PRESENT BY:
OUTLINE
1. Heavy Duty Platform Installation
and Dismantle.
2. Types of Prop.
3. Scaffolding Required Position.
4. Sequence of AAR Installation.
b. Dismantle:
- After complete the project, use tower crane to
remove platforms from voids area (see figure
3).
- Cut UB into 2 lengths (if require).
Use trolley to move beams to the building
boundary where mobile crane can access.
- Use mobile crane to lift up beams from fifth
floor to ground floor.
Trolley
Mobile Crane
2. Types of prop:
- 3 types of prop to be
installed:
- Props Location:
10
Scaffolding installation
sequence:
a. Type 1:
11
12
13
b. Type 2:
Step 1: YSSE to install scaffolding up to 3.5m at
column perimeter, for welding purpose.
Step 2: Install scaffolding next to column group for
welding purpose.
Step 3: Install scaffolding below prop for welding
purpose.
Step 4: Install scaffolding below ring for welding
purpose.
Step 5: Extend all internal scaffolding up to below
mushroom roof for bolt tightening purpose.
14
15
16
17
c. Type 3:
Step 1: YSSE to install scaffolding up to 3.5m at
column perimeter, for welding purpose.
Step 2: Install scaffolding next to column group for
welding purpose.
Step 3: Install scaffolding next to column group for
welding purpose.
Step 4: Install scaffolding next to column group for
welding purpose.
Step 5: Install scaffolding below perimeter ring for
welding purpose.
Step 6: Install scaffolding below perimeter ring for
welding purpose.
Step 7: Extend all internal scaffolding up to below
mushroom roof for bolt tightening purpose.
18
19
20
21
22
23
Installation sequence
duty
platforms,
props
and
Install
Install
Install
Install
Install
Install
Install
Install
Install
Install
Installation:
Step1: Setup heavy duty platform above void area where required
26
Step2: Install prop PR1, PR2 & PR3 to support ring frame
where required
27
29
30
Step4: Install 3D using tower crane TC4, use temporary bracket to lock
it, upon confirmed, weld it to 3C.
36
Step 7: Repeat step5&6, upon completed a full ring, weld all ring joints.
38
Step3: install Two 2CD using tower crane TC6 with temporary
bracket, use scaffolding to support it. Upon satisfied, proceed
to tack weld to 2BC.
41
Step4: install 2E using tower crane TC6 with temporary bracket, use prop
to support ring frame, upon confirmed. Proceed to tack weld to 2CD.42
Step5: Repeat step3&4, upon complete a full ring, weld all ring joints
together.
43
Step1: install 1st column at gridline k/38 with tower crane TC6.
44
Step2: repeat step1, install 4 columns at gridline k/38 with tower crane
TC6.
45
Step4: Install 1C using tower crane TC6, use PR1 to support ring
frame. Proceed to tack weld to 1B.
47
Step5: Repeat step3&4, upon complete a full ring, weld all ring joints
together.
48
Step1: Install 1st steel frame perimeter and cantilever using tower
crane, adjust alignment and level, upon confirmed and satisfied,
49
tighten stamp column anchor bolts.
Step1: Install 1st tie beam using tower crane, install scaffolding to
access tie beam installation. Adjust alignment and level, upon
51
confirmed and satisfied, weld it to ring frame.
52
Step3: Install first tie truss using tower crane, check alignment and
level, repeat same step to complete tie trusses installation at the
required locations.
53
Install first member of lower roof using tower crane, adjust alignment
and level, repeat same step to complete lower roof installation. 54
Install upper rings using tower crane TC4 or TC6, install and
tighten mush room roof trusses and finally install mushroom
55
57
Thank you!