You are on page 1of 89

A PRESENTATION ON 660MW TURBO-

GENERATOR ,ITS AUXILIARIES


AND ASSOCIATED SYSTEMS OF
STAGE I OF SIPAT SUPER THERMAL
PROJECT
STEAM TURBINE K-660-247
LMZ (LENINGRADSKY METALLICHESKY ZAVOD)

K STANDS FOR KLAPAN LTD.,BULGARIA WHICH SUPPLIES


TURBINE,NOZZLES,DIAPHRAGMS, SEALS,BLADES ETC.
GENERAL INFORMATION
TG DECK IS VIS SUPPORTED AND HAS 26 CONCRETE COLUMNS (T1 T26).
TG HALL IS CONSTITUTED OF 3 MAINS ROWS OF COLUMNS A,B ,C ROW AND TWO BAYS AB BAY AND BC
BAY. THE WIDTH OF AB BAY IS 36m AND BC BAY IS 12m

CONDENSER TUBE BANKS (CW PATH) HAS AN INCLINATION OF 40.


THERE ARE TWO MAIN EOT CRANES FOR TG HALL.EACH EOT CRANE IS HAVING A CAPACITY OF 200t FOR
MAIN HOIST AND 20t FOR AUXILIARY HOIST. 35.5m IS THE MAXIMUM VERTCAL DISTANCE A HOIST CAN
TRAVEL.TANDEM OPERATION OF TWO EOT CRANES ARE ALLOWED.
RATED CONDITIONS

LOAD : 660MW
BEFORE HP STOP VALVE
STEAM PRESSURE : 247KSC
STEAM TEMPERATURE : 5370C
STEAM FLOW : 2023.75T/HR

AFTER HPC
STEAM PRESSURE : 48KSC
STEAM PRESSURE : 298.710C

BEFORE IP STOP VALVE


STEAM PRESSURE : 43.2KSC
STEAM TEMPERATURE : 5650C

STEAM FLOW TO REHEATER : 1681.12T/HR.


DESIGN CONDENSER PRESSURE : 0.105KSC (abs.)
COOLING WATER FLOW : 64000M3/HR
FINAL FEED WATER TEMP. : 286.350C
FREQUENCY RANGE : 47.5 51.5 Hz
STEAM TURBINE

Generator rated speed 3000 rpm


Generator manufacturer Electrosila
No. of bleedings 8
Length of the turbine 36.362 m
No. of stages
HPT 17
IPT 11x2
LPT-1 5x2
LPT-2 5x2
Total 59
STEAM TURBINE

Parameters
Pr. Before HPC SV 247.0 Ksc
Temp. before HPC SV 537.0 0C

Steam flow 2023.75 TPH


Pr. After HPC 48.0 Ksc
Temp. after HPC 298.71 0C
Pr. Before IP SV 43.2 Ksc
Temp. before IP SV 565.0 0C

Steam flow to reheat 1681.12 TPH


Design Cond pr. 0.105 Ksc
CW flow 64000 TPH
Final FW Temp. 286.35 0C
STEAM TURBINE

Turbine Governing system


Mode of Governing Nozzle
Type E/H
Control fluid Firequel-L make
Supresta-USA
Normal Operating Pr.50 Ksc
Capacity 600 lpm
Fluid pump motor rating 200 KW
Filter material Ultipor
Mesh size 25
STEAM TURBINE

Lube oil system


Lube oil Tn-22C Russia Mobil DTE Oil light Teresso 32
In accordance with ISO VG 32
Absolute viscosity 16.7 Centipoise
Kinematic viscosity -32 Centistokes
Specific gravity 0.89
Flash point 180 0C
Fire point 240 0C

Oil requirement per bearing


N1 200 lpm
N2 200 lpm
N3 450 lpm
N4 280 lpm
N5 350 lpm
N6 350 lpm
N7 350 lpm
N8 350 lpm
N9 600 lpm
N10 600 lpm
STEAM TURBINE

Lube oil system


Total oil system capacity 52000 lit
Full volume of oil tank 58000 lit
Material of tank SS
Normal lube oil pressure 1.2 Ksc
Oil temp at inlet of bearings
Normal 55 0 C
Maximum 59 0C

Piping SS
Seal steam system
Source of gland sealing system
During normal operation End glands of HPC & IPC
During low load operation End glands of HPC & IPC + AS
Quantity of seal steam required 3.54 TPH
Seal steam pressure at turbine glands 1.1-1.2 Ksc
Seal steam temperature at turbine glands 160 0C
TURBINE SEAL STEAM

TWO HEADERS OR COLLECTORS ARE THERE i.e. HOT


COLLECTOR AND COLD COLLECTOR.
INITIAL SOURCE OF STEAM SUPPLY IS APRDS (UNIT
HT,16KSC,310OC).
PRESSURE AND TEMPERATURE OF COLD HEADER OR
COLLERTOR ARE 1.1TO1.15 KSC ABSOLUTE AND 140TO
180OC RESPECTIVELY.
PRESSURE AND TEMPERATURE OF HOT HEADER OR
COLLERTOR ARE 1.1TO1.15 KSC ABSOLUTE AND
RESPECTIVELY.
STEAM TURBINE

Turbine Protection
Over speed trip 110-112 %
Low lube oi pressure 0.3 (g) Ksc
Low vacuum trip 0.3 (abs) Ksc
Thrust bearing excessive wear trip +1.2/-2.0 mm
Pressure relief diaphragm setting 1.2 (abs) Ksc
STEAM TURBINE

Materials of construction
HP Outer casing 15Cr1Mo1V
HP blade/carrier casings 15Cr1Mo1V
IP Outer casing 15Cr1Mo1V
LP inner casing Steel 3
LP Outer casing Steel 3
HP Shaft 25Cr1Mo1V
IP Shaft 25Cr1Mo1V
LP Shaft 26CrNi3Mo2V
Moving blades
HPT first stage blades 18Cr11MoNiVNb (1-5)
HPT other stages 15Cr11MoV (6-17)
IPT first stage 18Cr11MoNiVNb (1-3)
IPT other stages 15Cr11MoV (4-11)
LPT last stage 13Cr11Ni2W2MoV
LPT other stages 20Cr13 (1-2)
LPT other stages 15Cr11MoV (3-4)
STEAM TURBINE
Fixed blades
HPT first stage 18Cr11MoNiVNb (1-5)
HPT other stages 15Cr11MoV (6-17)
IPT first stage 18Cr11MoNiVNb
IPT other stages 15Cr11MoV
LPT first stage 12Cr13 (1-4)
LPT Other stages 08 Cr13 (5)
Number of stages
HPT
Impulse stages 1
Reaction stages 16
IPT
Impulse stages 22
Reaction stages 0
LPT
Impulse stages 20
Reaction stages 0
All rows of blades are integrally shrouded
STEAM TURBINE

No. of HP Stop valves 2


No. of HP Control valves 4
Type of control valve unit Block united
No. of IP Stop valves 2
No. of IP Control valves 4
Type of control valves Separate
No. of Journal bearings for turbine 8
No. of Journal bearings for Gen 4
No. of thrust cum journal bearing 1
Type of thrust bearing Tilting
Type of journal bearing 6-Fixed & 2-Tilting pad
Material of bearing shell Alloy steel
Type of lining Babbit
LPT diaphrams 4

STEAM TURBINE

Turbine model No K-660-247


Generator model No TBB-660-2T3
Strainers are installed in the steam chests of the stop valves
In HPT, having passed the control stage and 8 stages which
generate left jet of steam (from generator towards front
bearing) steam changes its direction 180 and flows between
internal and external cylinders to 8 stages of right jet (towards
generator)
In CRH lines, NRV has a bypass with electric valve and control
valve to enable counter flow mode of HPT with the aim of
warming up of cylinder and high pressure cross over pipes at
turbine start up and cold condition
HPT has nozzle steam distribution system
IPT has throttle steam distribution system
On each upper half (cover) of low pressure cylinder four
membrane type relief valves are installed which are activated
when the absolute pressure in exhaust nozzles rises up to 1.35
1.4 Ksc absolute
TG SEAL STEAM SYSTEM
HPT SEAL STEAM CONNECTION

TO BLED STEAM TO LPH # 4

1ST CHAMBER 2ND CHAMBER

HPT

TO 2nd CHAMBER EXHAUST


TO HOT SEAL STEAM HEADER TO BLED STEAM TO D/A

TO GSC
IPT SEAL STEAM CONNECTION

IPT

TO COLD SEAL STEAM HEADER

TO GSC
LPT SEAL STEAM CONNECTION

LPT

FROM COLD SEAL STEAM HEADER

TO GSC
IN HIGH PRESSURE DRAINAGE EXPANSION TANK A VALVES IN DRAINAGE COLLECTORS FROM EXTRACTION
STEAM PIPES TO HPHs (10MAL20AA110, 10MAL20AA120, 10MAL20AA140) AND IN LOW PRESSURE
DRAINAGE EXPANSION TANK VALVES IN DRAINAGE COLLECTORS FROM EXTRACTION STEAM PIPES TO
LPHs(10MAL30AA110, 10MAL30AA120) CLOSE AUTOMATICALLY IF TURBINE LOAD INCREASES OVER 200MW
AND AT THE SAME TIME ALL VALVES ARE OPEN IN THE CORRESPONDING STEAM EXTRACTION FROM THE
TURBINE TO HPHs AND LPHs.
VALVES IN DRAINAGE PIPES OF HPBP AND LPBP (10MAL30AA107, 10MAL30AA108) CLOSE AUTOMATICALLY IF
TURBINE LOAD INCREASES OVER 30MW.
CONTROL FLUID SYSTEM

FIRE RESISTANT SYNTHETIC HYDRAULIC FLUID FYRQUEL L MANUFACTURED BY SUPRESTA IS USED AS


OPERATING FLUID.ITS SELF IGNITION TEMPERATURE IS ABOUT 740OC.
OPERATING PRESSURE IS APPROXIMATELY 50KSC.
OPERATING TEMPERATURE IS 45-55OC.
CONTROL OIL SUPPLY UNIT CNSISTS OF A RESERVOIR (10MAX10BB001)OF CAPACITY 7.0m3 ,2NOS.OIL
COOLERS(10MAX10AC001,10MAX10AC002),DE-AERATOR,MESH FILTER,FINE FILTER(10MAX18AT001),DUPLEX
FILTER(10MAX14AT001) AND 2 NOS. OF VERTICALLY MOUNTED CENTRIFUGAL
PUMPS(10MAX11AP001,10MAX12AP001) DRIVEN BY AC MOTOR (1W+1S).EACH PUMP IS HAVING A CAPACITY
OF 36m3/h AND DISCHARGE PRESSURE IS 50KSC.
CONTROL FLUID RESERVOIR IS SEPERATED BY TWO NUMBERS OF TANDEM MESHES OF CELL SIZE 0.25mm
INTO TWO SECTIONS ,DIRTY AND CLEAN. DE- AERATOR IS INSTALLED INSIDE THE RESERVOIR INFRONT OF
MESHES AND IT CONSISTS OF SLOPING PLATE ASSEMBLY.
CF FINE FILTER FOR REMOVING MECHANICAL IMPURITIES IS INSTALLED IN RESERVOIR. DURING NORMAL
OPERATION CF IS SUPPLIED TO THE FINE FILTER THROUGH AN ORIFICE OF DIAMETER 4mm FROM
UNSTABILIZED PRESSURE LINE VIA VALVE 10MAX18AA501 . AFTER THAT IT IS DISCHARGED IN THE DIRTY
CHAMBER OF THE RESERVOIR. WHEN TURBINE IS STOPPED CF IS SUPPLIED TO THE FINE FILTER WITH THE
HELP OF ANOTHER PUMP (CF TRANSFER PUMP,10MAX19AP001,CAPACITY 4m3/hr, AND DISCHARGE
PRESSURE 25KSC) VIA VALVES 10MAX19AA503 AND10MAX19AA504 FOR FILTERING PURPOSE KEEPING
MAIN PUMPS IN OFF CONDITION.
OIL PURIFICATION IS CONTINUOUS DUE TO FILTERING OF ITS PART VIA CONCURRENTLY MOUNTED WORKING
FILTER CARTRIDGES INSTALLED INSIDE THE FINE FILTER HOUSING.
FILTER CARTRIDGES DESIGN ALLOWS USAGE OF DIFFERENT FILTERING MATERIAL.

METAL SEMI-PINCEBECK MESH WITH FILTERING DEGREE OF 70 MICRONS TO FLUSH SYSTEM AFTER
INSTALLATION OR MAINTENANCE.

FILTER BELTING FABRIC WITH FILTERING DEGREE 30 40 MICRONS FOR PRIMARY REFINING DURING
TURBINE OPERATION.

FILTERING ELEMENTS MANUFACTURED BY PALL WITH FILTERING DEGREE 12 MICRONS FOR


CONTINUOUS OIL FILTERING DURING TURBINE OPERATION.

OCCURRENCE OF PRESSURE OF 0.1 TO 0.3KSC IN FILTER HOUSING WITHIN 1-3 HOURS SHOWS CORRECT
ASSEMBLY OF FILTER AND ITS PROPER OPERATION.
IT IS NECESSARY TO SWITCH OFF THE FINE FILTER AND REPLACE FILTERING ELEMENTS IF PRESSURE IN
FILTER HOUSING RISES UPTO 2KSC.WHICH SHOWS CONTAMINATION OF FILTER FABRIC.
INSIDE FILTER HOUSING THERE IS A RELIEF VALVE BYPASSING FLUID BESIDES FILTER CARTRIDGES WHEN
THEY ARE CONTAMINATED AND PRESSURE RISES UPTO 5KSC.
AN OIL LEVEL GAUGE WITH ALARM SYSTEM WHISKERS (10MAX10CL001,10MAX 10CL002) IS PROVIDED IN
THE CLEAN SIDE OF THE RESERVOIR.
NORMAL OPERATING LEVEL IS 700mm FROM THE UPPER COVER (30 GRADUATION OF L.G.) AND THE
AMOUNT OF CF IS 2.5m3
MAXIMUM ALLOWALABLE UPPER LIMIT (WITH CF PUMPS IN STOPPED CONDITION) IS 150mm FROM THE
UPPER COVER (85 GRADUATION OF L.G.) AND MINIMUM OPERATING LEVEL IS 800mm (20 GRADUATON OF
L.G.) FROM THE UPPER COVER.
CF PUMP STOPS AUTOMATICALLY INCASE OF RESERVOIR OIL LEVEL LOW-LOW.
FOR VISUAL OVSERVATION OF OIL LEVEL ,LEVELGLASSES HAVE BEEN PROVIDED IN THE BOTH SIDES (DIRTY
AS WELL AS CLEAN).
DIFFERENTIAL PRESSURE SWITCH (10MAX10CP001) HAS BEEN PROVIDED TO WARN ABOUT INCREASE IN
PRESSURE DIFFERENCE IN SIDE THE MESH FILTER. ALLOWABLE DIFFERENCE IN MESHES DOESNOT EXCEED
150mm.
THE STANDBY CF PUMP STARTS WHEN THE RUNNING ONE TRIPS OR SYSTEM PRESSURE DROPS TO 36KSC.
IT TAKES 2 MINS FOR THE SYSTEM TO GET PRESSURIZED.
IF SYSTEM PRESSURE DROPS TO 20KSC (10MAX14CP001) AND STOP VALVES START CLOSING ,THE
OPEARTING PUMP WILL STOP AND NO SIGNAL WILL BE GENERATED TO START THE STAND BY PUMP (SENSING
OIL LEAKAGE).
CF PUMP ALSO TRIPS ON FIRE PROTECTION.
DUPLEX FULL PASSAGE FILTER WITH FILTERING DEGREE 20-25MICRONS IS INSTALLED IN GENERAL
PRESSURE COLLECTOR OF CONTROL SYSTEM.IF PRESSURE DIFFERENCE (10MAX14CP301,10MAX15CP301)
ACROSS THE RUNNING FILTER REACHES 0.8KSC,THE STANDBY FILTER HAS TO BE TAKEN INTO SERVICE.
2 NOS.OF CF COOLERS (A&B) ARE INSTALLED IN THE CF SUPPLY LINE BEHIND THE DUPLEX FILTER. THESE
COOLERS ARE DOUBLE PASS (BY WATER) SURFACE HEAT EXCHANGERS WITH TUBULAR DESIGN ,WATER
STREAM FLOWS INSIDE THE TUBES AND CONSIST OF 148 TUBES OF SIZE 16X1500mm AND HEAT
EXCHANGE AREA 25m2.CF FLOWS FROM TO DOWNARD.
COOLERS ARE DESIGNED FOR A MAXIMUM COOLING WATER PRESSURE OF 10 0.5KSC AND CF PRESSURE
OF 68.7 0.5KSC.CF FLOW RATE TO EACH COOLER IS 50m3/hr AND PRESSURE DROP IS 0.2KSC. CW
FLOW RATE TO EACH COOLER IS 80m3/hr AND PRESSURE DROP IS 0.194KSC.
FOR HYDRODYNAMIC FLUSHING OF PIPELINES DURING MAINTENANCE,THERE IS A BYPASS VALVE
(10MAX14AA501)TO THE COOLERS WHICH SHOULD BE CLOSED AND SEALED DURING ROUTINE OPERATION.
IN THE INPUT AND OUTPUT TO THE COOLERS CF LINE IS PROVIDED WITH TRIPLE-PASS SWITCHING OVER
VALVES WHICH PREVENT FALSE ACTIVATION OF BOTH COOLERS.
CF TEMPERATURE IS MAINTAINED (48-52OC)BY COOLING WATER FLOW VARIATION WITH THE HELP OF A
FLOW CONTROL STATION CONSISTING OF A PNEUMATIC CONTROL VALVE (10PGM20AA001) AND A BYPASS
MOTORIZED CONTROL VALVE(10PGM20AA002).IN CASE TEMPERATURE RISES TO 55OC
(10MAX14CT001,10MAX14CT002),MOTORIZED BYPASS VALVE OPENS TO MAINTAIN THE CF TEMPERATURE.
THE MAXIMUM LIMIT OF CW TEMPERATURE AT COOLER INLET IS 37OC.IF CW TEMPERATURE IS BELOW 36OC
ONE COOLER CAN BE PUT OUT OF OPERATION.
CF SUPPLY TO CONTROL UNITS IS CARRIED OUT BY TWO PRESSURE COLLECTORS OF STABILIZED AND
UNSTABILIZED PRESSURE.
CF IS SUPPLIED TO UNSTABILIZED PRESSURE COLLECTOR THROUGH AN ORIFICE OF SIZE 22mm. STOP AND
CONTROL VALVE ACTUATORS ARE FED FROM THIS COLLECTOR.
INTO STABILIZED PRESSURE COLLECTOR WHICH FEEDS OIL TO ALL CONTROL DEVICES,CF IS SUPPLIED FROM
THE SECTION BETWEEN PUMPS AND THE ORIFICE.
DUE TO THE ARRANGEMENT MENTIONED ABOVE ,THE PRESSURE VARIATION IN UNSTABILIZED PRESSURE
COLLEECTOR CAUSED BY INCREASE IN CF CONSUMPTION WITH OPEN ACTUATORS AFFECTS IN A LESS
DEGREE PRESSURE VARIATION IN STABILIZED PRESSURE COLLECTOR.
SPRING-WEIGHT ACCUMULATOR (10MAX20BB001) IS CONNECTED TO UNSTABILIZED PRESSURE COLLECTOR
TO PREVENT DECREASE IN FORWARD PRESSURE IN CASE OF LOSS AC SUPPLY TO THE PUMPS FOR 5-7SECS
OR DURING PUMP CHANGE-OVER.
THE SETTING OF FLUID PRESSURE LEVEL (45KSC) TO BE ENSURED BY THE ACCUMULATOR IS DETERMINED
BY A WEIGHT WHICH IS CONCRETE FILLED IN THE SITE.
ONE NRV IS INSTALLED IN THE LINE CONNECTING THE ACCUMULATOR TO THE UNSTABILIZED PRESSURE
COLLECTOR. ACCUMULATOR IS FILLED WITH THE CF THROUGH AN ORIFICE OF SIZE 5mm INSTALLED IN THE
BYPASS LINE OF THE NRV.
TWO EXHAUST FANS (1W+1S) ,10MAX21AN001,10MAX21AN002 (CAPACITY OF 3200m3/hr AT A HEAD OF 5-
20mm OF WATER COLUMN) ARE ALSO INSTALLED TO REMOVE CF VAPOUR FROM CF RESERVOIR AND
SYSTEM.
THE EXHAUSTER SWITCHES ON AUTOMATICALLY WHEN CF PUMP STARTS AND SWITCHES OFF
AUTOMATICALLY WITH 15mins TIME DELAY AFTER THE STOPPING OF CF PUMP AND CF SYSTEM PRESSURE
DROPS BELOW 2.0KSC.
HYDRAULIC TEST OF PIPE LINES CARRIED OUT AT A PRESSURE OF 90KSC.HYDRAULIC TEST SHOULD BE
CARRIED OUT AFTER ASSEMBLING,OVERHAUL AND INSPECTION.
CONTROL FLUID SYSTEM
CONTROL FLUID SYSTEM

Isolation valves on pump suction & discharge side


Pump discharge pressure 50 Ksc
Capacity 41 TPH
Stabilized pressure header supply oil to servo motors of SV & CV
Un stabilized pressure header with 22 mm orifice
Accumulator in unstabilized pressure header
CF tank capacity 6.9 m3
Duplex filter
Control fluid transfer pump to empty the CF tank
CF Temperature control by control station in the ECW line
COMPONENT OF GOVERNING SYSTEM

1. ELECTRO-HYDRAULIC CONVERTER SUMMER 8 NOS.


2. SUMMER 8NOS.
3. ELECTRO-MECHANICAL CONVERTER 8NOS.
4. GOVERNING BLOCK

1. CONTROLGEAR(AE001) 1NO.
2. EMERGENCY GOVERNOR OR OVERSPEED GOVERNOR 1NO.
3. TRIP SOLENOID (AA213,AA214)-2NOS.
4. TEST ELECTROMAGNETS(AA211,AA212) 2NOS.
5. ROTATIONAL SPEED DETECTOR -3 NOS.
6. LIMITER OF PRESSURE (AA502) 1NO.
7. SPEED TRANSDUCER 1NO.
8. LEVER OF OVER SPEED GOVERNOR (AX201) 1NO.
9. PILOT VALVE FOR SUPPLY (AX202) 1NO.

5. ACCUMULATOR 1NO.
6. OIL SUPPLY AND PURIFIER UNIT
7. SERVOMOTOR OF HPSV 2NOS.
8. SERVOMOTOR OF HPCV 4NOS.
9. SERVOMOTOR OF IPSV 2NOS.
10. SERVOMOTOR OF IPCV 4NOS.
11. SERVOMOTOR OF CRH NRV 2NOS.
12. LOCKING PILOT VALVE (AA001,AA002,AB001,AB002)- 4NOS.
13. EX.STOP VALVE SERVOMOTOR OR ESV (10LBQ10AA101) 1NO.
DIFFERENT TYPES OF OIL
1. HEAD PRESSURE LINE (STABILIZED,50KSC,10MAX15)
2. HEAD PRESSURE LINE ( NON-STABILIZED,50KSC,10MAX15)
3. LINE OF PROTECTION (50KSC,10MAX51)
4. LINE TO COCK THE OVERSPEED GOVERNOR SLIDE VALVE (50KSC)
5. CONTROL OIL LINE TO STOP VALVE SERVOMOTORS (50KSC,10MAX16)
6. CONTROL LNE TO SUMMATORS (35KSC,10MAX17)
TURBINE PROTRCTIONS

1. OUT OF TOLERANCE ROTOR OVERSPEED : ALARM AT 3300RPM AND TRIPPING AT 3360RPM


2. OUT OF TOLERANCE AXIAL DISPLACEMENT OF ROTOR:
TOWARDS FRONT BEARING BY 0.6mm (-0.6mm) -ALARM.
TOWARDS FRONT BEARING BY 1.2mm (-1.2mm) - TRIPPING.
TOWARDS GENERATOR BY 1.4mm (+1.4mm)A- ALARM.
TOWARDS GENERATOR BY 2.0mm (+2.0mm) - TRIPPING.

3. LUBRICATING OIL PRESSURE DROP: ALARM AT 0.70KSC AND TRIPPING AT 0.30KSC WITH 3SECS TIME
DELAY.
4. PRESSURE RISE IN CONDENSER:ALARM AT 0.15KSC abs. AND TRIPPING AT 0.20KSC abs. PROTECTION
IS INTRODUCED AUTOMETICALLY AT UNIT START-UP AFTER PRESSURE DROP IN CONDENSER LOWER THAN
0.15KSC abs. OR AT TURBINE SPEED INCREASE OVER 1500RPM. PROTECTION IS IN OPERATION UNTIL
STOP VALVES ARE OPEN
5. INCREASE OF BEARING VIBRATION: ALARM SOUNDS AT INCREASE OF VERTICAL OR TRANSVERSE OR
AXIAL COMPONENT OF VIBRATION ON ANY BEARING OF TG SET REACHES 4.5mm/s .TRIPPING OCCURS
WITH 2 SECS TIME DELAY AT INCREASE OF VERTICAL OR TRANSVERSE COMPONENT OF VIBRATION OVER
11.2mm/s ON ANY TWO BEARINGS OF TG SET.
6. RISE IN STEAM TEMPERATURE AT HPT OUTLET:
7. LIVE STEAM TEMPERATURE BEFORE TURBINE FALLS BELOW 470OC:
8. LIVE STEAM TEMPERATURE BEFORE TURBINE RISES ABOVE 565 OC:
9. STEAM TEMPERATURE BEFORE IV FALLS BELOW 500 OC:
10. STEAM TEMPERATURE BEFORE IV RISES ABOVE 593 OC:
11. MOT LEVEL LOW-LOW:
12. DRIP LEVEL HIGH-HIGH IN ANY HPH:
13. ANY FAILURE IN TURBNE CONTROL SYSTEM ELECTRONICS:
14. GENETERATOR PROTECTION:
15. FIRE PROTECTION OPERATED:
16. EPB PRESED.
TURBINE LUBE OILSYSTEM
LUBRICATION OIL SYSTEM IS DESIGNED TO SUPPLY OIL TO TURBINE AND GENERATOR BEARINGS IN ALL
TURBINE PLANT OPERATION MODES AND ALSO TO PROVIDE ROTOR JACKING OIL SYSTEM AND GENERATOR
SEAL OIL SYSTEM WITH OIL.
LUBRICATION OIL IS ISO VG 32 TYPE WITH FOLLOWING PROPERTIES:

ABSOLUTE VISCOCITY : 16.7CENTIPOISE


KINEMATIC VISCOSITY : 32CENTISTOKE
SPECIFIC GRAVITY : 0.89
SPECIFIC HEAT : 0.459Kcal/Kg Deg.C
FLASH POINT : 180OC
FIRE POINT : 240OC
DEGREE OF CLEANLINESS : 16/13 ISO 4406
PERMISSIBLE SUSPENDED PARTICLE SIZE : 25 MICRON
WATER CONTENT : <10PPM

LUBE OILTANK IS MADE OF STAINLESS STEEL AND HAVING A CAPACITY OF 58m3 . PROVISION IS MADE FOR
OIL TREATMENT INSIDE THE TANK BY PROVIDING TWO ROWS OF FLAT GRIDS WITH MESH DIMENSIONS
0.25mm LOCATED INSIDE THE TANK WHICH DIVIDES THE TANK INTO DIRTY AND CEAN COMPARTMENTS. THE
AIR SEPARATOR CONSISTING OF TILTED METAL PLATES SET IS INSTALLED TO SEPARATE THE AIR DISSOLVED
IN OIL.
THE OIL TANK HAS ATTACHMENTS FOR OIL DRAINING TO OIL TREATMENT PLANT FOR SLUDGE DRAIN AND TO
EMERGENCY TANK INCASE OF FIRE.
NORMAL OPERATING LEVEL IS 600mm FROM TANK TOP COVER.ALARM IS AT 500mm AND TURBINE TRIP IS
THERE AT 400mm.
4 NOS OF LUBE OIL PUMPS (SINGLE STAGE CENTRIFUGAL) ARE INSTALLED VERTICALLY ABOVE THE TANK .2
PUMPS (AUXILLIARY OIL PUMP) ARE ac MOTOR DRIVEN AND 2 PUMPS ARE dc (EMERGENCY OIL PUMP) MOTOR
DRIVEN.
ONE PUMP WITH ac MOTOR IS CONTINUOUS RUNNING AND OTHER IS KEPT STANDBY.
EACH ac PUMP IS HAVING A DISCHARGE CAPACITY OF 300m3/hr A DISCHARGE PRESSURE OF 4.3KSC.
EOP WLL START IN CASE OF LOSS OF AC.EACH EOP IS HAVING A DISCHARGE CAPACITY OF 250m3/hr AND A
DISCHARGE PRESSURE OF 2 KSC.FOR HIGHIER RELIABILITY EOP DELIVERS OIL DIRECTLY TO THE BEARING
BYPASSING COOLER AND THROTTLE VALVE.
TG LUBE OIL SUPPLY SYSTEM
TG LUBE OIL SYSTEM
TG LUBE OIL SYSTEM

Turbine oil is ISO VG 32


KV 20-23 CST at 500C
Acidity Number < 0.05 mg KOH/r
Viscosity index > 90
Bearings
HPT Front N1
HPT Rear N2
IPT Front (TB) N3
IPT Rear N4
LPT-1 Front N5
LPT-1 Rear N6
LPT-2 Front N7
LPT-2 Rear N8
Generator Front N9
Generator Rear N10
Exciter Front N11
Exciter Rear N12
TG LUBE OIL SYSTEM

DC Lube oil pump 1 No.

Equipment Capacity (m3/hr) Head (Ksc)

AC Lube oil pump 300 4.3


DC Lube oil pump 250 2.0

NRV & Isolation valve in each Lube oil pump


discharge line
Oil first goes to duplex filter instead of cooler
Coolers Bypass line with isolating valve
Hydraulic Pressure control valve maintains the
pressure at the center shaft level at 1.2 Ksc
PCV Bypass with throttling orifice which provides
lubrication even at fully closed control valve
TG LUBE OIL SYSTEM

Oil is first delivered to bearing brasses through


emergency tanks located on bearing cap
Emergency tanks capacity in m3
N1 0.43
N2 0.35
N3 0.75
N4 0.44
N5 0.44
N6 0.44
N7 0.44
N8 0.44
N9 0.5
N10 0.44
N11 0.1
N12 0.1
TG LUBE OIL SYSTEM

Lube oil temperature control by control station in the ECW


inlet line to Lube oil coolers
View glasses in the oil return line from each bearing
MOT Capacity 58 m3
Duplex filters fineness 25 m
Provision is made for oil cleaning by delivering a portion of
oil from the oil pressure pipe to the oil tank through the fine
cleaning filter with fineness of 12-15 m
Fresh oil is filled through the above filter only
Oil recirculation pump to purify the oil
Electrical oil heater of 152 KW capacity is provided for the
preliminary oil warming in the lubrication oil tank before
turbine start up by running the oil recirculation pump
Oil draining to Emergency lube oil tank in case of emergency
with MOV
TG LUBE OIL SYSTEM

Oil trap at the suction of the vapor extractor fans


Oil trap drain to lubrication oil tank
Jacking oil pumps suction also given from lube oil discharge header after
coolers & before control valve
TG JACKING OIL AND BARRING GEAR SYSTEM
Barring gear & Jacking oil system

Automatic barring gear engagement at the rotor stop


and barring gear disengaging at the start-up
High pressure oil supply for bearing inserts oil jacking
Barring speed 1.05 rpm
Motorized barring gear
Torque transfer from the barring gear motor to the
turbine shaft is carried out via three stage reducer and
free wheel clutch
Reduction gear first stage shaft end mounts special
handle for hand barring
Normal source for jacking oil pumps suction is from
lube oil pumps discharge header after coolers
JOP discharge pressure: 120 Ksc
Barring Gear & Jacking oil system

Dozing devices at each bearing of the Turbine & Generator


which contain strainer, NRV, orifice & isolation valve
Bearing jacking oil is supplied via separate lines for oil jacking
of inserts of bearing no: 4-9
Stand-by bearing insert oil jacking pump is not provided
as the system is designed to realize auxiliary functions
at turbine start-up. If this pump does not start when it is
required then also the turbine can be operated normally
without any bearing damage and disturbance of turbine
operation
Each bearing insert jacking oil line is equipped with
orifice only
Both pumps cut in/cut out is 1500/1500
Barring gear cut in/cut out is 1500/1500
Barring Gear & Jacking oil system

Bearing Insert Oil Jacking Pump is started automatically, if the rotor


neck displacement becomes more than 0.1 mm relative to the
insert of any of bearings No. 4,9 provided that the oil pressure to
rotor jacking is higher than 45 kg/cm2 or the turbine rotor
rotational speed is higher than 1500 rpm
Pump is stopped automatically, with time delay of 30 seconds, if the rotor
neck displacement is less than 0.1 mm relative to the insert of bearings
No. 4-9
GENERATOR SEAL OIL SYSTEM
GENERATOR SEAL OIL SYSTEM

Seal oil pumps suction from MOT


No Hydrogen side seal oil pump
Pumps re-circulation line directly to MOT
Coolers bypass valve
Magnetic filters 2 No. (1W+1SB)
NRV in the seal oil line after filters
DPR
DPR bypass manual control valve
GENERATOR SEAL OIL SYSTEM

Damper tanks 2 No.: 1 for TE & 2 for EE,


designed for oil supply to front and back
generator shaft seals with drop, specified by the
height of damper tank installation, and also to
seal at short-time interruption in oil supply, at
the moment of automatic transfer from working
pump to standby and at generator runback with
generator shaft seal pumps switched of
View glasses in return oil lines
Float hydraulic seal functions as SOT
Hydraulic seal overflows in to return oil header
No SOST
Provision of trap upstream of fans
Fans suction is from return oil header
GENERATOR STATOR WATER COOLING SYSTEM
STATOR WATER COOLING SYSTEM

Water tank not on the generator


Ejector to make vacuum over the water tank to prevent air
ingress
Ejector cooling by auxiliary cooling water
Air venting of Generator through Gas trap connected from
winding inlet and outlet headers
Gas trap to determine hydrogen present which will be
extracted from trap cap to gas analyzer
Coolers bypass valve
Ion exchanger-1 contains anion & cat ion in H-OH form to
maintain conductivity
Ion exchanger-2 contains anion & cat ion in Na-OH form to
maintain Ph if it decreases below 8
Ion exchanger-1 first will be put in to service for reducing
dissolved oxygen below 5.0 s/cm and then it will be put out
of service. Then Ion exchanger-2 will be put in to service to
increase the Ph value. If conductivity increases above 12.5
s/cm, Ion exchanger-2 to be stopped
STATOR WATER COOLING SYSTEM

Control valves at the inlet of individual Ion


exchanger circuits
DM water flow through ion exchanger is 1.5 to 2.0
m
No NAOH dozing system
Ion exchangers separate bypass lines
Mechanical filter at the inlet of Ion exchanger
circuit
Dissolved oxygen analyzer & Ph analyzer
Winding inlet valve for flow adjustment
Winding outlet valve for pressure adjustment
Normal make up from DM make up line &
emergency make up line from CST
Filter in the common make up line
Control station in the common make up line
GENERATOR GAS SUPPLY SYSTEM
GENERATOR GAS SUPPLY SYSTEM

Two Hydrogen manifolds to connect 16 cylinders each


Direct acting Pressure regulator installed on cylinder connecting line to Manifold
header to reduce the Hydrogen pressure from 175 Ksc to 10 Ksc
Total Pressure regulators 32
Safety valve on each manifold header which operates when the Hydrogen
pressure in the manifold exceeds 10.5 Ksc
MOV & NRV in each manifold header
Three CO2 manifolds to connect 17 cylinders each
Each manifold header contains MOV, NRV & Isolation valve
MOV with manual bypass valve at the inlet of CO2 heater
CO2 heater is steam heated
Steam source is from auxiliary steam system
Steam parameters: 15 Ksc & 210 0C
MOV in the steam inlet line
Steam exhaust will go to FWSV Dish flash tank
Manifold header pressure is 175-20 Ksc
Control station with Pressure regulator provided D/S of heater to maintain a
pressure of 2.0-2.2 Ksc with manual bypass valve
SV installed D/S of pressure regulator operates if the pr > 5.0 Ksc
Capacity of one cylinder 50 lit
GENERATOR GAS SUPPLY SYSTEM

One Hydrogen manifold is in operation under normal operating conditions


If the pr decreases below < 10 Ksc, an alarm will come and operator
connects the standby manifold and disconnects the first manifold
Two CO2 manifolds are in operation under normal operating conditions
If the pr decreases below < 20 Ksc, an alarm will come and operator
connects the standby manifold and disconnects the first manifold
Provision is given for emergency removal of hydrogen from generator itself
by providing a line with one manual isolating valve & 2 No. MOV
FLASH TANKS
DRAINS FROM THE TURBINE AND STEAM LINES ARE REMOVED TO TWO HP DRAIN FLASH TANKS - A
(10MAL10BB001) AND B (10MAL20BB001) AND ONE LP DRAIN FLASH TANK (10MAL30BB001)
BOTH THE HP FLASH TANKS ARE HAVING A CAPACITY OF 2.6m3. LP DRAIN FLASH TANK IS ALSO HAVING A
CAPACITY OF 2.6m3.
CONDENSER

Design LMZ
Design CW Flow 64000 m3/hr
Vacuum 77 mm Hg (abs) at 33 0C
89 mm Hg (abs) at 36 0C
No. of passes 1
Total no. of tubes 22.225 (OD)x0.71 (t) - 29920
22.225 (OD)x1.00 (t) - 2080
Tube material ASTM A-249 TP 304
Rated TTD 3.40C
DT of CW 100C
CONDENSATE EXTRACTION PUMP

Design flow rate 238.75 Kg/s


Discharge pressure 32.15 Ksc
Shut of head 395 m
Pump speed 1480 rpm
Power input 972.3 KW
No. of stages 6
Type of first stage impeller double entry
Depth 7.43 m
DE-AERATOR

Design Pressure 13 Ksc


No. of trays 896
Spray valves 132
Design temp for D/A 395 0C
Design temp for FST 250 0C
DRIP PUMP

Design flow rate 324.509 TPH


Discharge pressure 43 ata
Shut of head 306.7 m
Pump speed 1486 rpm
Power input 310.1 KW
No. of stages 5
Type of first stage impeller centrifugal, single entry
Depth 1090 mm
MDBFP

Pump flow 769.950 TPH


Suction temp 186.2 0C

BP Suction pr. 14.05 ata


BFP Suction pr. 21.01 ata
BFP Discharge pr. 335.78 ata
BFP Discharge temp. 187.9 0C

BP Discharge pr.22.01 ata


Shut of head 4830 m
BFP Speed 6275 rpm
BP Speed 1490 rpm
Normal R/C flow 220 TPH
HC Rated O/P Speed 6505 rpm
Outer casing type barrel
No. of stages 7
BFP warm up flow 15 TPH
TDBFP

Pump flow 1283.14 TPH


Suction temp 186.2 0C
BP Suction pr. 14.10 ata
BFP Suction pr. 28.24 ata
BFP Discharge pr. 335.83 ata
BFP Discharge temp. 187.8 0C
BP Discharge pr. 29.06 ata
Shut of head 4580 m
BFP Speed 4678 rpm
BP Speed 2098 rpm
Normal R/C flow 365 TPH
HC Rated O/P Speed 6505 rpm
Outer casing type barrel
No. of stages 7
BFP warm up flow 20 TPH
TDBFP GOVERNING SYSTEM
GOVERNING SYSTEM

PARTS OF GOVERNING SYSTEM


Hydraulic Accumulator (HA)
Remote switch (RS)
Lubrication system pressure relay (LSPR)
Trip Gear (TG)
Stop valve (SV)
Governor valve 1 (GV1)
Governor valve 2 (GV2)
Cut of pilot valve (COPV)
Electro mechanical converter (EMC)
Electro mechanical converter position transducer (ECPT)
Electronic control part (ECP)
Servo motor (S)
Governor valves position transducer (GVPT)
TDBFP TURBINE

Number of stages 9
Casing Split
Steam admission Dual
Steam pressure at inlet 20.82 ata
Steam temperature at inlet 469 0C

Turbine operating speed 4678 rpm


Steam consumption 61.4 TPH
Steam pressure at exhaust 0.128 ata
Turning gear speed 15 rpm
Type of governing system Electro-Hydraulic
Over speed type trip Centrifugal + electrical
JOP Not required
Lube oil tank capacity 10.97 m3
Lube oil Same as main turbine
TDBFP CONDENSER

CW flow 3000 TPH


Vacuum in the condenser 0.128 Ksc (abs)
Total no. of tubes 3312
Tube OD and thickness 22.225x1.06 mm
No. of water passes 2
Tube material ASTM A-249 TP321
TDBFP LUBE OIL SYSTEM
TDBFP EXTRACTION SYSTEM
TDBFP CONDENSATE SYSTEM
ACW SYSTEM
ACW SYSTEM

Suction header is from all the 4 CW inlet lines to


condensers
MOV at Suction header from CW line
MOV at SCS inlet
MOV at PHE inlet & outlet
Supply to
Ejector of Stator water cooling system
TDBFP vacuum pumps (4 No.)
Main turbine vacuum pumps (1 No. extra)
MOV at return header to CW line
TURBINE VACUUM SYSTEM
TURBINE HEATING FLANGES SYSTEM
AUXILIARY STEAM SYSTEM
CONDENSATE SUPPLY SYSTEM TO EXT NRVS
EXHAUST HOOD SPRAY
FEED WATER SYSTEM
TDBFP-A FEED WATER SYSTEM
MDBFP FEED WATER SYSTEM
LP DOZING & OXY TREATMENT SYSTEM
HP BYPASS SYSTEM
LP BYPASS SYSTEM

You might also like