RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES ELECTRICAL DISTRIBUTION SYSTEM
Battery Missing
Conduit not Entirely Installed
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES ELECTRICAL DISTRIBUTION SYSTEM
No Lighting Fixture
Change over switch not Installed inside the DG Room
on mounting Pad
Gravel to be provided
for the Local
Distribution Panels
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES
No. 17
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES
No. 18
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES
No. 19
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES
No. 20
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR DG SET
Neutral to be grounded.
2 Proper grounding for Neutral to be done. Immediate
No. 21
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR CHANGE
OVER SWITCH
No. 22
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR MAIN
DISTRIBUTION PANEL
Sr. Finding Corrective Action Target Date
No
Body Grounding to be provided. Ensure Proper Body Grounding to be done Immediate
1
for all Main Distribution panels.
Direct buried cable laying crossing the Concrete Duct-banks to be installed at the
5 road to be in the duct bank. crossing of roads for the installation of Immediate
Cables.
Insulation Resistance test with Megger to
Insulation Resistance Test to be done prior to
6 be done before laying the cable. Immediate
laying of the cables.
Load Calculation of the connected loads to Load Calculation to be provided for all the
8 Immediate
be provided. connected loads.
No. 23
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR MAIN
DISTRIBUTION PANEL
No. 24
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR POWER
(LOCAL) DISTRIBUTION PANEL
No. 25
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR POWER
(LOCAL) DISTRIBUTION PANEL
GFCI (Ground fault Circuit Interrupter) Ensure GFCI to be provided where there
10 Immediate
for Kitchen and Toilets to be provided. is an usage of water.
No. 26
RISK ASSESSMENT FINDINGS OF BCEG TEMPORARY
FACILITIES & CORRECTIVE ACTION PLAN FOR
GROUNDING SYSTEM
Sr. Finding Corrective Action Target Date
No
Bare Copper Earthing Rod 25mm Dia with
Ensure the Bare Copper Earthing Rod is
1 3m long to be provided. Immediate
used with right dimensions.
All the Portable containers to be body Ensure the Portable containers to be body
3 grounded every 5m in Length. are grounded every 5m in Length. Immediate
No. 27
Thank
You