Time and Action Calender

Usually the delivery of goods closed between a buyer and an export house is :

Ex-country, or AC At consolidator , FOB sea or

AC-at consolidator , FOB air

So Backward calculations need to be done to work out the complete planning of the garment/ goods delivery

Ex country- date when goods need to exit the country AC date- at consolidator date..this can be: FOB sea or FOB air PCD- Planned cut date

Types of samples :

Proto sample / PD sample, mockup. Salesman samples/ internet / marketing/photo samples 1st fit sample 2nd and 3rd fits incorporating the comments/ changes and corrections PP /sealer sample TOP sample

Approval terminologies
Strikeoffs s/o Labdips l/d Desklooms Hyde policy

T n a Example

Style- Suede skirt with polyester dtm lining, invisible zipper and metal hook and eye AC- 10/10 sea port chennai Order qty- 2500 pcs Leather- italian goat suede color beige Lining and trims local sourced Factory located in- Delhi

Order and inhouse dates for smpl and bulk Trims Leather, fabric, packing materials Minimums n leadtimes FIS SHEETS Testing dates- FPT, GPT

Inspection dates Pilot Midlines/ inlines Final Documentation

T& A
AC sea ex fty final inspection midline inspection 10-Oct 5-Oct ex country-5 30-Sep ex fty-5 18-Sep final insp-12

TOP
pilot inspection PCD planned cut date

10-Sep pilot inspn+1


9-Sep pcd+4 5-Sep final inspection -25

size set approval


fit approval leather inhouse

31-Aug pcd-5
26-Aug pcd-10 26-Aug pcd-10

leather shade lot approval trim inhouse trim approval leather ordering (includes transit also) leather color approval to order trim ordering trim approval from buyer to order order confirmation on style, qty, color first proto sending first tech pack receipt

2-Sep pcd-3 26-Aug pcd-10 2-Sep pcd-3

22-Jul leather inhouse -35


17-Jul leather ordering-5 27-Jul trim inh -30 22-Jul trim order-5 17-Jul exfty-80 7-Jul 27-Jun first /p recd+10