Guide to Site Implementation Managers in


On-site Construction Management

Site Design and Implementation Management


Dept. www.huawei.com

July 2007

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential


Contents
I. Introduction to Site Management
Value of the Site Implementation Management Dept.

Relations between Site Implementation Management and Project Management

Position of the Site Implementation Manager and Site Engineer in a Project

II. Organizational Environment That the Site


Implementation Managers Are Located in

III. Main Work and Main Supervisory Points of the


Site Implementation Managers

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 2


Introduction to Site Management Value of the Site Implementation Management Dept.
1. Characteristics of a Multiple sites, wide range, many products involved, short delivery
telecom project time
2. Shortcomings of the original The sites are not managed by a general owner; the problems are not
extensive project resolved quickly; the plan turns into a visionary scheme
management mode
Management Competency models of project delivery
requirement
3. How to manage the
project properly so Senior CRM
Team management
that the problems in General management
Competency
model of the
site building can be Procurement management
Scope change management current PM
resolved? Resource management Competency model of
Cost management implementation
Quality management managers
Supervision on progress Competency model
Communication & coordination of site engineers

Recognize the Apply the Carry out Application


process knowledge of on-site
Drive problem telecom civil work supervision
of skills
resolution
The persons are organized to ensure timely and effective supervision over the progress and quality
on the spot of site implementation.
Our capability of managing the project delivery is widened to close supervision on the site.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 3


Introduction to Site Management Relations between Site Implementation Management and
Project Management

Project Aim curve of site


management implementation
management
Project management in the
overall perspective

Project management in the


perspective of
implementation

Project management in the Function


perspective of site management

Site implementation Scope of business


management

Mass production management of sites + site management of the project


Aims of site
implementation Transition from the mass production management of sites to the site
management management of the project

Smooth curved transition of site implementation management is the aim


pursued in management.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 4


Introduction to Site Management Position of the Site Implementation Manager and Site
Engineer in a Project

PM

Regional Site Design and


representative office Implementation Dept. Regional RPM Regional RPM

Definition of site implementation


manager: Telecom IM Outsourced auxiliary products IM
Site implementation manager
An owner of civil work implementation
in a project, and a general manager of
the site engineers
Seek, cultivate and manage the site

team
Planning & design
team
Site acquisition

project team
Equipment system

Optimization team
engineers.

Definition of site engineer:


A primary owner of site construction in

team
Civil work design
implementation team
Auxiliary products
implementation team
Telecom equipment
implementation.
Responsibilities: In the period from Site engineers (1N)
receipt of the site building permit and
design drawings to the power-on
completion of hardware equipment,
the site engineer must be responsible
for planning, progress, quality, safety
and on-site construction management
of the site civil work, and must
supervise and manage the installation
of equipment hardware.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 5


Contents
I. Introduction to Site Management

II. Organizational Environment That the Site


Implementation Managers Are Located in

III. Main Work and Main Supervisory Points of the Site


Implementation Managers

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 6


Organizational Environment That the Site Implementation Managers Are Located in

Which organizational environment am I located


in?
Whom can I seek help from when I am in
trouble?

HUAWEI TECHNOLOGIES CO., LTD.


? Huawei Confidential Page 7
Organizational Environment That the Site Implementation Managers Are Located in

President of the
region

Operations Support
HR Dept.
Dept.

Information Security
Finance Dept.
Management Office

Vice president of sales Vice president of delivery Vice president of business

Product Marketing
Development Dept.
Qualification Dept.
Market Finance Dept.

Technical Service

Public Relations
Sales Management

Commercial Affairs

Support Dept.
Supply Chain

Procurement
Key Project Dept.

Marketing
Business

Dept.
Dept.

Dept.
Dept.
Dept.

Representative office 1

Regional division Representative office N

VIP CGMD

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 8


Organizational Environment That the Site Implementation Managers Are Located in

President of the
region

Four functional
President of the departments of the
regional division regional division

Sales Management Technical Service


Dept. Dept.

Finance Dept. Commercial Affairs


Dept.

Representative
Representative

Representative

Representative

Representative
office 4

office N
office 1

office 2

office 3

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 9


Organizational Environment That the Site Implementation Managers Are Located in

Representative

Vice representative
Operations Support HR Dept.

(cadre)
Dept.

Finance Dept. Information Security


Management Office

Vice representative of sales Vice representative of delivery


Sales Management

Qualification Dept.
Technical Service

Product Marketing
Market Finance

Relation Dept.
support Dept.
Supply Chain

Procurement

Government

Marketing
CGMD
Dept.

Dept.

Dept.

Dept.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 10
Organizational Environment That the Site Implementation Managers Are Located in
Technical Service Dept.
of the region

PM

Professional Service Dept.


Technical Service Dept. of

Service Marketing Dept.

Service Training Dept.


Engineering Business

Regional PM
each product line
Dept.

Planning control team

Operations support team


Composition
of the project Network planning and design
team team
Site Design and Implementation
Project Management Dept.

Site acquisition team


Network Planning Dept.
Management Dept.

The project team members Site implementation team


come from the representative
office, regional division and
even each functional Procurement qualification team
department of the region.
Supply chain team

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 11


Organizational Environment That the Site Implementation Managers Are Located in

What to do when you are in What? You


cannot manage?
trouble? Let me do it.

Issue Type See Help from

Issues related to recruitment, remuneration to site engineers, internal HR Dept. of the representative
incentive, and so on office
Issues related to office equipment, construction tools, vehicles, and so on Administrative Dept. of the
representative office
Goods issues (issues related to international transport and customs clearing Logistics Manager
of materials, warehouse management, and goods allocation)

Issues related to local material procurement CEG

Issues related to subcontractors CEG\Contract Manager

Other issues Project Manager

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 12


Contents
I. Introduction to Site Management

II. Organizational Environment That Site Implementation


Managers Are Located in

III. Main Work and Main Supervisory Points of the


Site Implementation Managers

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 13


Main Work and Main Supervisory Points of the Site Implementation Managers

Read the contract


and tender Management of
site engineers

Acceptance
managemen
t Schedule control

Materials
Demonstration
management What site and section
should I
do?
Changes
Quality
managemen
management
t

Management of Safety
documents on site Subcontractor
management management
construction

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 14


Main Work and Main Supervisory Points of the Site Implementation Managers Read the
Contract and Tender

Read them as soon as possible to learn the general policies and the policies
Requirement on subcontract and project management
Hold a contract clarification meeting to comprehend the contract better

Interface of work division


Read the contract

Technical specifications on civil work and outsourced auxiliary products


Delivery terms, exemption clauses and acceptance criteria for civil work
and tender

Site model
Focus on
Construction specifications
Schedule, delivery milestone, and punishment and liability for delay
Composition of civil work cost
Force majeure
Clauses concerned with changes

Excerpt the major clauses and pass them to all members concerned in the
Important project team
Notify the project manager of the infeasible clauses and those that may bring
about loss to Huawei

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 15


Main Work and Main Supervisory Points of the Site Implementation Managers Management of
Site Engineers

Recruited for the project or as regular employees


Competencies:
Source 1) Use English in the work
2) Work background of civil work or steel structure. Experience in telecom projects is preferred.
3) Able to operate computers
4) Character: active, work carefully, strong sense of responsibility

One site engineer every three to four teams or every 20 sites


Management of site

Establish a system of competition and last elimination, staffing the project with one to two more site
Staffing
engineers
engineers

Site construction process (refer to the company-released process and tailor it for the project)
Site engineers manual (refer to the company-released process and tailor it for the project)
Training Guide to site acceptance (refer to the company-released process and tailor it for the project)
Guide to safe construction of sites (refer to the company-released process and tailor it for the project)
Quality management of the sites (refer to the company-released process and tailor it for the project)
Internal management system and operation process of the project team (drafted by the project team)

Clearly define the responsibilities and work in a result-driven way


Define more details of the work of site engineers and measure the work quantity
Daily
Establish a clear report system
management
Require the subcontractor to submit pictures when the subcontractor proceeds to a milestone of the
site so that the site engineers can be relieved of the access to sites and thus can supervise more
sites.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 16


Main Work and Main Supervisory Points of the Site Implementation Managers Schedule
Control

Read the contract carefully to fully understand the promised delivery scope,
Make a sub-plan responsibility interface of delivery and key milestones of delivery
for the civil work
Fully communicate with the project manager and control manager to learn the delivery
policies of the whole project
Fully communicate with the customer, local subcontractor and local employees to learn
the delivery environment and characteristics. In the communication, focus on:
1) The period of time when the civil work implementation is affected
Schedule control

2) Local popular construction procedures, process and special regulations


Site rollout and 3) Local efficiency baseline of civil work
delivery
4) Local subcontractor resource
schedule
5) How to acquire the key construction materials locally and whether they can be
acquired easily
6) Local inland transport
7) Work habit of the local people
Talk with the subcontract CEG and logistics personnel about the subcontractor and
Supervise the materials preparation as well as the plan under which the subcontractor and materials
schedule are estimated to get ready.
execution
Make a sub-plan for the civil work based on the abovementioned plan and submit it to
the project manager.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 17


Main Work and Main Supervisory Points of the Site Implementation Managers Schedule
Control

Make a sub-plan Determine which sites are built first and which are built later, and guarantee the
for the civil work resource for these sites;
Work with the subcontractor to make a schedule for the key milestones of each site
Take the local special delivery environment into account;
If the subcontractors promise or the plan for arrival of materials cannot satisfy the
requirement of the master plan, report this situation to the CEG and cause the CEG to
Schedule control

seek more subcontractors. Additionally, drive the logistics department to resolve the
problems of materials arrival;
Site rollout and
delivery plan While assigning sites to the subcontractors and site engineers, note that:
1) The number of sites assigned to each subcontractor cannot exceed the ratio fixed
in the bid evaluation result of the CEG. If the number breaks through the ratio for
any special reason, apply to the CEG department through an internal memo;
2) The sites assigned to a subcontractor must be located in the same region and on
the same traffic line. The sites of a high priority level must be assigned to a
subcontractor of high qualification;
Supervise the
schedule 3) The sites assigned to a site engineer must be centralized in the same region and
execution on the same traffic line, and managed by one subcontractor.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 18


Main Work and Main Supervisory Points of the Site Implementation Managers Schedule
Control

Make a sub-plan
for the civil work

CW forecast

Receive and transfer the task;


Schedule control

Arrange a check of the resource preparation, and cause the issues to be resolved;
If the plan delivered deviates from the specific implementation plan so greatly that the
Site rollout and
construction task cannot be complete, report this situation to seek for a solution;
delivery plan
Follow up on the reported result every day. Meet the site engineers and the
subcontracts routinely at least once each week to analyze the quality and progress;
For a delayed working procedure of a site, the subcontractor must rush through the
work to catch up with the schedule;
On each day, summarize the latest construction situation and send it to the business
module concerned or input it in the server for it to be shared by all modules;
Supervise the
Set more dense supervisory points than those fixed in the rollout table to control the
schedule
execution civil work progress of the site and get command of the statue quo of site
implementation. Supervise the civil work progress with the small tool in the CW
forecast attached above in this page.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 19


Main Work and Main Supervisory Points of the Site Implementation Managers Demonstrative
Site and Section
Build a general model site, demonstrating how each subcontractor should build its own model
site. These model sites together with the technical specification, quality standard and
Function acceptance criteria determined with the customer and subcontractors must be followed in
building the massive sites later.

Determine the specific site to be built as a model


1. Set a scheme for building a one for demonstration purpose
Demonstrative site

general model site Determine the subcontractor to build the site


Make a building plan
and section

2. Build the general model site

3. Verify the project quality standard and determine the


Steps acceptance criteria based on the general model site

4. Compile the pictures of the general model site complying


with the project quality standard into an album

5. Each of other subcontractors must build the first site into


its own model site.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 20


Main Work and Main Supervisory Points of the Site Implementation Managers Quality
Management

Quality Management Runs through the Whole Construction Project


Pre- Preparation before
sales Network planning Site acquisition Site design A
project kickoff
support

Supporting Guide to Preparation before Network Planning Guide Site Acquisition Process Site Design Process
Process or
Guide Project Kickoff

Review the project planning Review the network planning Review the site preselection Review the typical module
Key quality Build a general model site design
activities TSSR review
Training before project kickoff
Review the design document
Determine the project quality Acceptance of site acquisition
standard and acceptance
criteria
A Site building Engineering survey Equipment Acceptance to Mainte
installation maintenance nance
Supporting Process of Building Wireless Sites on Site Survey Process Equipment Installation Process Process of Transferring
Process or Ground Surface Acceptance to Maintenance
Guide

Review of the material requirements Review the Survey On-site inspection of goods Acceptance test
Key quality
Quality inspection of concealed works Report Hardware installation check Review of the cutover
activities
Quality inspection of construction of Software installation check scheme
outsourced auxiliary products Documents review

Internal acceptance of the civil work PAT of a single site

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 21


Main Work and Main Supervisory Points of the Site Implementation Managers Quality
Management
Key Quality Management Activities of the Building Managers

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 22


Main Work and Main Supervisory Points of the Site Implementation Managers Quality
Management

Six Key Points in Quality Management

Determine
the quality The activities of project
standard
quality management run
through the whole process
Count, analyze Build a
and clear the
of project implementation.
demonstrative
quality issues site The six quality activities
Site listed on the left are key
implementation
points of quality control.
manager
Random Training of A project will be
inspection of subcontractors and implemented at good
quality by site site engineers before
engineers project kickoff quality if the six key points
of quality control are
100% self-check executed well.
of construction by
subcontractors

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 23


Main Work and Main Supervisory Points of the Site Implementation Managers Safety
Management

Reference: Guide to Safe Construction of Wireless Sites


Management measures of safety in production:
Ask the subcontractor to make a safety management plan prior to the
commencement of its work, and review the plan
Organize training and assessment of the subcontractor personnel
Ask the subcontractor to check the safety control measures by itself
Sign an instrument setting out the responsibilities for safety in
construction
Cause the site engineers to supervise at any time the safety in
construction by the subcontractor

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 25


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Subcontractor Management in Implementation

Before
implementation Kickoff Implementation Acceptance
(resource meeting (implementation (acceptance
establishment) management) and payment)

Joint review of design


Meet the and technical Organize and plan the Acceptance of the
subcontractors clarification construction construction quality

Assess the Review the construction Establish a mechanism Acceptance of the


subcontractors schedule of communication quantities of work

Review the document Determine the Supervise the key


calling for bid points Payment support
acceptance scheme

Review the The subcontractors


subcontract get ready

Hand over the


building permit

Determine the mode


of communication

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 26


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Meet the Subcontractors

Meet the subcontractors to learn:


How they implement similar projects locally;
Their estimate of the duration of similar projects implemented locally
based on their experience;
Standard work hours of each key step in site building;
Their estimate of the main difficulties in implementing the project locally
based on their experience;
How they plan to overcome these difficulties
Their suggestions on implementation of the project

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 27


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Subcontractor Assessment Items

Awards received
Experience and background Machine to be used
of the responsible person

Past experience in
similar projects Work and
technical force

General control over Organizatio


the project n

Quality and safety Construction


assurance method

Schedule and
Management skills
measures to keep
Material
up with the
s
schedule

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 28


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Kickoff Meeting
Chairperson: Huawei project manager or implementation manager
Participants: design, logistics and site engineers concerned, subcontractors
Agenda of the kickoff meeting:
Joint review and technical clarification of the design;
Discuss and adopt the Design of Construction Organization and General Schedule
submitted by the subcontractors;
Determine the checking criteria, checking list and acceptance scheme;
Confirm that the construction personnel and machine are ready, and fix the date of
commencement;
Hand over the Building Permit to the subcontractors, if necessary;
Determine the mode of communication.
The person appointed by Huawei must prepare the Minutes of Meeting on the spot and have it
signed by three parties.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 29


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management
Establish a Mechanism of Communication with the
Subcontractors
The mechanism of communication between Huawei and the subcontractors
addresses the following aspects:
Appoint the contact persons who are available at the fixed time and
have clear responsibilities;
Establish a system of routine meeting (one meeting each week);
Establish a hierarchical communication channel between both parties;
The site implementation manager gives instructions to the
subcontractors based on the standard instruction templates.
Attached: Set of On-site Instruction Templates

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 30


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Assigning Sites to the Subcontractors

Assignment principle:
The sites assigned to a subcontractor must be located in the same
region;
The sites in a region must be assigned to two or more subcontractors;
The number of sites assigned to a subcontractor in one attempt under a
PO must take the subcontractors production capacity into account.
Generally, one to two sites over a subcontractors maximum production
capacity can be assigned to the subcontractor.
One site engineer must be appointed to manage the sites assigned to a
subcontractor.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 31


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Supervision over the Subcontractors


Supervise each subcontractor in the following perspective:
Personnel and machine input in the project: Irregularly check, without a prior notice on the
subcontractor, whether the quantity of staff and machine input in the project is the
promised quantity and whether the staff competencies satisfy the project requirement.
Materials: Irregularly check, without a prior notice, the subcontractors warehouse to see
whether sufficient materials are stored.
Progress: Check the sites constantly to determine whether the subcontractor keeps up
with its promised schedule.
Quality: Determine a quality standard with the subcontractor based on the subcontract
definition, centralized training of the subcontractors, and access to the demonstrative site
and section. Inspect the quality control points in implementation based on Huawei-
released quality management requirements.
Cash flow: Supervise the cash flow of the subcontractor to avoid any stoppage of work
caused by delayed payment by Huawei.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 32


Main Work and Main Supervisory Points of the Site Implementation Managers Subcontractor
Management

Acceptance and Payment


Acceptance of the
construction quality
Payment support
Acceptance of the
quantities of work

Acceptance of the construction quality: Rely on the project-specific Quality


Acceptance Form.
Acceptance of the quantities of work: Rely on the Bill Of Quantities (BOQ) of the
PO/VO.
For the details of acceptance, refer to the Guide to Acceptance of Site
Construction Projects .
The site implementation manager must give attention to the payment to
subcontractors. The subcontractors can work contentedly and effectively only
after they get paid.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 33


Main Work and Main Supervisory Points of the Site Implementation Managers Management of
Documents on Site Construction

Key points of management of construction documents:


The documents on site construction must be archived by site folder. The
documents of each site are archived in one folder.
The requirements for archiving the construction documents vary from project to
project. In the initial phase of a project, the site implementation manager must
fully communicate with the customer and the project team members to determine
the final archiving requirement.
After defining the document demand, the site implementation manager should
hold a special meeting to convey the site document requirement to the
subcontractors and site engineers.
Within one week after construction completion of a site, the site engineer must
submit the folder of the site to the documentation controller for review and
archiving.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 34


Main Work and Main Supervisory Points of the Site Implementation Managers Management of
Documents on Site Construction
List of documents in a site folder

Site design documents, including all the records on design changes and on the design
1
documents obtained by each subcontractor
2 BOQ of the site
3 Self-check List of Key Actions in Site Construction
4 Site Quality Checklist, including the acceptance records on concealed works
5 Record on Safety Inspection of the Site
6 Change records
7 Pictures evidencing the site clean-up
8 Pictures evidencing the site quality and safety issues
9 Preliminary Acceptance Record of the Site
10 Records on negotiation with the subcontractor
11 Inspection Report on the Test Block

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 35


Main Work and Main Supervisory Points of the Site Implementation Managers Changes
Management

Changes Management

Strictly control the project changes made by each subcontractor;


Require each subcontractor to give an option quotation, and set forth and
strict the items to be changed;
In implementation, each subcontractor can make changes under the restrictive
conditions of change, and must undertake the extra work at its own cost.
Changes to any item without a unit price cannot be effected unless and until the
unit price is fixed;
Define a project change process, requiring the subcontractors to acquire
authorization and permit from Huawei before they make any changes;
Drive the design engineer to manage the version of site design documents so
that the design documents available to the site engineers and construction
subcontractors are of the latest version.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 36


Main Work and Main Supervisory Points of the Site Implementation Managers Materials
Management

Purchase Policies for Towers

Tower materials are first needed by the civil work of each site, but have a long
lead
time and construction period. They require close attention in a project.

Design the towers into unified patterns to reduce the tower types;
Locally purchase the towers or the first batch of towers;
Require the tower suppliers to first produce and deliver anchor bolts;
It is suggested that the project team should purchase the tower supervision
service;
The site implementation manager can use the small tool of tower management;
Refer to the document Site Ready For Tower vs Delivery FC attached.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 37


Main Work and Main Supervisory Points of the Site Implementation Managers Materials
Management

Key Points of Material Purchase

In purchasing diesel generators, confirm with the customer the brand, technical
specifications and other technical parameters of the selected diesel generator shelter, and
pay attention to the local after-sales service capability of the selected diesel generator
suppliers.
ATS is available in a wide variety, the auxiliary materials set forth in the purchase order must
be correct;
Confirm with the customer the technical specifications of the auxiliary materials after the
contract is concluded but before Huawei places a purchase order of material preparation;
Cement, sandstone and reimbursement bars are generally provided by the subcontractors.
Check these materials;
For key materials, appoint a person to specially review the electronic packing list before the
delivery to ensure the goods to be delivered agree with the purchase order placed earlier.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 38


Main Work and Main Supervisory Points of the Site Implementation Managers Materials
Management
Case: Standard Lead Time of Key Materials in South
Africa
Material Sub- Standard Lead Time Qualificatio Time for Remarks
category n Period Applying
for Code
Tower 45 days (less than 100 towers in 5 days 5 days Tower made in China
no more than four tower
patterns)
Micro wave 8 weeks (PDH and SH-SDH) or 5 days 5 days Micro wave of a global
12 weeks (LH SDH) or domestic brand
Shelter 3035 days (les than 100 5 days 5 days Agisson
shelter)
Diesel generator 9 weeks 5 days 5 days The lead time varies
(made at home) with the batch size and
model.

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 39