SAFETY FIRST

Site preparation

PT. PAKUBUMI SEMESTA..KAWASAN INDUSTRI PULO GADUNG , JL. PULO KAMBING RAYA NO.34-36,
CONTACT US AT PHONE : (021) 4682 4349 (HUNTING), FAX : (021) 4600 034, E-mail :
pakubumi@cbn.net.id
visit us via internet address : www.pakubumi semesta.com
SAFETY FIRST

Setting out drilling point using theodolite based on Bench Mark


provided on site location

Theodolite
Ruler

Bench Mark
Driving point

PT. PAKUBUMI SEMESTA..KAWASAN INDUSTRI PULO GADUNG , JL. PULO KAMBING RAYA NO.34-36,
CONTACT US AT PHONE : (021) 4682 4349 (HUNTING), FAX : (021) 4600 034, E-mail :
pakubumi@cbn.net.id
visit us via internet address : www.pakubumi semesta.com
Start drilling at the pile position
with auger

Installing preliminary casing ( 3 m )


Continue drilling till toe level with bucket drilling, beware of SAFETY FIRST
collapsible soil
Supply water to maintain water level in the drilling hole higher than
existing ground water level or supply slurry stabilizer if some soil
layer in the hole tend to collapse
SAFETY FIRST
After Drilling reach the toe level,
clean the hole base with cleanning
bucket
SAFETY FIRST
Installing reinforcement cage section
by section, and joint each section
with teck welding
SAFETY FIRST
Installing the tremie pipe as the
mean for pouring ready mix
concrete
SAFETY FIRST

Before pouring, check the slump of


the concrete and make concrete
cylinder / cube test samples

SLUMP TEST PROCESS


Cylinder or Cube Sample and Slump Test Equipment

Height of the required slump


SAFETY FIRST
Start pouring ready mix concrete
into the drilling hole
SAFETY FIRST
Finish pouring until the cut off level
+ 1 m bad concrete
SAFETY FIRST
Pulling out the tremie pipe after the
completion of pouring
SAFETY FIRST
Pulling out the steel casing before
the concrete initial setting occured
SAFETY FIRST
Pulling out the steel casing before
the concrete initial setting occured
SAFETY FIRST
Bored pile already installed
SAFETY FIRST
Soil (ex drilling) taking out from the
site
SAFETY FIRST
Soil (ex drilling) taking out from the
site