Test Closure

Introduction

Test Closure Entry Criteria

Test Closure Exit Criteria

Test Summary Reports

Critical Issue Encountered

Introduction
Final phase in STLC. Ensures that all the testing activities are performed in adherence to the Test Plan. Decides whether the project can be moved into the production phase or not. (means Go/No Go Decision)

Introduction

Test Closure Entry Criteria

Test Closure Exit Criteria

Test Summary Reports

Critical Issue Encountered

Entry Criteria of Test Closure


Scope/Objective should be completed

Defect status should be closed.

Entry Criteria of Test Closure


All Test cases should be executed.

All the test cases should mapped to the Req

Introduction

Test Closure Entry Criteria

Test Closure Exit Criteria

Test Summary Reports

Critical Issue Encountered

Test Closure Exit Criteria


Test Summary Report

Exit Criteria of Test Closure

Critical Issue Encounter

Introduction

Test Closure Entry Criteria

Test Closure Exit Criteria

Test Summary Reports

Critical Issue Encountered

Test Summary Reports


It contains the following information, Total No. of Testcases Total No. of Testcases executed No. of Testcases failed No. of failed Testcases has been fixed No. of Testcases has been rejected and deferred.

Content of Test Summary Reports


1. Test summary Reports a) Details Of the Build/Runs b) Types of testing Conducted c) Test Environment/Tools Used d) Items to be Tested and Items Not to be Tested Test Results a) Metrics Generated i. Test Management Metrics ii. Test Coverage Metrics iii. Defect Metrics b) Assessment of Quality Test deliverables a) Known Issues b) Recommendation

2.

3.

Contents of Test Summary Reports with Examples


1. Test summary Reports a) Details Of the Build/Runs. (Scope Of Build) b) Types of testing Conducted. (Functional Or Non Functional testing) c) Test Environment/Tools Used. ( Server, Platform, Configuration and Tool used for testing) d) Items to be Tested and Items Not to be Tested.

2. Test Results a) Metrics Generated i. Test Management Metrics. (Total no of Bug Fixes, Total No of Enhancements, No of Bugs/Enhancements covered in Test Cases, Test case Design Productivity, Test Execution Productivity, Requirement Stability index) ii. Test Coverage Metrics. (Total test cases-Functional and Regression test cases, Test case in Scope, Total Test case Passed, Total Test Case Failed, Total no of Test case Non-executed, Total Executed Test Cases, Test Coverage (At the End of the Sprints) , Pass percentage (At the End of the Sprints) iii. Defect Metrics. (Defect Status and Severity, Defect Trend)

2. b) Assessment of Quality. (Acceptable, Quality IndexSystem Stability) 3. Test deliverables Test Cases designed as part of bugs/enhancements Test Log/Test Summary Results Requirement Traceability Matrix a) Known Issues b) Recommendation

Introduction

Test Closure Entry Criteria

Test Closure Exit Criteria

Test Summary Reports

Critical Issue Encountered

Critical Issue Encountered


The issues that were encountered by the testing team are identified and discussed. The resolutions for the critical issues are documented. Unresolved outstanding issues are listed out.