
228.75
228.75
228.75
241.25
241.25
241.25
241.25

948,065.53
948,065.53
948,065.53
948,065.53
948,065.53
948,065.53
948,065.53
1,010,030.60
1,010,030.60
1,004,036.11
1,010,030.60
1,065,633.42
1,071,995.67
1,065,633.42
1,071,995.67
1,127,230.73
1,133,960.74
1,127,230.73
1,133,960.74
1,188,828.03
1,188,828.03
1,195,925.80
119,592.58

Preparing the surface and plaster all internal RCC / Masonry surface in
cement mortar 1:6, upto 20mm thick in a single coat, smooth finished to
line and plumb at all levels including lead and lifts with necessary
scaffolding, curing, etc., complete as per the specifications , drawings
and as directed by Engineer-in Charge.
Sub- Cellar Floor
Cellar Floor
Ground Floor
First Floor
Second Floor
Third Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

201.81
201.81
2018.06
2019.75
2019.75
2019.75

1,614.45
1,614.45
16,144.45
16,157.97
16,157.97
16,157.97

172.00
172.00
172.00
172.00
172.00
172.00

25%
25%
25%
25%
25%
25%

215.00
215.00
215.00
215.00
215.00
215.00

347,105.75
347,105.75
3,471,057.47
3,473,964.27
3,473,964.27
3,473,964.27

C8.2

C8.2.1
C8.2.2
C8.2.3
C8.2.4
C8.2.5
C8.2.6

7/6/2012,Shell Core Boq

23 of 30

Item no
C8.2.7
C8.2.8
C8.2.9
C8.2.10
C8.2.11
C8.2.12
C8.2.13
C8.2.14
C8.2.15
C8.2.16
C8.2.17
C8.2.18
C8.2.19
C8.2.20
C8.2.21
C8.2.22
C8.2.23

C8.3

C8.3.1
C8.3.2
C8.3.3
C8.3.4
C8.3.5
C8.3.6
C8.3.7
C8.3.8
C8.3.9
C8.3.10
C8.3.11
C8.3.12
C8.3.13
C8.3.14
C8.3.15
C8.3.16
C8.3.17
C8.3.18
C8.3.19
C8.3.20
C8.3.21

Description of Item
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor
Terrace Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

Block -I
Quantity
2019.75
2019.75
2019.75
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
2080.92
208.09

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

675.77
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
528.85
661.07
661.07
871.00

Unit

All Blocks Qty


B to I
16,157.97
16,157.97
16,157.97
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
16,647.38
1,664.74

172.00
182.00
182.00
182.00
182.00
192.00
192.00
192.00
192.00
202.00
202.00
202.00
202.00
212.00
212.00
212.00
212.00
334,401.80

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

Estimated
Rate in Rs.
215.00
227.50
227.50
227.50
227.50
240.00
240.00
240.00
240.00
252.50
252.50
252.50
252.50
265.00
265.00
265.00
265.00

273.00
273.00
273.00
273.00
273.00
273.00
273.00
273.00
273.00
273.00
273.00
288.00
288.00
288.00
288.00
288.00
288.00
288.00
288.00
288.00
288.00
94,875.18

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

341.25
341.25
341.25
341.25
341.25
341.25
341.25
341.25
341.25
341.25
341.25
360.00
360.00
360.00
360.00
360.00
360.00
360.00
360.00
360.00
360.00

(L+M) Rate

OH %

Amount in

Rs.

Remarks

3,473,964.27
3,675,938.94
3,675,938.94
3,787,277.83
3,787,277.83
3,995,370.01
3,995,370.01
3,995,370.01
3,995,370.01
4,203,462.20
4,203,462.20
4,203,462.20
4,203,462.20
4,411,554.39
4,411,554.39
4,411,554.39
441,155.44

Preparing the surface and plaster 25mm to all external RCC / Masonry
surface in cement mortar 1:4, in two coats, sand finished to required line
and plumb at all levels including lead and lifts with necessary scaffolding,
curing, waterproofing compound, using approved quality of waterproofing
compound as per manufactures specification etc., complete as per the
drawings and as directed by Engineer-in Charge.

Ground/ Stilt Floor


First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor
Terrace Floor & Above

7/6/2012,Shell Core Boq

5,406.15
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
4,230.82
5,288.53
5,288.53
6,967.99

1,844,850.19
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,443,768.14
1,523,096.06
1,523,096.06
1,523,096.06
1,523,096.06
1,523,096.06
1,523,096.06
1,523,096.06
1,903,870.08
1,903,870.08
2,508,477.47

24 of 30

Description of Item

Unit

Block -I
Quantity

Preparing the surface and providing rough plaster 10mm Thk in CM 1:6
on RCC/Masonry surface at all levels, to required level, line and plumb at
all levels including lead and lifts with necessary scaffolding, curing etc,
complete as per the specifications , drawings and as directed by Engineerin Charge.
Ground/ Stilt Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor
Eighthteenth Floor
Nineteenth Floor

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23
238.23

1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84
1,905.84

Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90
41.90

335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16
335.16

Item no

C8.4

C8.4.1
C8.4.2
C8.4.3
C8.4.4
C8.4.5
C8.4.6
C8.4.7
C8.4.8
C8.4.9
C8.4.10
C8.4.11
C8.4.12
C8.4.13
C8.4.14
C8.4.15
C8.4.16
C8.4.17
C8.4.18
C8.4.19
C8.4.20

C8.5

External Plastering for Lintels/ Sunshades of 15mm thick in CM 1:4 (1


cement :4 fine sand) in single coat including mixing of water proofing
compound , sponge finish including necessary scaffolding and curing
etc., complete at all heights and locations as per specifications, drawings
and as directed by Engineer-in Charge.

C8.5.1
C8.5.2
C8.5.3
C8.5.4
C8.5.5
C8.5.6
C8.5.7
C8.5.8
C8.5.9
C8.5.10
C8.5.11
C8.5.12
C8.5.13
C8.5.14
C8.5.15
C8.5.16
C8.5.17
C8.5.18

Ground Floor
First Floor
Second Floor
Third Floor
Fourth Floor
Fifth Floor
Sixth Floor
Seventh Floor
Eighth Floor
Nineth Floor
Tenth Floor
Eleventh Floor
Twelveth Floor
Thirteenth Floor
Fourteenth Floor
Fitteenth Floor
sixteenth Floor
Seventeenth Floor

7/6/2012,Shell Core Boq

All Blocks Qty


B to I

OH %

Estimated
Rate in Rs.

140.00
140.00
140.00
140.00
140.00
150.00
150.00
150.00
150.00
160.00
160.00
160.00
160.00
170.00
170.00
170.00
170.00
180.00
180.00
180.00
38,116.80

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

175.00
175.00
175.00
175.00
175.00
187.50
187.50
187.50
187.50
200.00
200.00
200.00
200.00
212.50
212.50
212.50
212.50
225.00
225.00
225.00

333,522.00
333,522.00
333,522.00
333,522.00
333,522.00
357,345.00
357,345.00
357,345.00
357,345.00
381,168.00
381,168.00
381,168.00
381,168.00
404,991.00
404,991.00
404,991.00
404,991.00
428,814.00
428,814.00
428,814.00

288.00
288.00
288.00
288.00
288.00
298.00
298.00
298.00
298.00
308.00
308.00
308.00
308.00
318.00
318.00
318.00
318.00
328.00

25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%
25%

360.00
360.00
360.00
360.00
360.00
372.50
372.50
372.50
372.50
385.00
385.00
385.00
385.00
397.50
397.50
397.50
397.50
410.00

120,657.60
120,657.60
120,657.60
120,657.60
120,657.60
124,847.10
124,847.10
124,847.10
124,847.10
129,036.60
129,036.60
129,036.60
129,036.60
133,226.10
133,226.10
133,226.10
133,226.10
137,415.60

(L+M) Rate

Amount in

Rs.

Remarks

25 of 30

Item no
C8.5.19
C8.5.20

Description of Item
Eighthteenth Floor
Nineteenth Floor

Unit
Sqm
Sqm

Block -I
Quantity
41.90
41.90

All Blocks Qty


B to I
335.16
335.16

(L+M) Rate

328.00
328.00

25%
25%

Estimated
Rate in Rs.
410.00
410.00

OH %

Amount in

Rs.

Remarks

137,415.60
137,415.60

6,703.20

C8.6

C8.7

C8.8

Preparing the surfaces and Providing waterproof plaster with 20 mm thk


water proof compound admixture (Fosroc or equivalent) as per
manufacturer's instructions in cement mortar 1:4 at all levels for Retaing
Sqm
walls, sump and any other places etc, complete as per the specifications ,
drawings and as directed by Engineer-in Charge.

Providing and fixing in position galvanized expanded metal mesh 20


gauge (ARPITHA make or equivalent) at junctions of concrete and
Sqm
masonry and other locations as called for including fixing with GI nails.
(For walls chased by service contractor)

R/O

R/O

282.00

25%

352.50

R/O

R/O

147.00

25%

183.75

Providing architectural groove in external plastering (Walls,Columns,


Pedestals etc.,)at all heights (other than grooves at junctions of RCC and
masonry) for specified width and depth as follows:

C8.8.1

25X12mm

Rmt

192.96

1,543.68

57.00

25%

71.25

109,987.20

C8.9

Providing architectural Band in external plastering at all heights for


specified width, depth upto 150mm and 20mm thk as per the Rmt
Architectural drawings and specifications

192.96

1,543.68

121.60

25%

152.00

234,639.36

C8

Sub-Total for Plastering Works.

C9

WATERPROOFING WORKS
Providing waterproofing for the areas as per the following specifications
listed below with a minimum guarantee period of 10 years and testing of
treatment at intervals as specified.

Note :-

586,532.64

146,317,199.53

Specialized agency to be approved by Client / Consultants. PRINCIPAL


CONTRACTOR SHALL GIVE GUARANTEE FOR STIPULATED TIME
FOR THE WATERPROOFING WORKS DONE AT SITE
C9.1
C9.1.1.1
C9.1.1.2

C9.2

Providing and applying waterproofing treatment to surfaces with all


necessary tools and tackles etc., complete
Podium
Cellar - Around the block s & drive ways

Sqm
Sqm

Treatment to construction joints in the Raft Slab and Retaining Wall


of Basement and any other water retaining structures
Providing and fixing Penebar/Hydroswell HDP 2010, 20 mm x 10 mm
Sqm
sized, hydrophilic Swellable Water bar fixed at construction joints in raft
slab and retaining etc. complete

7/6/2012,Shell Core Boq

4204.38
741.95

33,635.07
5,935.60

590.91
590.91

10%
10%

650.00
650.00

21,862,793.33
3,858,140.00

26 of 30

Item no

C9.3

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

Remarks

Waterproofing treatment to Grade slab (ONLY FOR GRADE SLAB)


Providing & laying Polythene sheet of 100-150 micron thickness as a
separation layer on the PCC, below grade slab also included, and also as
per the instuctions of site incharge etc complete.

C9.3.1

For Blocks -

C9.4

Lift Pits Water Proofing

C9.4.1

The first part consists of application of Hydrocem (Mastroseal / Brush


Bond RFX equivalent) flexible polymer modified cementitious coating
system applied in 2 coats at total doses 1 Kg per Sq. Mt to the internal
surface of the water tank which includes fixing of Nylon mesh / Geo fabric Sqm
with minimum over lap of 100mm after cleaning and brushing the
concrete surface, grouting the porous area with cement grout and curing
for 7 days, testing etc. complete

136.77

1,094.16

231.00

10%

254.10

278,026.06

C9.4.2

Second part consists Providing and laying waterproof and protective


screed / plaster consisting of plaster of average 25 mm thick on the wall
in cement mortar (1:3) and average 50 mm thick on the floor with 20mm
metal half embedded randomly after first layer, including mixing
Sqm
Plastocrete Plus / Proofsol LWP Integral Waterproofing Compound @
100ml per bag of cement making wattas at the junctions of floor and wall,
testing & curing for 7 days etc. complete. (CEMENT COEFFICENT:0.432
Bags/Sqm)

136.77

1,094.16

232.00

10%

255.20

279,229.63

C9.5

Toilets, Utility, & Balcony/ Sitout Water Proofing

C9.5.1

Providing waterproofing for the Toilets by Surface method. The first part
consists of application of two layer of Mastrseal-550(BASF)/ Hydrocem/
Brush Bond RFX or Equivalent waterproof coating (1.8 Kg/sqm) after
base preparation, cleaning, brushing and removal of flacky materials,
grouting the porous area with cementations grout, fixing of weep holes,
Sqm
Grouting of pipe outlets etc using Masterflow 918 and second layer of
coating using the same coating when the first coating is still green. The
coatings shall be applied at intervals and as per the manufacturers
specifications. (Note:- Actual treated area shall be measured for
payment) (CEMENT COEFFICENT:0.01 Bags/Sqm)

4417.95

35,343.60

231.00

10%

254.10

8,980,809.78

C9.5.2

Providing waterproofing plastering over polymercoat in CM 1:4 of


thickness 35mm for floor, 25mm for walls till floor level and 18mm till
300mm above floor level with water proof admixture (Rheomac 707/
Sqm
Conplast X 421 IC) with a minimum guarantee period of 10 years. Note:Actual treated area shall be measured for payment
(CEMENT COEFFICENT:0.22 Bags/Sqm)

4417.95

35,343.60

232.00

10%

255.20

9,019,687.74

C9.5.3

Providing and filling with Brick batts in sunken portions of utilities only
including cost and conveyance of all materials and all labour charges etc.,
Cum
complete as per drawings & specifications and as directed by Engineer-In
charge.

111.79

894.35

10%

1,910.70

1,708,831.30

7/6/2012,Shell Core Boq

Sqm

1737.00

27 of 30

Item no
C9.6

Description of Item

Unit

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

Remarks

Terrace Water Proofing


Providing waterproofing for Terraces by following one or all methods as
per the specifications listed below with a minimum guarantee period of 10
years and Testing of treatment as per the requirements.

C9.6.1

The first part consists of removal of loose particles, cleaning brushing the
concrete making dust free surface. Testing and treatment for construction
joints, leakages & honeycombs and cement grouting the porous area with
FLOW CABLE 50admixture 250gms per bag. Applying first coat of
Masterseal 550 EL/ Hydrocem/ Brush Bond RFX or equivalent Sqm
polymer based flexible cementations waterproof coating applied in first
coats in the form of slurry to the terrace slab and on the parapet wall upto
300 mm over the terrace slab complete. (Note:- Plan area shall be
measured for payment) (CEMENT COEFFICENT:0.01 Bags/Sqm)

823.29

6,586.31

231.00

10%

254.10

1,673,581.88

C9.6.1

second part consists of water proofing the Terrace by providing protective


layer of M15 Grade Concrete to required slope with average thickness of
50 - 75mm with waterproofing admixture as per manufacturers
specification. Over and above one coat of cement plaster with CM 1:4
with water proofing compound (Rheomac 707/ Conplast X 421 IC) to be
Sqm
done with minimum thickness of 25mm. Proper gradient shall be
maintained at rain water outlet. Impression marking of size 300 x 300
square with 3mm rod shall also be done. Treatment shall continue along
parapet for 300mm height, water curing and testing for water tightness by
pounding with water for 14 days etc. complete. Note:- Plan area shall be

823.29

6,586.31

232.00

10%

255.20

1,680,826.82

C9.6.2

second part consists of water proofing the Terrace by providing protective


layer of Brick batt Coba thickness of 150mm with waterproofing
admixture as per manufacturers specification. Over and above one coat
of cement plaster with CM 1:4 with water proofing compound (Rheomac
707/ Conplast X 421 IC) to be done with minimum thickness of 25mm.
Proper gradient shall be maintained at rain water outlet. Impression
Cum
marking of size 300 x 300 square with 3mm rod shall also be done.
Treatment shall continue along parapet for 300mm height, water curing
and testing for water tightness by pounding with water for 14 days etc.
complete. Note:- Plan area shall be measured for payment. (CEMENT
COEFFICENT:0.25 Bags/Sqm). This includes a minimum of 10 years
warranty.

87.35

698.77

10%

1,910.70

1,335,135.25

C9.7

Over Head Tank Water Proofing

C9.7.1

The first part consists of application of Hydrocem (Mastroseal / Brush


Bond RFX equivalent) flexible polymer modified cementitious coating
system applied in 2 coats at total doses 1 Kg per Sq. Mt to the internal
surface of the water tank which includes fixing of Nylon mesh / Geo fabric Sqm
with minimum over lap of 100mm after cleaning and brushing the
concrete surface, grouting the porous area with cement grout and curing
for 7 days, testing etc. complete

246.99

1,975.89

10%

254.10

502,074.56

7/6/2012,Shell Core Boq

1737.00

231.00

28 of 30

Item no

C9.7.2

C9.8

C9.8.1

Description of Item

Unit

Second part consists Providing and laying waterproof and protective


screed / plaster consisting of plaster of average 25 mm thick on the wall
in cement mortar (1:3) and average 50 mm thick on the floor with 20mm
metal half embedded randomly after first layer, including mixing
Sqm
Plastocrete Plus / Proofsol LWP Integral Waterproofing Compound @
100ml per bag of cement making wattas at the junctions of floor and wall,
testing & curing for 7 days etc. complete.(CEMENT COEFFICENT:0.432
Bags/Sqm)
Treatment to Expansion joint to Horizontal and Vertical joints at
Podium upto 25 mm width
Providing, placing and fixing in position 25mm thick High density
thermocole of supreme make at all Expansion joints and separation
Sqm
joints at all levels and wherever specified to the required sizes
andshapes.

Block -I
Quantity

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

Amount in

Rs.

246.99

1,975.89

232.00

10%

255.20

504,248.05

155.00

1,488.00

300.00

10%

330.00

491,040.00

C9.8.2

Providing and applying Kemperol V210 waterproofing system of M/s.


Kemper Systems, Germany or Equivalent in a strip of 225 mm width,
Rmt
including making edges of the expansion joints Backer rods, all as per
manufacturers specification etc. complete.

155.00

1,240.00

1,500.00

10%

1,650.00

2,046,000.00

C9.9

GROUTING :- Cleaning the surface making dust free and grouting the
pipe outlets of different diameters with non Shrink CONBEXTRA Nos
GP1/GP2 free flow grout at Toilets, Balcony & Utility etc completed

800.00

6,400.00

200.00

10%

220.00

1,408,000.00

C9

Total for Water Proof Works .

C11

MISCELLANEOUS WORKS
Providing and fixing in position the PVC coated steps of size 300x150mm
for UG Sumps and OH Tank including placing 150mm inside concrete
(while doing form work), aligning during concreting, grouting the junction if No's
required, cleaning etc.,

C11.1

C11.2
C11.2.1
C11.2.2
C11.2.3
C11.2.4
C11.2.5

Drilling holes and providing lockset for fixing reinforcement


8mm dia
10mm dia
12mm dia
16mm dia
20mm dia

C11.3

Supplying and fixing G.I.Puddle Flanges of various dia and size made
out of G.I with screwed ends, cap and plates for embedment in concrete
as necessary with suitable accessories, consumables welding
accessories including placing in position, grouting etc. Complete.

7/6/2012,Shell Core Boq

140,291.72

No's
No's
No's
No's
No's

30.00

2400.00
2400.00

240.00

19,200.00
19,200.00
-

Remarks

55,628,424.40

225.00

50.00
50.00

10%

10%
10%

247.50

55.00
55.00

59,400.00

1,056,000.00
1,056,000.00
-

29 of 30

Item no

Description of Item

Unit

C11.3.1
C11.3.2
C11.3.3
C11.3.4
C11.3.5

Between 450 & 750mm long


50mm to 100mm dia
100mm to 200mm dia
200mm to 300mm dia
300mm to 400mm dia

C11.4

Providing Core cut holes in RCC slabs, RCC Walls of dia varying from
450mm to 1000mm using proper cutting tools without damaging the Nos
stability of the structure.

C11.5

Making of Openings in masonry walls using proper cutting tools of varying


size 300mm x 300mm to 750mm x 900mm and finishing the entire Nos
exposed surface with cement mortar plaster.

C11.6

Supplyig and Fixing Heavy Duty Manhole Cover and Frame of "NECO"
make, cover weighing not less than the following and being a size of
Nos
600mm x 600mm for UG sump including painting with two coats of anticorrosive paint over a coat of primer etc.

C11.7

Supply and fixing Galvanised Iron(GI/ PVC) waterstop of 230mm wide all
water retaining structures as per the drawing with all sundry works extra Rmt
complete.

Block -I
Quantity

Nos
Nos
Nos
Nos

All Blocks Qty


B to I

(L+M) Rate

OH %

Estimated
Rate in Rs.

3,200.00

Rs.

Remarks

400.00

Amount in

350.00

10%

385.00

1,232,000.00
-

4.00

32.00

2,000.00

10%

2,200.00

70,400.00
-

C11.8

CoreCutting Holes for Podium Slab


110mm Dia
120mm Dia

C11.9

Amount forMiscelienious Civil Works (Pergolas, Sub Cellar/Cellar


Eminities like Toilet blocks Laundry, Car wash Points, Electrical &
Communications Rooms, Fire Pump Room, etc,.)

C11

Total for Miscellaneous Works(Shell & Core).


GRAND TOTAL (S & C )

7/6/2012,Shell Core Boq

Nos
Nos

LS

30
30

240.00
240.00

500.00
500.00

10%
10%

550.00
550.00

132,000.00
132,000.00

7,500,000.00

11,237,800.00
1,264,690,053.48

30 of 30

You might also like