PETROVIETNAM TECHNICAL SERVICES CORPORATION

PTSC MECHANICAL & CONSTRUCTION


LIVING QUARTER & HELIDECK
AGENDA
NO ACTIVITIES TIME
1 LQ Introduction 5’

2 LQ STRUCTURE 15’

3 LQ SITE MOVING, JACKING, SKIDDING 10’

4 LQ Architecture installation 10’

5 LQ Piping installation 15’

6 LQ HVAC installation 10’

7 LQ E&I installation 10’

8 Pre-com 15’

9 Corrugated wall connection issue 5’

10 Q&A 5’
SAO CPP LQ INTRODUCTION

Total weight: 1175MT consist of:


Structure: 660 MT
Architecture: 194 MT
Piping: 54MT
HVAC: 96MT
E&I: 144MT
Safety: 14 MT
Location: Located on CPP at:
Above Mezzanine Deck (+)29.500.
From row 7 to row 8.
Capacity of 80 POB.
LQ to be a fabrication package under
PTSC fabrication scope.
KEY MILESTONE

LQ First cutting
Start piping Start Architecture Start Testing/Pre-
Start Structural LQ Habitation.
fabrication. fabrication. com/Com.
fabrication.

02-Jul-2018 16-Nov-2018 27-Dec-2018 11-Jul-2019 25-Feb-2020

18-Jul-2018 16-Nov-2018 26-Jan-2018 02-Oct-2019

Start Start E&I Start HVAC Jacking


Blasting/painting. fabrication. fabrication. Operation.
LQ STRUCTURE

NO Content TIME
1 LQ Main Structure Components 5’

2 LQ Overall Structure Fabrication sequence 5’

3 LQ Detailed Fabrication Sequence 15


LQ Main Structure Components

HELI-DECK

HELI-DECK Support

LQ DECK 4

LQ DECK 3

LQ DECK 2

Corrugated Walls

Main and mini-Columns

LQ DECK 1
LQ Overall Structure Fabrication sequence

Install Other structure.


31-May-19
Install Heli-Deck
Install Heli-Deck support Frame
23-Mar-19
Install Deck 4 onto Deck 3
Install Columns and walls onto Deck 3
30-Jan-19
Install Deck 3 onto Deck 2
Integration Schedule
Install Columns and Walls onto Deck 2
04-Dec-18
Lift LQ Deck 2 onto Deck 1 04-Dec-18
Install Deck 2 onto Deck 1 Lift LQ Deck 3 onto Deck 2 30-Jan-19
Install columns and wall onto Deck 1 Lift LQ Deck 4 onto Deck 3 23-Mar-19
13-Oct-18 Lift Support Helideck 09-Apr-19
FAB DECK 1 at final position
Lift Helideck 31-May-19
LQ Detailed Fabrication Sequence Stage 1:
Fabrication PGs, beams, Nodes,…
Fabrication Main supports on
Activities Start Finish ROS
foundation, temporary supports
Yard upgrade (Reuse Available
existing foundation) foundation
Fab/Layout Temporary
Support for Assembly
Decks 15-Jun-18 01-Aug-18 Available

Stage 2:
Layout Main supports on foundation
and support on the ground
Leveling all supports

Stage 3
LQ Detailed Fabrication Sequence Stage 3:
Activities Start Finish ROS
Layout and assembly Deck 1 at final
Position.
Fab Mating Support
Install Mounting support for
(LQ and CPP) 02-Jul-18 02-Jul-18 20-Jun-18
Equipment, wall.
Fab Nodes of Deck 02-Jul-18 04-Aug-18 20-Jun-18 Install starter for support system.
Fabricate PG for LQ 02-Jul-18 30-Aug-18 20-Jun-18 Install piping support where is
Cut & Prepare Primary posible.
Beam of Deck 02-Jul-18 25-Jul-18 20-Jun-18 Install landing of staircase/walkway

Cut & Prepare stiffener 10-Aug-18 21-Aug-18 29-Jul-18


Cut & Prep Secondary
Beam 02-Aug-18 18-Aug-18 21-Jul-18
Install Stiffs 19-Sep-18 02-Oct-18 02-Sep-18
Fabrication of Piping
Support 16-Nov-18 08-Jan-19 12-Oct-18 Stage 4:
Install Piping Spool and Layout and assembly Deck 2, 3, 4
Valves 11-Jan-19 08-Mar-19 15-Mar-19
on the Site.
Fab E&I supports 16-Nov-18 25-Jan-19 12-Oct-18 Install Piping supports on Deck
2,3,4
Fab HVAC Support 11-Jan-19 06-Mar-19 12-Oct-18
Install Starter Brackets for E&I,
Fab Furniture/Cabinate
Support 27-Dec-18 26-Jan-19 15-Dec-18
HVAC, Architecture Support.
Install Install Deck Penetration.
Furniture/Cabinet Install insulation pin below decks.
Support 03-Jan-19 02-Feb-19 22-Dec-18 Install mounting support for
equipment.
Install landing of staircase/walkway Stage 5
LQ Detailed Fabrication Sequence Stage 5:
Layout and assembly HeliDeck.
Activities Start Finish ROS Install Drain gutter
Cut & Prepare and Roll Install safety Net support Frame
Crimped Wall Plating Install E&I, Piping supports
for Level 1 11-Sep-18 01-Nov-18 01-Sep-18
Cut & Prepare Primary
Beam of Heli Deck 21-Nov-18 13-Dec-18 09-Nov-18
Fab Nodes of Helideck 21-Nov-18 19-Dec-18 09-Nov-18
Cut & Prep Secondary
Beams of Helideck 30-Nov-18 22-Dec-18 18-Nov-18
Cut & Prepare Stiffener
of Helideck 24-Dec-18 31-Dec-18 12-Dec-18
Cut & Prep Deck Plate
of Helideck 24-Dec-18 16-Jan-19 12-Dec-18
Fab Safety Net Panel 08-Jan-19 05-Mar-19 27-Dec-18
Fabricate Tertiary Steel Stage 6:
(handrail, Ladder. Steel walls fabrication,…
Walkways....) 14-Jan-19 16-Mar-19 02-Jan-19 Install insulation pins.
Fab Safety Net Support Apply shop primer before installing to the
Framing 25-Jan-19 11-Mar-19 13-Jan-19 Deck.
HELIDECK
Fabrication 21-Nov-18 30-May-19
Piping for HELIDECK 22-Feb-19 08-May-19
E&I for HELIDECK 22-Feb-19 15-May-19 Stage 7

Steel wall
LQ Detailed Fabrication Sequence Stage 7:
Install columns and walls above deck 1.
Activities Start Finish ROS Continue install mounting support for
equipment.
Cut & Prep Main
Columns of level 1 18-Aug-18 08-Sep-18 06-Aug-18
Fab Furniture/Cabinate
Support 27-Dec-18 26-Jan-19 15-Dec-18
Fabrication of Piping
Support for Level 2 24-Nov-18 16-Jan-19
Install Piping suppport
for Level 2 20-Dec-18 15-Feb-19
Fab Piping Spools for
Level 2 12-Dec-18 02-Feb-19
Install Piping Spool and
Valves for Level 2 19-Jan-19 16-Mar-19
Install E&I supports for
Level 2 20-Dec-18 05-Mar-19
Install HVAC Support Stage 8:
for Level 2 26-Feb-19 01-Apr-19 Trim columns, mini-columns, wall panel to equal height
Fab Furniture / Cabinet Adding temporary supports to assist the fit – up
Support 09-Jan-19 23-Mar-19 activities.
Install Furniture / Two Crawl crane to be used to minimize the
Cabinet Support 29-Jan-19 12-Apr-19 displacement during lifting deck.
Spreader bar to be consider base on the lifting
Lift & Weld Deck 2
calculation.
onto Deck 1 04-Dec-18 17-Dec-18
Build 02 scaffolding stairs for access to LQ.
Lifting deck 2 onto deck 1.

Stage 9
LQ Detailed Fabrication Sequence
Stage 9:
Activities Start Finish ROS Release hot work under deck 2 for final
Install Main Columns painting.
of Level 2 18-Dec-18 28-Dec-18 Install HVAC, E&I, Architecture under Dec 2
Install Crimped Walls Install staircase at Deck 1
at Level 2 29-Dec-18 25-Feb-19
Install Braces for Level
2 29-Dec-18 16-Jan-19
Install E&I supports for
Level 2 20-Dec-18 05-Mar-19
Install E&I Equipment 05-Mar-19 08-Apr-19 18-Apr-19
Install E&I Cable
Tray/Ladder 15-Mar-19 25-Jun-19 07-Mar-19
E&I Cable Pulling 26-Apr-19 10-Aug-19 15-Apr-19
Termination/ Stage 10:
Continuity Check E&I Install Columns and walls above deck 2
cables 10-May-19 29-Aug-19 15-Mar-19
Continue install mounting support for
Equipment.
Install Wet unit/some equipment or put on the
deck 2 at a secured location.

Stage 11
LQ Detailed Fabrication Sequence Stage 11:
Trim columns, mini-columns, wall panel to
Activities Start Finish ROS equal height
Lift & Weld Deck 3 Adding temporary supports to assist the fit –
onto Deck 2 30-Jan-19 16-Feb-19 up activities.
Fabrication of Piping
Two Crawl crane to be used to minimize the
Support for Level 3 29-Dec-18 25-Feb-19
Install Piping suppport displacement during lifting deck.
for Level 3 18-Feb-19 10-Apr-19 Spreader bar to be consider base on the
Fab Piping Spool for lifting calculation.
Level3 23-Feb-19 17-Apr-19 Lifting Deck 3 onto Deck 2.
Install Piping Spool and
Valves for Level 3 06-Apr-19 31-May-19
Install E&I Supports for
Level 3 18-Feb-19 29-Apr-19
Install HVAC Support
for Level 3 21-Mar-19 27-Mar-19
Fab Furniture/Cabinate
Support 25-Mar-19 05-Jun-19
Stage 12:
Install
Furniture/Cabinet Release hot work under deck 3 for final
Support 05-Apr-19 17-Jun-19 painting.
Install HVAC, E&I, Architecture under
Dec 3
Install staircase at Deck 2

Stage 13
LQ Detailed Fabrication Sequence Stage 13:
Install Columns and walls above deck 3
Activities Start Finish ROS Continue install mounting support for
Install Main Columns Equipment.
of Level 3 18-Feb-19 28-Feb-19 Install Wet unit/some eqipment or put on the
Install Crimped Wall deck 3 at a secured location
Plates of Level 3 21-Feb-19 13-Apr-19 Install Dump waiter on set from the top of deck
Fabrication of Piping
3.
Support for Level 4 29-Dec-18 25-Feb-19
Install Piping suppport
for Level 4 06-Apr-19 31-May-19
Install E&I Supports for
Level 4 06-Apr-19 18-Jun-19
Install HVAC Support
for Level 4 12-Apr-19 19-Apr-19
Stage 14:
Trim columns, mini-columns, wall panel to equal
height
Adding temporary supports to assist the fit – up
activities.
Two Crawl crane to be used to minimize the
displacement during lifting deck.
Spreader bar to be consider base on the lifting
calculation.
Lifting Deck 4 onto Deck 3.

Stage 15
LQ Detailed Fabrication Sequence Stage 15:
Release hot work under deck 4 for final
Activities Start Finish ROS
painting.
Lift Support Helideck 09-Apr-19 20-Apr-19 Install HVAC, E&I, Architecture under Dec 4
Install Braces above Install staircase at Deck 3
Deck 4 16-Apr-19 04-May-19
Lift Helideck & Weld 31-May-19 17-Jun-19

Stage 16:
Installing Heli-Deck Support frame and
support truss.
Install HVAC rack above Deck 4.

Stage 17
LQ Detailed Fabrication Sequence Stage 17:
Lifting Heli-Deck with the maximum
Activities Start Finish ROS attachment/scaffolding.
Lift Helideck & Weld 31-May-19 17-Jun-19
Install Staircase for LQ 18-Jun-19 26-Aug-19
Install Teritiary Steel
(handrail, ladder,
walkway...) for LQ 18-Jun-19 26-Aug-19
Helideck Friction
Testing 20-Sep-19 01-Oct-19

Stage 18:
Install access platform, staircases.
Installing equipment above Deck 4 and
Heli-Deck.
Install Helideck lighting

Stage 19
LQ Detailed Fabrication Sequence

Stage 20:
Stage 19:
Remove temporary supports, Keep the main supports
Testing, Pre-Com,….
LQ ready for Site moving, Jacking, skidding to CPP.
LQ SITE MOVING, JACKING, SKIDDING

NO Content TIME
1 LQ Site Moving Operation 5’

2 LQ Jacking Operation 5’

3 LQ Skidding Operation 5’
LQ Site Moving Operation
LQ Site Moving Operation
• The Structure was arranged on temporary
supports height 1800mm.
• To make the trailer suitable to the height.
• Bottom of the Structure will be marked for
correct trailer arrangement underneath. In
addition, maneuvering path is identified by
marking lines alongside the lengthwise of the
Structure on the ground, the trailer wheels to be
driven in between these lines.
• All obstructions which interfere the trailer’s
moving path will be removed.
• After finishing all the preparation, the test lift for
Structure will performed. Before performing the
trial lift. A notice will be informed to involved
Parties prior to lifting test.
• Using rubbers at top of the platform trailer to
increase friction between the Structure and
trailers. Jacking-up the trailer platforms till top
of platform trailers touching the bottom of
Structure.
• Lashing Structure to trailers by chain ropes.
• Checking all pressure of trailers to control the
load condition before moving.

Solutions for the Oil & Gas Industry


LQ Jacking Operation
• Transportation of equipment to site.
• Clearing working area during the whole work
execution, setup of exclusion zone for non-
authorized people.
• Inspection of Foundation conditions (e.g.
levelness/overall conditions, etc.) at jacking
locations & forklift positions for assembly of
equipment prior to any activities.
• Inspection of foundation, prepared by Contractor.
• Dimension control dept. to mark-up positions of
where to place/position jacking towers. install
jacking towers at given positions/locations. To be
verified by Contractor.
• The power pack and the readout displays need
electric power to function. An ordinary two phase
connection will be sufficient for one power-pack,
32 Amps, 230 V.
• The control station shall be protected from adverse
weather conditions during the operation. Weather
protection such as weather tent or similar. See
control station on jacking drawings in appendix C.
• The load cells shall be positioned as per the
approved Engineering manual and load cells
arrangement.

Solutions for the Oil & Gas Industry


• Installation of Jacking towers (x4)
• Measuring of jacking towers. 4 jacking towers
• Check results from measurements
• Offset shimplates on top of jacking towers. 4
jacking towers.
• Measuring of jacking nodes for LQ module &
jack. towers final pos.
• Measuring of jacking towers and jacking nodes
• Check results from measurements
• Verification of module placement on top of
jacking towers, 4 jacking towers.
• Verification of shimpack on top of top jacking
element.
• Jacking LQ Module up one element and place
module on steel/jacking element (jack retracted)
• Measuring of jacking towers. 4 jacking towers
• Check results from measurements
• Tighten bolts to shim-pack
• Jacking LQ Module up one element and place
module on steel/jacking element (jack retracted)
• Jack LQ module up 5 more elements
• Verification of module height under module.
Max. height under module at mechanical safe
pos. 13000 mm.
• Installation of supports

Solutions for the Oil & Gas Industry


• Verify that grillage supports is in position and
jacking operation to be continued
• Jacking LQ Module up and remove one
element, place LQ module down on supports
• Verify that LQ module is in correct position
• End of Jacking operation for LQ Module
• Install feeding table extensions. (x6)
• Jacking down elem. And removal of equipment

Solutions for the Oil & Gas Industry


Solutions for the Oil & Gas Industry
LQ Skidding Operation
• Locking gripper unit: The hydraulic cylinders
controlling the claws are extended so that these are
locked onto the flange of the skid beams.
• Break out/start of skidding: The two primary
pushing cylinders connecting the rear skidshoes
to the gripper unit are pressurised (4x 100 Tonne)
until the skidshoes (and thus module) starts moving.
• Extending primary cylinders And thus skidding the
module forward. The cylinders have a maximum
stroke of 1050mm and are synchronically extended at
both skidshoes. When the end of stroke is reached the
cylinders are de-pressurised.
• Unlocking Gripper unit and retracting cylinder The
claws of the gripper unit are unlocked and the
primary pushing cylinders are hydraulically retracted.
These steps will be repeated until module reaches the
end position of module.

Solutions for the Oil & Gas Industry


Removal of skidshoe Operation
• Removing of bolt connection between module &
intermediate piece: The bolt connections between the
bottom of module steel members and intermediate
pieces are removed. Shim plates are removed and
skidshoes are lowered to lowest height.
• Removal skidshoe guides: The skidshoe guides
located at the side will be removed and all
hydraulic connections are disconnected.
• Positioning of Teflon pads: Where required Teflon pads
will be positioned on the skid tracks to decrease friction
& protect the stainless steel of the skidshoes.
• Positioning skidshoes on skid track: Chain hoists are
positioned to secure skidshoe and to drag the skidshoe
in a sideway direction onto the preinstalled skid
tracks. After positioning of the skidshoes onto the
skid tracks the skidshoe guides are reinstalled to
secure the skidshoes.
• Skidding out skidshoes: Trough an external pulling
force (tire fort or similar equipment) the skidshoes are
skidded out. During this operation Teflon pads will
continuously be positioned from back of skidshoes to
front.
• Removal by crane At the outside the skidshoes will be
removed by crane.

Solutions for the Oil & Gas Industry


Corrugated wall connection issue
Typical Guide plate
Concern: Currently the corrugated wall for shape for Columns
LQ is connected directly to Top and Bottom joining during lifting
deck beams, during lifting the deck, it can operation.
cause clashing between Wall and Deck.
Construction will conduct some method as
below:
• Using 02 Crawl cranes for lifting LQ
Decks to minimize displacement of
elements during lifting.
• Adding some supports at the middle of
the Deck to ensure the deck will touch
to support before touching to the
columns.
• The location of the additional supports
to be considered base of the
displacement and the actual dimension
of the Decks.
• Proposed with DE to move small
columns to Grid line.

Solutions for the Oil & Gas Industry


LQ ARCHITECTURE

NO Content TIME
1 LQ Architecture Arrangement 5’

2 LQ Architecture installation Over view 5’

3 LQ Main installation Sequence 10


LQ Architecture Arrangement: First Floor

Room arrangement at level 1:


• Freezer room. • Male lockers room • Recreation room
• Chiller room. • Galley Room. • Infirmary
• Laundry Room. • Dining Hall • Smoking room
• Camp boss Room. • Dry store. • Dump waiter
LQ Architecture Arrangement: Second Floor

Room arrangement at level 2:


• 4 Men room: 8 rooms
• 2 Men room: 14 rooms
• Dump waiter
LQ Architecture Arrangement: Third Floor

Room arrangement at level 2:


• 1 Man VIP room • Gymnagium room
• 2 Men room: 6 rooms • Helicopter lounge
• 1 Man room: 7 rooms • Library
• TB Room • HLO & Amin office
Overall Architecture installation
sequence

Doors and Windows


Furniture
Ceiling with Unistrut support system
Partition wall
Flooring
LQ Structure Frame with insulation
Overall Architecture installation
Install all steel supports
sequence for a typical room
Activities Start Finish ROS
Fab Furniture / Cabinet
Support 09-Jan-19 23-Mar-19 13-Mar-19 Apply underlayment
Install Furniture /
Cabinet Support 29-Jan-19 12-Apr-19 02-Apr-19
Insulation 21-Mar-19 25-Jun-19 15-Jun-19 Install Wet unit
Install Wet Unit 02-Apr-19 13-Jun-19 03-Jun-19
Install Wall Panel 26-Apr-19 10-Aug-19 31-Jul-19
Install wall with opening for
Install Ceiling Panel 16-May-19 24-Jul-19 14-Jul-19
Install Window and
related item (Lighting, HVAC)
Door (outside) 16-May-19 28-Aug-19 18-Aug-19
Install Floor Screeded 16-May-19 28-Aug-19 18-Aug-19 Install ceiling with opening for
Install Cabinet & related item (Lighting, HVAC)
Funiture 22-May-19 04-Sep-19 25-Aug-19
Fab & Install Others 03-Jun-19 28-Aug-19 18-Aug-19
Apply Floor decoration
Install Doors 20-Jun-19 05-Aug-19 26-Jul-19
(such as vinyl sheet)

Install Furniture items/related


items from E&I, HVAC.

Install Door/window
Wall insulation sequence Surface preparation
Welding pins to Wall by Stub welding
process in workshop. Install Pin
Ballasting/painting in workshop.
Install onto the deck. Touch up painting
Release all related hot works at near
and far side.
Before install the Rock wool, the actual Install rock wool
dimension to be measured carefully.
The rock wool to be cut to suitable size Seal by aluminum foil
and install to the steel structure.
Install washers to secure the rock wall Install washers
to the wall.
Install the finishing end to decorate.
Final inspection base on the ITP for Cut out exceed length of pin
Architecture.
Install finishing end

Final inspection
Wall panel Fab and installation
Surface preparation
sequence
Bottom profile: The installation starts Install support, top and bottom profile to
by placing the bottom profile correctly structure
on the deck according to dimensions of
cabins, corridors etc. and in relation to Touch up painting
steel bulkhead and pipes etc.
Top Profile: are placed vertically above Panels pre-fabrication (marking, cut holes,
the bottom profiles at a distance of cut exceed length…)
allowing correct ceiling height.
Wall panel: to be pre-fabricated at Install Wall Panel
workshop such as marking and cutting
for Holes of penetration, exceed
Seal the panel connection base on
length,.. the type of connection.
• Do not remove the protection film
layer before the outfitting finished.
Cleaning

Final inspection
Flooring application sequence Surface preparation
Steel Floor surface: Free from contamination,
Applied Zinc silicate shop primer. Plug holes Apply primer coat
and gaps.
Primer coat: Mixing by power tool with
correct mixing rate in 10 to 20 minutes. Apply base coat
Coating by roller/brush.
Base Coat: Mixing by power tool with correct
Apply top coat
mixing rate in 20 to 30 minutes. Pour the
mixed composition to deck and spread by
steel board. Making inclining surface where Grinding to smooth surface
required. Don’t remix material. Avoid any
load to floor at least 24hrs.
1 Top coat: Mixing by power tool with correct Apply Glue layer
mixing rate. Coating by roller/brush. Sanding
by sand paper.
Apply Vinyl sheet
2 Top coat: for a good surface.
Apply vinyl with glue: the surface to be
protect by cover. Seal the seam by heating vinyl
rod
Apply for: Corridor, Dinning hall, Rec.Lounge,
infirmary, Bed room, TV room, Gymnasium,
Library, Helicopter lounge, HLO & Admin Final inspection
office.
Tile floor application sequence Apply underlayment
Underlayment: Same as Vinyl floor.
Primer coat: Mixing by power tool with
correct mixing rate in 10 to 20 minutes. Grinding to smooth surface
Coating by roller/brush.
Base Coat: Mixing by power tool with correct
mixing rate in 20 to 30 minutes. Pour the Apply Glue layer
mixed composition to deck and spread by
steel board. Making inclining surface where
required. Don’t remix material. Avoid any Laying the Tiles
load to floor at least 24hrs.
1 Top coat: Mixing by power tool with correct Marking an cut to lay the rest
mixing rate. Coating by roller/brush. Sanding tiles.
by sand paper.
2 Top coat: for a good surface.
Apply vinyl with glue: the surface to be Apply Grout
protect by cover.
Apply for: Galley, Air Lock, Laundry, Dish/pot
wash, Male locker, wet unit, Galley toilet, Cleaning
toilet and long bath area in infirmary room,
Dry store room.
Some room for VIP apply carpet. Final inspection
Ceiling installation sequence Install support for frame
Starter Brackets: To be clean surface
and install starter brackets during the
Deck is fabricating on the ground. Install support frame
Final painting: after release all
related hot work.
Install Ceiling support frame: Install ceiling frame
with hanger.
currently considering to use Unistrut
frame for supporting ceiling.
Ceiling Frame: to be attached to Pre-fabricate ceiling
panels
Unistrut frame by hangers.
Ceiling panels: to be pre-fabricated
in workshop followed the dimension, Install ceiling panels
vendor instruction manual.

Cleaning

Final inspection
Architecture equipment installation Install mounting
support, leveling support
Mounting support: to be install on the
Deck during fabrication on the ground.
Lifting equipment: Any equipment Lifting to the floor
with exceed size of the main door
opening to be place on the deck Connect bolt to
before above deck coming. The other mounting plinth and
equipment to be lifted to the leveling
landing/walkway then transport to the
right place by handling carefully. Chiller/Freezer
Welding to fix the
The equipment will be secured and connection
Dump waiter
maintained after installing until final
release to Client. Connecting
accessories

Cleaning/securing

Final testing/inspection

Bunk bed Wet unit


PIPING SYSTEM IN LQ

Content

Overview piping system in LQ


Sequence fabrication and erection
ROS and schedule start work
PIPING SYSTEM IN LQ
Overview piping systems in LQ

Utility system:
- Fresh water
- Sewage treatment
- Open drain

Safety system
- Fire water
PIPING SYSTEM IN LQ
Overview piping system in LQ
Utility system:
- Fresh water: supply hot
& cold water to LQ

 Cold water
 Hot water
PIPING SYSTEM IN LQ
Overview piping system in LQ

Utility system:
- Sewage treatment:
black & grey water

 Black water
 Grey water
PIPING SYSTEM IN LQ
Overview piping system in LQ

Safety system
- Fire water
 Fire water
PIPING SYSTEM IN LQ
Spool fabricated flow chart
Sequence fabrication and erection Pipe marking
Painting

REJ
(Spool)

REJ
QC
Sequence fabrication QC

and erection pipe spool Cutting


Erection
(Spool)
Fittup

REJ
QC

Welding

REJ
REJ
QC

NDT
PIPING SYSTEM IN LQ
Sequence fabrication and erection
 Fabrication and erection in
order from deck 1 to deck 4

 Classify to :
- Priority 01 support
- Priority 02 main line – header
- Priority 03 brand line go to rooms

 Piping work carry out after the structure


deck completed and before installation
ceiling and wall panel wherever running
pipe line. Truly coordinate the other
discipline avoid clashing and consider
installation partial support and pipe spool
in advance lift up deck
PIPING SYSTEM IN LQ
Sequence fabrication and erection
 Fabrication and erection in
order from deck 1 to deck 4

 Classify to :
- Priority 01 support
- Priority 02 main line – header
- Priority 03 brand line go to rooms

 Piping work carry out after the structure


deck completed and before installation
ceiling and wall panel wherever running
pipe line. Truly coordinate the other
discipline avoid clashing and consider
installation partial support and pipe spool
in advance lift up deck
PIPING SYSTEM IN LQ
ROS and schedule start work
ROS Fabrication Installation Fabrication Installation Fabrication Installation Fabrication Installation
Piping Ppackage Using for
Forecast D1 D1 D2 D2 D3 D3 D4 D4
Piping and E&I
18-Dec-18
1 Support Support 30-Sep-18 16-Nov-18 24-Nov-18 20-Dec-18 29-Dec-18 18-Feb-19 29-Dec-18 6-Apr-19
(Included LQ)
Utility
Piping Bulk Items-1 system: 20-Nov-18
2 10-Nov-18 11-Jan-19 12-Dec-18 19-Jan-19 17-Jan-19 6-Apr-19 17-Jan-19 22-Apr-19
(Included LQ) Fresh water
Open drain
Utility
CPVC Piping system:
3 10-Nov-19 20-Nov-18 11-Jan-19 12-Dec-18 19-Jan-19 17-Jan-19 6-Apr-19 17-Jan-19 22-Apr-19
(Included LQ) Sewage
treatment
Safety
CuNi Pipe & Fitting 20-Nov-18
4 system: 30-Dec-18 11-Jan-19 12-Dec-18 19-Jan-19 17-Jan-19 6-Apr-19 17-Jan-19 22-Apr-19
(Included LQ)
- Fire water
Manual Valves
5 all 15-Feb-19 22-Feb-19 26-Feb-19 6-Apr-19 22-Apr-19
(Included LQ)

Piping Gaskets &


6 Insulation Kits all 12-Feb-19 22-Feb-19 26-Feb-19 6-Apr-19 22-Apr-19
(Included LQ)
Piping Bolt with
7 Components all 15-Jan-19 22-Feb-19 26-Feb-19 6-Apr-19 22-Apr-19
(Included LQ)
ELECTRIC AND INSTRUMENT SYSTEM IN LQ

Content

 Overview E&I system in LQ


 Sequence E&I fabrication and installation
 ROS and schedule start work
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Overview E&I systems in LQ

Electric system:

Fire and gas system

Telecom and PAGA system


ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Electric system:
- Power & Control
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Electric system:
- Lighting & Small power

Emergency exit light Recessed mounted fluorescent light


ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Electric system:
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Fire and gas system

Smoke, heat detector ceiling mount Smoke detector ceiling void mount
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Fire and gas system
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Telecom and PAGA system
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Fabricate E&I Supports
Sequence E&I fabrication and installation
Install E&I Supports

Install cable tray, ladder

Cable pulling

Install E&I equipment

Cables gland & terminate

Cable testing

Final inspection
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Sequence E&I fabrication and installation

18-Dec-18
Install E&I Supports

15-Mar-19
Install cable tray, ladder
26-Apr-19
Cable pulling

16-Apr-19
Install E&I equipment

15-May-19
Cables gland & terminate
ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Install E&I supports (Option 1):
Oglaend system

Install Starter Brackets

Install E&I support by Bolting


ELECTRIC AND INSTRUMENT SYSTEM IN LQ
Install E&I supports (Option 2)
Unistrut section

Install Unistrut channel

Install Steel Supports, stud bolt…


ELECTRIC AND INSTRUMENT SYSTEM IN LQ
ROS and schedule start work
Fabrication
Package ROS Remark
Plan
1 Piping and E&I Support 16-Nov-18

2 Distribution Boards 15-Apr-19


3 F&G devices 1-May-19
4 Lighting, Socket Outlet, Switch and Accessories 15-May-18
5 Helideck lighting system 15-Jun-19
6 E&I Cable 26-Apr-19
7 E&I Cable tray, Ladder and Accessories 15-Mar-19
8 E&I Cable Gland and Accessories 15-May-19
9 E&I Junction Box and Control Station 16-Apr-19
10 E&I MCT, Earthing and Miscellaneous Material 15-Jan-19
11 Telecommunication Package 25-Jun-19
12 PAGA System package 25-Apr-19
13 CCTV 15-Jun-19
PETROVIETNAM TECHNICAL SERVICES CORPORATION
PTSC MECHANICAL & CONSTRUCTION

Mechanical Completion, Pre-Commissioning


& Commissioning Sequence
LIVING QUARTER & HELIDECK
OVERVIEW

• Location: Mezzanine deck


• 4 level & Helideck
• POB: 80

PTSC M&C - Solutions for the Oil & Gas Industry


SCHEDULE

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
OVERALL
PRE-COMMISSIONING BEFORE JACKING PRE-COMMISSIONING AFTER JACKING

• Cold water, hot water: service test • Heli-fuel package: full pre-commissioning &
commissioning
• Heli-fuel package: partial pre-commissioning
• Helideck fire fighting system: full pre-
• Helideck fire fighting system: mechanical pre-
commissioning & commissioning
commissioning
• Fire & Gas system
• Galley suppression system: mechanical testing
• Telecom system
• Normal lighting & distribution board
• HVAC system
• Helideck lighting
• Pre-commissioning and commissioning Fresh water,
• Emergency lighting
Hot water, Sewage Treatment combine with package.
• Laundry, Galley, Infirmary equipment: pre-com &
PTSC M&C - Commissioning
Solutions for the Oil & Gas Industry
MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
Sub MC before Pre-Com Pre-Com after Commissioning after
Description ROS Remark
System Jacking before Jacking Jacking jacking

• Piping : Full
• Only piping : Full
LQ Cold water LQ • Mechanical: Full
service test Piping interface
53.06 Cold Water Utility • Instrument : Full N/A c/w package at CPP
(full in LQ, but partial with CPP
Plumbing
(full in LQ, but partial in in Sub System)
Sub System)
• Piping : Full
• Only piping : Full
• Mechanical: Full
LQ Hot Water service test Piping interface
53.08 • Instrument : Full N/A c/w package at CPP
Distribution (full in LQ, but partial with CPP
(full in LQ, but partial in in Sub System)
Sub System)
• Piping: Full
Non Hazardous Open Piping interface
56.02 (full in LQ, but partial in N/A N/A c/w package at CPP
Drain Header with CPP
Sub System)

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
Sub MC before Pre-Com Pre-Com after Commissioning
Description ROS Remark
System Jacking before Jacking Jacking after jacking

• Electric Cable
Interface with
• Piping: Full • Mechanical: CPP
• Mechanical: Partial
61.01 Helifuel Package 21-Apr-19 • Mechanical: Partial Partial X • 1 Helifuel
• Electrical: Partial
• Electrical: Partial • Electrical: Full storage tank
was located at
CPP

• Mechanical: Full
Helifuel Dispensing • Mechanical: Full • Electrical: Full Electric Cable
61.02 21-Apr-19 • Electrical: Partial X
Package • Electrical: Partial • Instrument: Full Interface with CPP
• Instrument: Partial
• Piping: Full
Sewage Water c/w package at Piping interface
66.03 (Full in LQ, but partial in N/A N/A
Collection CPP with CPP
Sub System)

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ

MC before Pre-Com Pre-Com after Commissioning


Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

70.07 / 08/ AFDS - LQ Level 1/ 2/ 3 c/w AFDS Panel at c/w AFDS Panel at
25-May-19 • F&G: Full (N)
09 /10 and Stairway CPP CPP

Fire zone FZ-8 LQ


70.25 / 26 Fire zone FZ-9 Roof Deck 25-May-19 • F&G: Full (N) c/w ICSS at CPP c/w ICSS at CPP
& Heli Deck
• Mechanical: Function
• Piping: Full test for deluge skid & PC & Com
71.08
Helideck Firefighting
• Mechanical: Full commissioning before • Instrument: c/w with
System Jacking ICSS at CPP Temporary
• Instrument: Partial Water
• Instrument: Partial

Firewater hydrant & hose • Piping: Full C/w Firewater


71.10 N/A N/A
reel • Mechanical: Full system

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
MC before Pre-Com Pre-Com after Commissioning
Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

• Piping: Full

72.03 Galley Suppressant System 30-Jun-19 • Mechanical: Full • Mechanical: Full • Instrument: Full N/A

• Instrument: Partial

Electrical Cable
82.22 Galley Distribution Board 20-Apr-19 • Electrical: Full • Electrical: Full (N) X interface with
CPP

Electrical Cable
82.23 Laundry Distribution Board 20-Apr-19 • Electrical: Full • Electrical: Full (N) X interface with
CPP

Electrical Cable
82.25 / 26 / Normal Lighting & Small
15-May-19 • Electrical: Full • Electrical: Full (N) X interface with
27 Power Distribution Board
CPP

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
MC before Pre-Com Pre-Com after Commissioning
Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

Electrical Cable
Helideck lighting 30-May-19 • Electrical: Full • Electrical: Full (N) X interface with
CPP

Electrical Cable
84.16 Emergency lighting LQ 12-Jul-19 • Electrical: Full • Electrical: Full (N) X interface with
CPP

c/w Package at c/w Package at


86.01/ 02 PAGA system 25-May-19 • Telecom: Partial (N)
CPP CPP

c/w Package at c/w Package at


86.03 VSAT System • Telecom: Partial (N)
CPP CPP

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
MC before Pre-Com Pre-Com after Commissioning
Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

c/w Package at c/w Package at


86.04 Inmarsat & Racon System • Telecom: Partial (N)
CPP CPP

c/w Package at c/w Package at


86.05 PABX and Telephone System • Telecom: Partial (N)
CPP CPP

c/w Package at c/w Package at


86.06 LAN System • Telecom: Partial (N)
CPP CPP

86.08 / 09 / c/w Package at c/w Package at


Radio System • Telecom: Partial (N)
10 CPP CPP

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
MC before Pre-Com Pre-Com after Commissioning
Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

86.11 NDB system • Telecom: Full • Telecom: Full (N) X Console in LQ

c/w Package at c/w Package at


86.12 Radar & AIS System • Telecom: Partial (N)
CPP CPP

c/w Package at c/w Package at


86.13 CCTV System 30-Jul-19 • Telecom: Partial (N)
CPP CPP

c/w Package at c/w Package at


86.14 Meteorological System • Telecom: Partial (N)
CPP CPP

c/w Package at c/w Package at


86.16 Entertainment System • Telecom: Partial (N)
CPP CPP

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
MC before Pre-Com Pre-Com after Commissioning
Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

HVAC System A/B for LQ:

• Ducting 01-Mar-19 • Ducting, E&I


• Piping: Full Cable
• AHU 01-Aug-19 interface
97.07 / 08 • Mechanical: Partial c/w with HCP, c/w with HCP,
• Condensing Unit 01-Aug-19 (N) SWG & MCC at SWG & MCC at with CPP
• Electrical: Partial CPP CPP • Control
• Instrument devices such 15-Mar-19
• Instrument: Partial Panel located
as transmitter, damper
at CPP.
• Electrical devices
15-Mar-19

• Mechanical: Full • Full Pre-com &


Laundry Equipment 10-Feb-19
• Electrical: Full Com

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
MC before Pre-Com Pre-Com after Commissioning
Sub System Description ROS Remark
Jacking before Jacking Jacking after jacking

Galley Equipment ( Chiller, • Mechanical: Full • Full Pre-com &


10-Feb-19
freezer …) • Electrical: Full Com

• Mechanical: Full • Full Pre-com &


Infirmary Equipment 19-Jul-19
• Electrical: Full Com

LQ Safety Equipment & Life


76.05 30-Sep-19 • Mechanical: Full N/A N/A N/A
Saving

72.09 Firefighting equipment 30-Nov-19 • Mechanical: Full N/A N/A N/A

PTSC M&C - Solutions for the Oil & Gas Industry


MECHANICAL COMPLETIPON, PRE-COMMISSIONING AND
COMMISSIONING for LQ
TEMPORARY SYSTEM FOR PRE-COMMISSIONING & COMMISSIONING

1. Temporary power for LQ Lighting & Distribution Board: 3P, 400V, estimated power 60 kW

2. Temporary power for LQ HVAC, or the other package: 3P, 400V , estimated power 400 kW

3. Temporary water for Helideck fire fighting ( approximate 8 bar pressure)

4. Temporary instrument air compressor ( approximate 5 bar pressure)

PTSC M&C - Solutions for the Oil & Gas Industry


LIST LQ HABITATION

PTSC M&C - Solutions for the Oil & Gas Industry


THANK FOR YOUR ATTENTION