You are on page 1of 66

Internal Use (Only)

Dec. 31 2006

ENE040613040018 HUAWEI BSC6000

Deployment Guide
www.huawei.com

ISSUE 1.0
GSM BSS Training Team

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

HUAWEI TECHNOLOGIES Co., Ltd.

The course tells the preparation for the


deployment of HUAWEI BSC6000, and
describes the deployment procedure and
noteworthy issues of the following three
operations:

Hardware installation

Software installation

Commissioning, acceptance test, and cutover

HUAWEI Confidential

Reference
Guide to HUAWEI BSC6000 Deployment
HUAWEI BSC6000 Hardware Installation
Manual
Version Upgrade Guide

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Target
At the end of the course, the students can:
Get a grasp of the preparation for the deployment of
BSC6000
Get a good grasp of the hardware installation process
and noteworthy issues during the deployment
Get a good grasp of the process of software upgrade,
commissioning, and noteworthy issues of BSC6000
Get a grasp of the methods of acceptance test and
cutover during the BSC6000 deployment

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Chapter 1 Preparation for the Deployment


Chapter 2 Hardware Installation and Check
Chapter 3 Software Installation and
Commissioning
Chapter 4 Cutover and Acceptance Test

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Engineering Preparation
Software version
Apply for the software version Software on
http://support.huawei.com/
Apply for the License
Data preparation
Have the data upgrade tool available
Make off-line configuration according to the data provided by the
customer
Resource preparation
Human resource
Documents
Tools and instruments

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Engineering Preparation
For the deployment, the following information and documents need be
obtained:
Contract information (about the product configuration)
Goods information
Survey Report
Installation Environment Check List
Customer information (Information such as order delivery information of the
contract and contract number can be obtained from the EPMS system.)
Engineering Document
Notes
According to demands, determine whether to create the Engineering
Implementation Scheme
Check whether the equipment room meets the installation requirements,
and whether the mains power, the distribution frame, and ground cable are
available. For specifics, refer to the Installation Environment Check List.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Chapter 1 Preparation for the Deployment


Chapter 2 Hardware Installation and Check
Chapter 3 Software Installation and
Commissioning
Chapter 4 Cutover and Acceptance Test

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Hardware Installation and Check


Hardware installation and check include the following issues:
Hardware installation procedure
Hardware installation preparation
Hardware installation
Noteworthy issues
Quality check

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Hardware Installation Procedure


Prepare for the installation

The right flowchart shows the hardware


installation procedure.

Cabling rack (upward/downward cabling)

Notes:
Install the cabinet

Before the installation, know well


about related content in the Survey

Install the external power cable

Report.
In the equipment room, a cabinet can

Install internal components of the cabinet

be installed on either raised floor or

Install boards

cement floor, so pay attention to


Install signal cables

related noteworthy issues according


to the actual situation.

Install the cabinet and other fitting parts


Install the LMT computer and alarm box
Check of hardware installation

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Prepare for the Installation


Obtain the following technical documents
Documents offering guidance of the installation: network planning, floor
plan, detailed construction drawing, and cabling diagram
Product manual
Other related documents: contract or agreement, equipment configuration
table, and goods delivery list.
Arrange the construction personnel
Have the installation tools available: tools and meters
Check the installation environment: check the installation environment
according to the Installation Environment Check List.
Unpacking check
Check the package
Open the wooden case
Open the carton
Check goods

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the cabinet

Cabinet installation on raised floor

Confirm the installation position of the cabinet


Confirm the installation position of the rack
Cabinet installation on cement floor
Install the rack
Confirm the installation position of the cabinet
Install the cabinet
Install the cabinet
Insulation test
Insulation test
No
No
Has the test passed or not?

No
Has the test passed or not?

Yes
Yes

Connect the combining cabinets

Connect the combining cabinets


Recover the antistatic floor
Installation is complete
Installation is complete

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the External Power Cables


A cabinet need the following external power cables:

Two external -48V power cables (blue, 25mm2) connecting to the cabinet

Two external GND power cables (black, 25mm2) connecting to the cabinet

One external PGND cable (Kelly, 25mm2) connecting to the cabinet

Three PGND cables interconnecting the combining cabinets (Kelly, 6mm2,


equipotential connection cables, three PGND cables connecting two adjacent
cabinets, ensuring equal potential among combining cabinets)

The below picture shows the connection of external power cables:

PDF

48V1
48V2
RTN
PGND

48V1

48V2
GND
PGND

BSC6000 cabinet
HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the External Power Cables


PDF and the power distribution box of BSC6000 cabinet

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the External Power Cables


Notes for installation of external power cables
Ensure the standard and neat layout of cables
Ensure the standard and neat binding of cables
Test the power supply function

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the External Power Cables


Test the power supply function
Confirm that the switch of the tributary, through which PDF provides
power to the BSC6000 cabinet, is set to OFF.
Confirm that all switches on the power distribution box of the BSC6000
cabinet are set to OFF.
Use a multimeter to test the voltage of -48v input terminal1 and -48v input
terminal2 of the power distribution box. If the voltage is over 0.1v, then
if the distribution cables are correct, the PDF power supply switch is
invalid, so please replace the power supply switch.
If the distribution cables are incorrect, connect the cables again.
Set the power supply switch corresponding to PDF to ON.
Measure the input voltage of the BSC6000 cabinet. The voltage should
ranges between -57V and -40V.
Set the power distribution switch corresponding to PDF to OFF.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install internal components of the cabinet


Install the internal components of the cabinet in the following order:
GBAM server
LAN Switch
KVM
Subrack
A service cabinet need be installed with only subracks.
Notes of installation:
Before installing internal components of the cabinet, set all power supply
switches on the power distribution box of the cabinet to OFF.
During installation, ensure that all rack-mounting ears are orderly and that
there are equal distances between components, equal distances between
components and blank panels, and equal distances between blank
panels, and avoid any too big distance.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Bit

Install Subracks

Meaning

Subrack number control bit

means 1. The highest bit of DIP corresponds

Subrack number control bit

with the highest bit of the byte.

Subrack number control bit

Subrack number control bit

eight DIP bits, the quantity of 1 must be odd.

Subrack number control bit

Use the following method to set: First set the

Odd parity check bit

DIP bit 15 and 8. DIP bit 7 is generally 0.

It is undefined, and is generally set as


0.

The automatic DIP bit of the GSCU board


in the central subrack is:
0, the starting of boards is highly
dependent on the GBAM server, namely
that the boards load from the server after
starting.
1, the starting of boards is less
dependent on the GBAM server, namely
that the boards check the validity of the
Flash file when starting, and load from
the Flash file if the Flash file is valid or
load from the server if the Flash file is
invalid.

The switch state ON means 0 and OFF

The odd parity check is used for DIP. In the

Then count the quantity of 1 in the current DIP


bits. If the quantity is even, set DIP bit 6 as 1.
If the quantity is odd, set DIP bit 6 as 0.

ON

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install Signal Cables


A BSC6000 cabinet need be installed with the following signal cables:
Monitor signal cable of the power distribution box
GTNU cross-connect cable
Network cable (including GSCU interconnect network cable and
other network cables)
Y-shape clock cable
Trunk cable (including trunks cables of the Abis, Ater, A, and Pb
interface)

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Layout Principles of Signal Cables


Because a large amount of cables need be distributed in a BSC6000 cabinet, comply
with the layout principles when performing capacity expansion and distributing cables to
avoid waste of the cabling space and affect of the subsequent capacity expansion. The
principles of capacity expansion are as follows:
Add cabinets from left to right (when facing the rear of the cabinets)
Add subracks from bottom to top
Add boards from the middle to two sides
In the upward cabling or downward cabling mode, distribute cables in the same
sequence and the principle is as follows:
All cables coming out of the front of the cabinet are distributed at the front of the
cabinet and all cables coming out of the rear of the cabinet are distributed at the
rear of the cabinet.
When distributing cables at the front of the cabinet, first distribute signal cables from
the GSCU board and then distribute signal cables from the GGCU board. No
sequence is required to distribute other signal cables.
When distributing cables at the rear of the cabinet, first distribute trunk cables and
then distribute optical fibers.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Notes
Notes about the installation
When distributing signal cables, do not destroy the jacket of the
signal cables.
If a signal cable need be pulled out, hold its connector instead of
pulling the cable, so that the signal cable is not damaged.
The manual describes only the installation method. To determine the
actual installation positions of the cables, comply with the
requirements concluded by the survey and refer to the data
configuration scheme.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Cable Distribution Requirements


The bending radius of all cables should be not smaller than the required
minimum bending radius.
All cables should be distributed in a standard and neat way.
All cables should be bound in a standard and net way.

Cable tie
Cable tie

Correct

HUAWEI TECHNOLOGIES Co., Ltd.

Incorrect

Cable

The minimum
bending radius

Network cable

25mm

Trunk cable

40mm

75 coaxial clock cable

45mm

Y-shape clock cable

25mm

GTNU cross-connect
cable

35mm

Interconnect cable
between GSCU subracks

25mm

Signal cable of alarm box

25mm

Monitor signal cable of


power distribution box

25mm

Optical fiber

40mm

HUAWEI Confidential

Install Monitor Signal Cable


The power distribution box of a cabinet is
connected only to the monitor port of the

Power distribution box

bottom subrack in the cabinet.


Insert one end of the monitor signal cable of
the power distribution box to the MONITOR
socket on the metallic screen board. Lead

Subrack

the monitor signal cable through the cabling


trough to the side of the cabinet, and along
a post to the COM4 interface at the rear of
the power distribution box, and then insert
the other end to the COM4 interface.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

MONITOR

COM4

Install Monitor Signal Cable

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Installing Inter-GTNU Cables


Install the GTNU cross-connect
cable, as shown in the below picture.
1

Pin14
A

Pin1
W1

X1

Pin1
A

W3
X3

W2

W4

X2

HUAWEI TECHNOLOGIES Co., Ltd.

Pin14

X4

HUAWEI Confidential

Installing Inter-GTNU Cables


Full interconnection is used for different
GTNU subracks.

0
GTNU

GTNU

Full interconnection between GMPS and


GEPS
Full interconnection between GTCSs
The Interconnecting of GTNU cross-connect
must be same to data configuration
Right figure shows how to connect interGTNU cables between subracks.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

1
GTNU

GTNU

Installing Inter-GTNU Cables


Right figure shows how to connect

0
GTNU

the inter-GTNU cables in 3 subracks

GTNU

(1 GMPS+2 GEPS, or 3 GTCS).

1
GTNU

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

2
GTNU

GTNU

GTNU

Installing Inter-GTNU Cables


Right figure shows how to

connect the inter-GTNU cables

GTNU

3
GTNU

GTNU

GTNU

in 4 subracks (1 GMPS+3
GEPS, or 4 GTCS).

1
GTNU

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

2
GTNU

GTNU

GTNU

Installing Ethernet Cables


Network cables to be installed fall into the following types:
Inter-GSCU Ethernet cables
Ethernet cables between the GSCU and the GBAM
Ethernet cables between the LAN switch and the GBAM
Ethernet cables between the LAN switch and the LMT or the
M2000/LAN
Ethernet cables between the LAN switch and the CBC

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Installing Inter-GSCU Ethernet Cables


Connecting inter-GSCU Ethernet cables between subracks

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Installing Inter-GSCU Ethernet Cables


Interconnection between GSCU subracks
Star-shape interconnection between GMPS and

0
GSCU

GEPS

GSCU

Star-shape interconnection between GTCSs


When installing interconnect network cables between
GSCU subracks, use different ways for the following two
situations:
The GSCU subracks to be connected are in the
same cabinet.

GSCU

The GSCU subracks to be connected are in different


cabinets.
Connecting inter-GSCU Ethernet cables in 2 subracks
as shown in the right picture.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

GSCU

Installing Inter-GSCU Ethernet Cables


Connecting inter-GSCU Ethernet

0
GSCU

cables in 3 subracks as show in the

GSCU

right picture.

2
GSCU

HUAWEI TECHNOLOGIES Co., Ltd.

GSCU

HUAWEI Confidential

GSCU

GSCU

Installing Inter-GSCU Ethernet Cables


Connecting

0
GSCU

inter-GSCU

GSCU

Ethernet cables
in 4 subracks as
show in the right
picture.

2
GSCU

HUAWEI TECHNOLOGIES Co., Ltd.

GSCU

GSCU

HUAWEI Confidential

GSCU

3
GSCU

GSCU

Installing Y-Shaped Clock Cables


The below picture shows the GTNU cross-connect cables.

W2
8
1

X1

X2

W1
8

W3

X3

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Installing Y-Shaped Clock Cables


The right picture shows the connection of clock cables between subracks.
GMPS
GGCU

GEPS
GSCU

CLKIN

HUAWEI TECHNOLOGIES Co., Ltd.

GGCU

GEPS
GSCU

CLKIN

HUAWEI Confidential

GSCU

GEPS
GSCU

GSCU

GSCU

Installing Trunk Cables


Distribute trunk cables according to the following orders:
Distribute trunk cables from the bottom subrack to the top subrack in the same
cabinet.
Distribute trunk cables from the middle to the side boards in the same subrack.
Distribute trunk cables leftwards from Slot 20 to Slot 27 and rightwards from Slot
19 to Slot 14.
Distribute trunk cables from the bottom DB44 interface to the top DB44 interface
on the same board.
Interconnect trunk cables of different equipment according to the following principles:
Connect the TX of trunk cable E1 at the BSC6000 side to the RX of E1 of the peer
equipment.
Connect the RX of trunk cable E1 at the BSC6000 side to the TX of E1 of the peer
equipment.
Decide which pair of E1 at the BSC6000 side interconnects to which pair of E1 of
the peer equipment according to the specific data configuration.
Before interconnecting different types of cables, for example 75ohm coaxial cable
and 120ohm twisted pair, use multiplexers or tielines to transduce the impedance.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Installing Trunk Cables


Set the DIP switch of GEIU according to the actual situation at the site.
Switch DIP bit

Description

75

120

S1

Impedance selection switch of


No.0~7 E1/T1

ON

OFF

Impedance selection switch of


No.8~15

ON

OFF

Impedance selection switch of


No.16~23

ON

ON

OFF

Impedance selection switch of


No.24~31

ON

OFF

5~8

Idle

ON

OFF

S3

1~8

Transmit end PGND selection


switch of No.0~7

ON

OFF

S4

1~8

Transmit end PGND selection


switch of No.8~15

ON

OFF

S5

1~8

Transmit end PGND selection


switch of No.16~23

ON

OFF

S6

1~8

Transmit end PGND selection


switch of No.24~31

ON

OFF

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

S6

OFF
ON

S5

OFF

ON
S4

OFF

ON
S3

OFF

ON
S1 OFF

Distribution Order of Trunk Cables


Distribution order: A -> B -> C -> D

GEIU

GEIU

E1/T1(24~31)

E1/T1(24~31)

E1/T1(16~23)

E1/T1(16~23)

E1/T1(8~15)

E1/T1(8~15)

E1/T1(0~7)

E1/T1(0~7)

Active

Standby
A BC D

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Installing Trunk Cables


1

2
3
4

6
6

Rear of the cabinet

HUAWEI TECHNOLOGIES Co., Ltd.

Side of the cabinet

HUAWEI Confidential

Install Other Components of a Cabinet


Install the following components of a cabinet
Install the side door
Install the front door and rear door
Install the PGND cable of the cabinet door
Attach an engineering label to the cabinet

HUAWEI
Product label

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Hardware Installation Check


Hardware installation check includes the following items:
Check the installation of the cabinet (refer to the Cabinet
Installation Check List in the Installation Manual)
Check the installation of the cable (including the power cable,
PGND cable, and signal cable)
Check the installation of local maintenance terminal and alarm box
Power on and check
Check the environment sanitation of the site

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Power On and Check


Check before power-on
Check and ensure that no board is inserted in the slots on the backplane.

Power on the power distribution box and check.

Power on the cabinet


After ensuring that the cabinet is powered off, use a multimeter to test the
resistance of each power wire post on the cabinet top and grounding wire posts to
check for short circuit.

After ensuring that all switches of the power distribution box above the cabinet are
turned to OFF. When the power supply switch of the tributary, through which PDF
supplies power to the BSC6000 cabinet, is in no-load mode, use a multimeter to
check whether the output voltage of PDF is in the required voltage scope (-57V~40V). At the moment, the RUN indicator on the power distribution box should blink.

When PDF normally works, turn the switches of the power distribution box to ON
one by one and use a multimeter to check whether the output voltage of the power
distribution box is in the required voltage scope (-57V~-40V).

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Power On and Check


Power on and check each module in the cabinet:
Check whether the fan can normally work.

Check and ensure that no board is inserted in the slots.

Turn all the power supply switches, which control the subrack power, on the power
distribution box to ON.

Turn on the power switches of modules such as the server and KVM one by one to
check whether the equipment can normally work.

Check the power supply state of the components inside the cabinet.

Power on and check boards:


Turn all the power supply switches, which control the subrack power, on the power
distribution box to ON.

Insert the boards one by one.

Note: Check the boards indicator after inserting a board. Insert the next board only
if the indicator is normal.
If a board is abnormal, turn off the power switches, remove all inserted boards,
and confirm the cause of the fault.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Power On and Check


The below picture shows the power controlling of each module in the cabinet
by the power distribution switches of the power distribution box.

Assignment of Switches

HUAWEI TECHNOLOGIES Co., Ltd.

SW1SW4

GEPS/GTCS

SW2SW5

GEPS/GTCS

SW3SW6

GEPS/GTCS

HUAWEI Confidential

Check the Environment Sanitation of the Site


Do not pile up packages and boards in the equipment room in a
disorderly way, but put them neatly in the equipment room.
Do not leave cable ties or any other thing in the cabling rack (trough), at
the cabinet bottom, or around the cabinet.
Do not leave cable ties or any other thing below the raised floor. After
installation is complete, restore the raised floor to keep it smooth and
clean.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Chapter 1 Preparation for the Deployment


Chapter 2 Hardware Installation and Check
Chapter 3 Software Installation and
Commissioning
Chapter 4 Cutover and Acceptance Test

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Summary
Software installation
Software structure
Install OMU software
Install LMT software
Download the software of BSS board
Software commissioning
Network commissioning
Prepare for the commissioning
Commissioning procedure
Service test

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Software Layout
The software of BSC6000 uses a distributed structure and includes the board
software and Operation & Maintenance software.
The board software, which is distributed among all boards of BSC6000,
includes the following types:
Board version software
Patch software
Bios software
The Operation & Maintenance software includes the following types:
OMU software
LMT software
M2000 network management software
Software installation process:
Install OMU software Install LMT software Download the BSS board
software

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Software Description
Software

Function

Installation
time

Suse Linux Enterprise Server 9.0 It provides an operating platform for the
OMU software

Before
delivery

It provides an operating platform for the


LMT software

Before
delivery

OMU software

It operates on the GBAM server and


finishes the Operation & Maintenance
function of the system.

At the site

LMT software

It performs the maintenance function


through the OMU software on the GBAM
server.

At the site

BSS board software

It includes the radio resource processing


At the site
software, resource controlling plane
software, BTS management software, and
configuration management software, which
implement functions of different entities.

Windows2000 Professional(SP4)/
Windows XP Professional(SP2)

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Networking Diagram
Networking scheme

GMPS

Use Port10 of GSCU in the basic

GSCU

GSCU

subrack to interconnect GSCU


and the GBAM server.
Port10 on the active and standby

Intranet
80.0.X.X

EHT 10

EHT 10

GSCU in the basic subrack form


a Trunk group to avoid affect on
communication when the

GBAM

network interface of GSCU or

eth1

eth0
eth2

GBAM server has faults.


Connect both internet interfaces

LAN Switch
Internet

of the GBAM server to the same


LAN Switch.

HUAWEI TECHNOLOGIES Co., Ltd.

LMT

HUAWEI Confidential

M2000

Prepare for the Installation of OMU Software


Obtain the installation information (make records in the Installation Information Record
Table)
The root user of GBAM server: The root user name is root and the initial password
is 11111111.
Samba user name: The initial user name is bsc6000 and the initial password is
11111111.
The initial IP of the server: At the initial state, no setting is made for the four network
cards. It is necessary to obtain the internet IP, subnet mask, and default gateway,
which are to be allocated for the GBAM server.
Check the settings of the server (refer to the chapter about the settings of server in the
Software Installation Manual)
Check the version of the operating system
Check the partition rules of hard disk
Check the memory size
Check configuration information of the network cards
Check the settings of the Samba directory
Check the connection of KVM

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the OMU Software


Use the following two methods to install the OMU software:
When being not at the deployment site, install the OMU software through
the network.
When being at the deployment site, run the disk of OMU software in the
disk drive of the GBAM server to install the OMU software.
Install the OMU software by running the disk
Put the OMU install disk in the disk drive of the GBAM server.
Log into the GBAM server as root user.
Type in the cd /media/cdrom command and change the current directory
to /media/cdrom.
Type in the rpm -ivh omu-9.1-1.i586.rpm command.
Type in the omuctrl cfg command. Configure the network interface
according to the prompt and start the OMU software.
Type in the omuctrl status command. Check the operating state of the
OMU software to ensure that the installation is complete.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Install the LMT Software


After the local maintenance terminal of BSC6000 is installed, the menu
includes the following parts:
BSC6000 local maintenance terminal
BSC6000 BTS maintenance terminal
Alarm transfer tool
Uninstall Huawei local maintenance terminal
Performance browse tool

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

LMT Directory Structure


Folder

Description

FtpServer

FTP SERVER program folder

SWM

BSC board software management folder

Bin

The folder where executable programs of the


BSC6000 local maintenance terminal are
saved

BscObj

BSC object folder

Btsm

The folder of BTS maintenance terminal BTSM


program BSC6000

Cfg

The folder where configuration files are saved

Convert

The folder of alarm convert tool program

Help

The folder of LMT Help files

pfbTool

The folder of performance browse tool


program

Uninstall

The folder of uninstall program files and


uninstall log files

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Download BSC Board Software


Download BSC board software
Copy the complete set of issued software to the directory
Common\SWM\Software of LMT.
Log into the BSC6000 local maintenance terminal, in the menu
select BSC software > BSC software maintenance > Download
software and finish downloading according to instructions of the
wizard.
Query software information in the OMU version area.
Notes
If the downloading fails, restart and download again.
Give English names to the downloaded files.
Halt of the downloading does not affect the whole downloading
process.
HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Download BTS Board Software


Download BTS board software
Copy the BTS version software to HW LMT\Common.

Log into the BSC6000 local maintenance terminal, in the menu select BTS maintenance
> Download BTS software, and finish software downloading according to instructions of
the wizard.

Notes
BTS board software support only the file name with .bin or .hex as its suffix.

Do not change the file name of BTS board software.

If on the GBAM server, a files name is the same as the downloaded file, the file on the
GBAM server will be overwritten. The system gives no prompt about the overwriting. So it
is recommended to make backup of the files on the GBAM server before downloading to
avoid data loss.

If the downloading state is waiting for download, wait for the response from the FTP
server.

In the downloading process, if the downloading of a file is halted the files following
continues to be downloaded. If the downloading process is existed midway, the file
currently being downloaded will be downloaded, but the files following will not be
downloaded.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Commissioning Process
Prepare for

For specific methods and

Commissioning
Load BSC

procedure of
commissioning, refer to

software
Load BTS

the Commissioning Guide.

software
Verify the Abis
interface
Verify the Ater
interface
Verify the A interface
Verify the Pb
interface
Interconnect BSC to
M2000
HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Prepare for Commissioning


Prepare for commissioning
Ensure that the OMU software is installed.
Ensure that the LMT software is installed.
Check the network connection and ensure that LMT can log into
the GBAM server.
Samba service can be normally started.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Load the BSS Software


The process of loading BSC software:
Check the GBAM version area
Load the software
Trigger the software
Query the board software
Query the board state
The process of downloading BTS software:
Download the BTS software (The downloading of BTS software is
complete during software installation.)
Configure the BTS software
Load the BTS software
Query the BTS attribute
Trigger the BTS software
Query the board information

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Commissioning of BSC at the Local Office


Change over the active
and standby boards:
check the changeover
function of the boards
working in the active and
standby state
Query the software
license: check whether
the License configuration
information becomes
effective

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Interface Debugging and Service Test


Interface debugging: The methods of debugging the Abis, Ater, A, and Pb
interfaces are given in the lesson of software debugging.
Service test
Dialing test of basic services
Basic service
Speech
service

Data service

Operation &
Maintenance
management

Dialing test process

Expected result

MS calls local PSTN subscribers or


The connect success rate exceeds
local PSTN subscribers call MS for 50 90%. The voice is clear and has no
times respectively.
obvious noise.
MS calls MS for 50 times.

The connect success rate exceeds


90%. The voice is clear and has no
obvious noise.

MS sends faxes to facsimile


machines, and facsimile machines
send faxes to MS.

The faxes are correctly transmitted and


received.

Test the GPRS or EDGE function of


MS.

The data rate is basically the same as


the tested data rate in lab.

During operation, change over boards The changeover success rate exceeds
for five times.
90%, and the service is not interrupted
by the changeover.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Service Test
Service test
Dialing test of feature services
Feature services

Dialing test process

Expected result

Inter-system
switchover

Use a dual-mode mobile phone


to switch over from GSM
network to UMTS network and
from UMTS network to GSM
network for 50 times
respectively.

The connect success rate


exceeds 90%. The voice
is clear and has no
obvious noise.

Location service

Make an MS initiate a call and


The position of MS meets
keep connection, and locate the the accuracy
MS.
requirement.

AMR service

MS calls PSTN subscriber and


selects AMR as the speech
version. Test for 50 times.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

The connect success rate


exceeds 90%. The voice
is clear and has no
obvious noise.

Chapter 1 Preparation for the Deployment


Chapter 2 Hardware Installation and Check
Chapter 3 Software Installation and
Commissioning
Chapter 4 Cutover and Acceptance Test

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Preliminary Acceptance Test


Prepare for the preliminary acceptance test
Before the preliminary acceptance test (PAT), the engineering supervisor makes the following
preparation:
sorts out project completion documents
works out the Preliminary Acceptance Test Scheme
Submit the Preliminary Acceptance Test Application Report to the customer
Understand the customers special requirements about the PAT, and confirm the schedule and
items of the PAT.
Check whether the customer has required necessary tools, test instruments and meters.
Preliminary acceptance test
The engineering supervisor and the customer organize the PAT. The customer manager,
service manager, or project manager of the region can participate in the PAT.
After the PAT passes, hand over project completion documents to the customer. Fill in the
Document Handover List and have the customer sign on the list to confirm.
After the PAT is complete, have the customer sign or stamp on the Equipment Installation
Report and the Certificate of Preliminary Acceptance.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Cutover
Cooperate with the customer to work out the Cutover Scheme according to the
demands.
Confirm the responsible persons and duty division of both parties.
Negotiate with the customer about how to guarantee the success of the
equipment cutover and about the remedy measures in case of cutover
failures.
Arrange personnel to observe operation of the equipment.
Noteworthy issues during cutover:
Designate the responsible persons for each operation.
Take the next step only after ensuring that a step is complete. Two
operators are required for those important steps.
Designate responsible departments and persons for each cutover step and
the dialing test.
If the cutover is not complete, the dialing test fails, or the success rate is
lower than 80% by MM-DD XX:00, unconditionally back off the cutover.

HUAWEI TECHNOLOGIES Co., Ltd.

HUAWEI Confidential

Internal Use (Only)

Dec. 31 2006

Thank You