PROJECT ENVIRONMENTAL MONITORING

AND AUDIT PRIORITIZATION SCHEME


(PEMAPS)
- is a simplified, semi-quantitative
environmental risk assessment (ERA)
that can be applied by non-ERA experts
mainly for planning purposes

PROJECT ENVIRONMENTAL MONITORING


AND AUDIT PRIORITIZATION SCHEME
(PEMAPS)
1. Conceptual Basis
2. Scoring Guidelines

PEMAPS
Adapted from the risk-based

methodology called National/Regional


Industry Prioritization Scheme (NRIPS)
developed by EMB-USAIDs Industrial
Environmental Management Project
(IEMP)
Uses Environmental Risk Assessment
(ERA) technique

ELEMENTS OF ENVIRONMENTAL RISK


ASSESSMENT
1. SOURCE/STRESSORS
- environmental aspects of the facility or activity or
environment which can cause impacts on vulnerable
receptors, directly or indirectly if transported through
certain pathways.
2. PATHWAYS/FATE
- environmental media such as air for air pollutants and
water bodies for water-borne contaminants
3. RECEIVING MEDIA & RECEPTORS/VULNERABLE
VICTIMS
- human beings, flora, fauna, ecosystems or ecological
services and life support systems

PEMAPS Scoring Guidelines


Instructs the scorer on how to determine the
number of priority points to assign to a project or
undertaking or facility covered by the PEIS and
issued an ECC
Helps the scorer decide when an assumption
must be made when relevant information is
insufficient or lacking

Risk Criteria and Points for PEMAPS


Scoring
1. Project Considerations (20)
a. Industry Factors
b. Waste Generation & Management
c. Pollution Control Systems (PCS)

2. Pathways/Transport of a Contaminant
(6)
a. Prevailing wind direction
b. Rainfall
c. Terrain
d. Depth to groundwater

Risk Criteria and Points for


PEMAPS Scoring
3. Receiving Media/Receptors (38 pts.)
- Determines the relative potential risk of a facility

4. Environmental Performance (34 pts.)


- Compliance (RA 8749, RA 9275, RA 6969, PD
1586, RA 9003)
- Complaints

5. Regional Priorities & Thrusts (2 pts.)


TOTAL PEMAPS SCORE = 100 PTS.

RISK CRITERION
A

POINT
Subtotal

PROJECT CONSIDERATIONS

20

Size and Type

Waste Generation & Management

10

Pollution Control System

PATHWAYS

RECEIVING MEDIA/RECEPTORS Air

Total

Air

Surface Water Distance

Fresh Water

Salt Water

4.5

Ground Water

Land

10.5

RISK CRITERION
D

Subtotal

ENVIRONMENTAL PERFORMANCE
Compliance

POINT
Total
34
30

RA 8749

RA 9275

PD 1586

RA 6969

RA 9003

Complaints

REGIONAL PRIORITIES & THRUSTS

TOTAL

100

PROJECT CONSIDERATIONS
INDUSTRY FACTORS
Type & Size
- size based on the no. of employees
- Environmentally Critical Project (ECP)
- Environmentally Critical Area (ECA)
WASTE GENERATION
- Air emissions
- Liquid effluents
- Solid wastes
- Hazardous vs. Non-hazardous
POLLUTION MANAGEMENT
-Pollution Control System (PCS) effectiveness

PATHWAYS

Fate and transport of a contaminant or stressor:


- Prevailing wind direction
- Rainfall
- Terrain
- Ground water

Receiving Media/Receptors
AIR
- Distance to nearest community
RECEIVING SURFACE WATER BODY
- Distance to water body
- Size of population using water body
- Classification of water use
- Size of water body
- Economic value of water body

Receiving Media/Receptors
GROUND WATER
- Discharge to recharge area
- Distance to nearest well
- Ground water use
LAND
- Current land use within 0.5 km.
- Planned or potential land use within 0.5 km.
- No. of Environmentally Critical Areas within 1
km.
- Distance to nearest ECA
* Recharge area an area into which water naturally
flows or is pumped to serve as a drinking water supply

Environmental Performance
Compliance to Environmental Laws, Rules and
Regulations (RA 8749, RA 9275, RA 6969, PD
1586, RA 9003)
- Administrative violation
- Standards violation
* Effluent or emission or discharge
* Ambient
* Human Impact
- Recalcitrant?
Complaints
- Citizen & NGOs
- other Govt. Agencies, Private Institutions
Regional Priorities/Thrusts

Prioritization of PEMAPS Score


1. Project Risk Categorization
- Sub-total points from project considerations,
pathways, receiving media, environmental
performance are added.
- Sum of points are then categorized to:
* high risk (70-100 pts.)
* medium risk (40-69 pts.)
* low risk (0-39 pts.)