Bale Packing
by
Imranali Shaikh
(PDPU)
Process of Bale packing
Final Bale
Platting Checking Cutting Faming Packing
Packing
Platting
First the role will be connected in the platting
machine.
After this platting machine will fold the cloth
according to the required dimension.(e.g. 65cm
for bottom & 80cm for shirting)
Time taken at platting
Platting time
50
47.466
45
40
35
31.116
30
15
12.85
10
0
1 2 3 4 5 6 7
Checking
After platting the checking operation takes
place.
In this operation the inspection of platted cloth
is done by workers naked eyes.
For each batch there are two workers assigned.
In this operation if they find defect so they will
mark that defect by putting some small piece
of cloth inside the platted cloth.
Time taken at checking
Checking time
90
80 81.366
70
63.45
60 59.248
54.854 54.854 54.854 54.854 54.854 54.854 54.854
51.816
50
45.55 Checking Time
42.966
40 avg.
39.583
30
20
10
0
1 2 3 4 5 6 7
Cutting
In this stage the cutting of platted cloth is takes
place.
After checking the cloth will cut by the cutting
master(worker) according to required
dimensions.(e.g. in 160cm,640cm,1600cm)
The dimension are provided by the customer
and instructed to cutting master(worker).
In this stage the defected part is removed.
Time taken at cutting
Cutting time
70
60 59.716
56.366
50
31.066 avg.
30
20
10
0
1 2 3 4 5 6 7
Faming
In this stage the cloth will be folded by worker
in a folding machine.
Worker will fold the cloth and make a bale by
using folding machine.
Time taken at faming
90
faming time
80 80.183 79.866
70
63.7
60 61.239 61.239 61.239 61.239 61.239
61.166 61.239 61.239
55.248
50
48.733
Faming Time
40 39.783
avg.
30
20
10
0
1 2 3 4 5 6 7
Packing
Now in this stage the folded cloth(folded bale)
is packed.
In this stage the worker will put stickers
according to its specification.
After this the bale is packed in plastic bag.
Time taken at packing
80 Packing time
71.8
70 70.166
62.248
60
40 41.066
39.6 38.683 Packing Time
avg.
30
20
10
0
1 2 3 4 5 6 7
Final bale packing
Now in this stage the bale is first scanned by
its barcode sticker and according to its meters
and weight the bale is packed in a carton box
and the carton box is again packed in a large
plastic bags.
This whole process is done by the help of
software (software name :- NOW).
Time taken at final packing
Final packing time
14
13.25
12
11.733
10.85
10.583
10 10.116 10.116 10.116 10.116 10.116 10.116 10.116
9.683
9.416
6 avg.
5.3
0
1 2 3 4 5 6 7
Total time taken by the whole
process
Total time
300
277.728
268.248 263.814
255.497
250 249.464 250.814
249.464 249.464 249.464 249.464 249.464 249.464
233.581
200 196.566
100
50
0
RB17-005094-5 RB17-005094-6 RB17-005094-3 RB17-005094-1 RB17-004165-1 RB17-005094-4 RB17-004189-1
Average process time
Average
Average Average Average Average Average Final Average
SR. Platting Checking Cutting Faming Packing Packing Total
No Time Time Time Time Time Time time
0.6
0.5
0.4
Average = 0.511802701
0.3
0.2
0.1
0
RB17-005094-5 RB17-005094-6 RB17-005094-3 RB17-005094-1 RB17-004165-1 RB17-005094-4 RB17-004189-1