Construction of farm house

Company: Farm solutions

Team Members
Mujeeb ur rehman (project manager)
Rizwan mushtaq
Owais riaz
Sharukh Shoukat
Mansoor ali
Project Synopsis
Our CEO assigned a project to construct a 5 can
luxurious farm house in Chak Shezad Islamaba
having budget (25 million).
Project Goal:
The main goal of this project is to provide the
accomplished residency to our client in the cit

Technical specifications:
Project include the construction of total (sq ft
28586) covered area single story having 8 roo
and a servant quarter(1361 sq.ft).
It also include a gym, swimming
pool(12*20*5) in the middle of lawn. Lawn
situated in the front side of plot having area
(5445 sq.ft)
Boundary wall having 10ft high special
steel fencing will be installed and four
security cameras on all four corner of the
wall will be installed.
HVAC system will be installed for heating
and cooling of the building.
Current status of project:
Prototype model is competed.
Drawings are in progress.
Market potential:
In this busy world people want live natural and healthy
life from a slightly outside from the city. So there is a big
potential of construction of farm house in cities.
Our company has the core history and valuable market
for this type
Of projects.
Cost Management Plan

Unit of
Measure

Control
Level of
Threshold
Precision
s

Cost
Managem
ent Plan
Process
Level of
Descriptio
Accuracy
ns

Organizati
Reporting onal
Formats Procedura
l Links
Cost Management Plan
Based upon the units used in local construction market

Unit of Measure
Currency Pakistani Rupee
Area Square Foot
Resource Hours Days
Mixed Concrete Cubic Meter
Weight Kg
Paint/Water Liters
Bricks Numbers
Cost Management Plan
Based upon the scope and magnitude of the project

19750=20
000

21225=21
000

Level of Precision
Cost Management Plan

-10%
+10%

Level of Accuracy
Control threshold:

We have set 15% upper or lower variation from the cost baseline. From
variation this limit project manager should give a solid reason for it.
Acceptable Deviation 15%

From the context of our project the deviation of 15% is


acceptable for our project with the help of using these
techniques
1. OPS
2. Expert opinion
3. analogous technique
Threshold
UCL

c
o
s
t

LCL

Months
24
Reporting Formats

We are using existing company reporting formats


which are word files and company temples.
MS Office would be used for documentation based
upon formats provided by PMO.
Construction of farm house

Building Landscapin
Foundation Interiors
Structure g

Get Design
Draw Material Design
Interior
Blueprints public area
Constructio
Decide
n Pillars, Lay
Dig Earth Furniture
beams Walkways
Decide
Constructio
light
Get n Walls Set up
Fixture
Material Plumbing lawns
Procure
Lay Work Furniture Plant
Foundation Electric Fix Light, saplings
Work Ac and
Fans
Organizational Structure
CEO

Finance Technical
Hr Manager
Managers Manager

Project
Manager

Interior
Labor Civil Engineer
designer
Organizational Procedural Links

In this area we allocate the responsibility and expense


of the resource needed in order to complete the
activities
Interior
Technical Construction of farm house
Designer
Manager Interior
Civil Engineer Designer

Building Landscapin
Foundation Interiors
Structure g

Get Design
Draw Material Design
Interior
Blueprints public area
Constructio
Decide
n Pillars, Lay
Dig Earth Furniture
beams Walkways
Decide
Constructio
light
Get n Walls Set up
Fixture
Material Plumbing lawns
Procure
Lay Work Furniture Plant
Foundation Electric Fix Light, saplings
Work Ac and
Fans