• Rate analysis for Brick & Stone work

Brick Masonry –
115mm thick Masonry in sqm
230mm thick Masonry in cum
Stone Masonry –
Normal start from minimum thickness of 350mm to 900mm

12/23/2017 1
Mortar :-
Quantities for 1 cu m of Brick work Mortar requirement
= total volume of Bk. Work minus net volume of
Calculation of quantities for brick work bricks
• Take a wall of 30cm nominal thickness of = 29 – ( 0.19 x 0.09 x 0.09 x 14500 )
20m length & 5m height. = 29 – 22.315
Nominal volume = 20 x 0.3 x 5 = 30 cum = 6.685 cum.
• Normally mortar joint will be less than 1 For frog filling , for use of cut bricks, for
bonding, for uniform joints, wastages etc. 15%
cm , taking 1 cm mortar joint , the actual extra mortar may be required.
thickness of wall be 29 cm. Therefore , the volume of mortar
• Therefore actual volume = 20 x 0.29 x 5 = = 6.685 + 6.685 x 0.15
29 cum.
= 7.688 cum
Number of standards bricks of 20cm x For dry volume increase by ¼ dry volume of
10cm x 10cm x nominal size = 29 / 0.20 x mortar = 7.688 + 1.911 = 9.61 cum
0.10 x 0.10 = 14500 nos. For 30cum of brick work , dry volume of mortar
• Therefore number of bricks per cum ( =9.61 cum. Therefore for 10cum of brick work,
nominal ) = 14500 / 30 = 484 nos. dry volume of mortar = 9.61 x 10/30 = 3.2 cum
Considering 5% breakages, wastages, etc. In practice , 3.0 cum cement mortar in dry state
this may be taken 500 numbers per cum. of mortar are taken for 10cum brickwork. As an
approximate 30% dry mortar may be taken.
12/23/2017 2
Quantities for 1 cu m of Brick work
• Method of calculation of quantities for Notes:
brick work 1. Number of Bricks = 500
• Volume of dry mortar = 30% of 2. Volume of one bag of cement =
volume of brick work 0.035 mᵌ
• Hence , if Y mᵌ of Brick Work in cement 3. In half brick masonry (115 mm
Mortar 1:4 – thick ), from surface area
• Volume of mortar required = 0.30 x Y consideration , 1sq m of area
• Volume of cement = 1 / (1+4) x 0.30 Y contains about 50 bricks.
• Sand = 4 / (1+4) x 0.30 Y

12/23/2017 3
Quantities for 1 cu m of Brick work
• Method of calculation of quantities for Notes:
Concrete mix Rates for calculating unit rates of brick
• Hence , if 1 mᵌ of wet mortar is to be work.
produced in proportion 1:4 – Brick – 7/- per brick
• Volume of dry concrete = 0.30 x 1 Cement - 400/- per bag
• Volume of cement Sand - 4000/- per cu m
= 1 / (1+4) x 0.30 x 1
Labour charges - 5357 /- per cum
= 0.3 cu m
= 0.3 / .035
= 1.71 =͂ 2 bags
• Sand = 4 / (1+4) x 0.30 x 1
= 0.24 cu m

12/23/2017 4
Description Quantity / No. Rate Per Amount

Materials
Bricks 500.00 nos. Rs .0007.00 cum Rs. 3500.00
Sand 0.240 cum Rs. 4000.00 cum Rs. 960.00
Cement 2.00 bags Rs. 0400.00 Per bag Rs. 800.00
1.Material cost Rs. 5260.00
Labour
Labour for placing concrete including 1 cum Rs. 5357.00 cum Rs. 5357.00
scafoling, curing etc.

2.Labour Cost Rs. 5357.00


Adding 1 & 2 Rs. 10617.00
Rs. 10600.00
10% contractors profit Rs. 1060.00
1.5% water & electric consumption charges Rs. 159.00
Rate for 1 cum Rs. 11819.00
Say Rs. 11820.00
Rate for 10 cum of brick work Rs. 1,18,200.00

12/23/2017 5
• Assignment 1 :

1. Work out the rate of 230mm th Brick work in super structure with IS
brick with 1:6 cement sand mortar for 10cum.
2. Work out the rate of 115mm th Brick work in super structure with IS
brick with 1:4 cement sand mortar for 10 sqm.
3. Work out the rate of 115mm th Brick work in super structure with IS
brick with 1:6 cement sand mortar for 10 sqm.

12/23/2017 6
Quantities for 1 cu m of Stone work
Calculation of quantities for stone work
• Rubble required for the masonry work will be about 25% more than the quantity
of said masonry work ; i.e. for 1 cum masonry work , rubble required will be 1.25
cum .
• For 1 cum of masonry work , mortar required will be 0.30 cum.

12/23/2017 7
Quantities for 1 cu m of Stone work
• Method of calculation of quantities for Notes:
brick work 1. Quantity of Rubble = 1.25 cum
• Volume of dry mortar = 30% of 2. Volume of one bag of cement =
volume of stone work 0.035 mᵌ
• Hence , if Y mᵌ of Stone Work in
cement Mortar 1:4 –
• Volume of mortar required = 0.30 x Y
• Volume of cement = 1 / (1+4) x 0.30 Y
• Sand = 4 / (1+4) x 0.30 Y

12/23/2017 8
Quantities for 1 cu m of Stone work
• Method of calculation of quantities for Notes:
Concrete mix Rates for calculating unit rates of stone
• Hence , if 1 mᵌ of wet mortar is to be work.
produced in proportion 1:4 – Stone – 1.25 cum
• Volume of dry concrete = 0.30 x 1 Cement - 400/- per bag
• Volume of cement Sand - 4000/- per cu m
= 1 / (1+4) x 0.30 x 1
Labour charges - 3012 /- per cum
= 0.3 cu m
= 0.3 / .035
= 1.71 =͂ 2 bags
• Sand = 4 / (1+4) x 0.30 x 1
= 0.24 cu m

12/23/2017 9
Description Quantity / No. Rate Per Amount

Materials
Stones 1.250 cum Rs .1020.00 cum Rs. 1275.00
Sand 0.240 cum Rs. 4000.00 cum Rs. 960.00
Cement 2.00 bags Rs. 0400.00 Per bag Rs. 800.00
1.Material cost Rs. 3035.00
Labour
Labour for placing concrete including 1 cum Rs. 3012.00 cum Rs. 3012.00
scafoling, curing etc.

2.Labour Cost Rs. 3012.00


Adding 1 & 2 Rs. 6047.00
Rs. 6050.00
10% contractors profit Rs. 605.00
1.5% water & electric consumption charges Rs. 090.75
Rate for 1 cum Rs. 6745.75
Say Rs. 6800.00
Rate for 10 cum of stone work Rs. 68,000.00

12/23/2017 10
• Assignment 2 :

1. Work out the rate for Random Rubble stone masonry with 1:6 mortar
in foundation for 10cum.
2. Work out the rate for Coursed Rubble stone masonry with 1:3 mortar
in superstructure for 10cum.
3. Work out the rate for Ashlar masonry with 1:3 mortar in
superstructure for 10cum.

12/23/2017 11