You are on page 1of 14

The Project Cycle

THE LIFE CYCLE OF A CONSTRUCTION


PROJECT

SIX BASIC PHASES CONTRIBUTE TO DEVELOPING A PROJECT FROM AN IDEA


TO REALITY:

Concept and Engineering and Start-up and Operation or


Procurement Construction
feasibility studies Design implementation utilization
FIGURE 2-1 is a bar chart showing a typical chronology
for the steps in the project cycle.
1.) CONCEPT AND FEASIBILITY STUDIES

• Long before designers start preparing drawings, and certainly well


before field construction can commence, considerable thought must go
into broad-scale planning.

• Elements of this scale include conceptual analyses, technical and


economic feasibility studies, and environmental impact reports.
For example, location is fundamental to planning for a new industrial plant.

 Where can the plant be located to provide desirable, nearby employment for an
adequate supply of skilled, productive workers?
 What are the present and projected costs and customs associated with the labor
force?
 What will be the sociological and economic impact of this plant in the community?
 What will be the environmental impact?
Ex. COAL POWER PLANT
2.) ENGINEERING AND DESIGN
• 2 MAIN PHASES:

a) Preliminary engineering and design


b) Detailed engineering and design
a. PRELIMINARY ENGINEERING AND DESIGN

o It stress architectural concepts, evaluation of technological process


alternatives, size and capacity decisions, and comparative economic studies.
 To illustrate, in a high-rise building it determines the number and spacing of the
stories, the general layout of the service and occupied floor spaces, and the overall
design approach. In building construction, the architect has the primary
responsibility for preliminary design.

o In heavy construction, engineers are responsible for the preliminary design,


but they often need substantial input from professionals in the natural
sciences.

o Once preliminary engineering and design are essentially complete, there is


generally an extensive review process before detailed work is allowed to
proceed.
b. DETAILED ENGINEERING AND DESIGN
o It involves the process of successively breaking down, analyzing, and designing
the structure and its elements so that it complies w/ recognized standards of
safety and performance while rendering the design in the form of a set of explicit
drawings and specifications that will tell the constructors exactly how to build
the structure in the field.
o This detailed field is traditional realm of design professionals, including
architects, interior designers, landscape architects, and several engineering
disciplines.
o In addition to designing the structure itself, the design professional often
conducts detailed field studies to get good engineering information on foundation
conditions, slope stability, and structural properties of natural materials.
3.) PROCUREMENT
• 2 MAJOR TYPES OF ACTIVITIES:
a) Contracting and subcontracting for services of general and specialty
construction contractors.
b) Obtaining materials and equipment required to construct the project.

Allocation of responsibilities for these two functions varies widely, and it is


especially dependent on the contractual approach taken for a particular
project.
4.) CONSTRUCTION

• It is the process whereby designer’s plans and specifications are converted into
physical structures and facilities.

• It involves the organization and coordination of all the resources for the project-
labor, construction equipment, permanent and temporary materials, supplies and
utilities, money, technology and methods, and time- to complete the project on
schedule within the budget, and according to the standard of quality and
performance specified by the designer.
5.) START-UP AND IMPLEMENTATION

• As the project nears completion, it is important to be sure that all components


function well together as a total system.
• In some cases, this mainly involves testing, adjusting, and correcting the major
electrical and mechanical systems so that they perform at their optimum level.
• Often this phase also involves a warranty period during which the designer
and the contractors can be called back to correct problems that were not
immediately evident upon initial testing and to make adjustments to better
suit the facility to the owner’s needs after he has had a chance to try it out.
6.) OPERATION AND UTILIZATION

• The functional value of the project will depend upon the decisions and
implementation of the objectives developed during the preceding phases.
• With a projected life of 20 to 25 years or more, it is evident that the overall
cost and value to the owner throughout the operating life are determined
largely during the period from conception through start-up.
• In the case of major alterations or expansions, the operation phase can also
involve recycling through the first five phases of a project mentioned above,
whether the work is done in-house or by contract.
The End

You might also like