Professional Documents
Culture Documents
RESOURCES
Project Crashing
The process of accelerating a project is
referred as crashing.
Crashing a project relates to resource
commitment; the more resources expended, the
faster the project will finish.
There are several reasons to crash a project:
Initial schedule was too optimistic
Market needs change and the project is in demand
earlier than anticipated
The project has slipped considerably behind
schedule
There are contractual late penalties
Project Crashing
Principal methods for crashing are:
Improving existing resources productivity
Changing work methods
Increasing the quantity of resources
Increasing the quantity of resources is the
most commonly used method for project
crashing. There are 2 approaches:
Working current resources for longer hours
(overtime, weekend work, etc.)
Adding more personnel
Project Crashing
Fully expedited (no expense is spared)
Crash
Point
Crashed
Cost
Normal
Point
Normal
Crashed
Normal
Activity Duration
Project Crashing
In analyzing crash options, the goal is to find
the point at which time and cost trade-offs are
optimized.
Various combinations of time-cost trade-offs
for crash options can be determined by using
the following formula:
Slope = crash cost normal cost
normal time crash time
Cost
$1,000
$2,500
$750
$3,500
$500
$2,000
$4,500
Crashed
Duration
Cost
3 days
$2,000
3 days
$5,000
2 days
$1,200
5 days
$5,000
1 day
$2,000
4 days
$3,000
7 days
$6,300
Crashed
Cost Duration
Extra Duration
Cost
5,000 4 weeks
4,000 3 weeks
B*
10,000 5 weeks
3,000 4 weeks
3,500 2 weeks
3,500
D*
4,500 6 weeks
4,000 4 weeks
E*
1,500 3 weeks
2,500 2 weeks
7,500 8 weeks
5,000 7 weeks
G*
3,000 7 weeks
2,500 6 weeks
2,500 6 weeks
3,000 5 weeks
1 week
Direct Penalties
Costs
Overhead
Total
21
weeks
37,500
10,000
10,500
58,000
20
weeks
40,000
5,000
10,000
55,000
19
weeks
42,500
-0-
9,500
52,000
18
weeks
45,500
-0-
9,000
54,000
16
weeks
49,500
-0-
8,000
56,500
Resource Loading
Resource loading describes the amounts of
individual resources an existing schedule
requires during specific time periods.
The loads (requirements) of each resource
type are listed as a function of time period.
Resource loading gives a general
understanding of the demands a project or set
of projects will make on a firms resources.
Resource Loading
The project manager must be aware of the
flows of usage for each input resource
throughout the life of the project.
It is the project managers responsibility to
ensure that the required resources, in the
required amounts, are available when and
where they are needed.
Critical path:A-C-F-H-K
Critical path:A-C-F-H-K
Duration
Total Float
Resource Hours
Needed Per Week
Total Resources
Required
30
20
18
18
12
16
21
20
25
Total
194
12
10
8
6
4
2
0
1
11
13
15
17
Project Days
19
21
23
25
27
5 D 9
Res = 7
9 E 11
Res = 3
1. Start with a
network diagram
4 C 7
Res = 2
11 F 12
Res = 6
A
B
C
D
E
F
Resource
6
2
2
7
3
6
Duration
ES
Slack
LF
4
1
3
4
2
1
0
4
4
5
9
11
0
0
4
0
0
0
4
5
11
9
11
12
Resources
8
6
4
2
C
2
F
E
6
8 10 12
Project Days
14
Resource
imbalance
Resources
8
6
4
2
C
2
E
6
8 10 12
Project Days
14