Torbjrn Einarsson 2004 Cigre SCB5 Session

Preferential Subject 3
ABB Question 8a
Sweden
ABB - 1
SC B5: PS3, Q 8a How to optimize settings?

What methodologies are used to optimize settings for


series compensated line application?

REAL TIME SIMULATIONS!


ABB - 2
Why real time simulations?

Real time simulations are very useful tool for the setting verification
process
Series compensated networks are normally very complicated
Analytical method more time consuming
Difficult to cover all combinations of fault conditions and the interactions
between IED`s and power system when using analytical methods
Difficult to foresee all the dynamic behavior when doing the setting
calculations
Voltage inversion, might cause directionality problem
Sub-synchronous oscillations, might cause overreach
Verifying the total protection scheme
Very good learning process
ABB - 3
Example of series compensated network
200 km
130 kV

SC

400 kV
250 km 100 km 400 km 170 km

130 kV P P 130 kV

350 km 130 kV
Equivalent source
130 kV
SC Shunt compensator
Three-winding power transformer
SC
Two-winding power transformer
Series capacitor with
over-voltage protection
Shunt reactor
P Line protection under test
ABB - 4