You are on page 1of 32

BIHAR STATE ROAD DEVELOPMENT

CORPORATION LIMITED
PRESENTATION BEFORE MD ON Dated 31st May’2019

R’ Block - Digha Road (Phase-1)


`
PROGRESS REVIEW

AUTHORITY ENGINEER

EPC CONTRACTOR
1
SL No Details Page No
1 Location Map 3
2 Project Administrative Details 4
3 Project Technical Details 5-6
4 Project Milestones 7
5 Payment Milestones 8
6 Bifurcation Of Project Cost As Per Schedule-H 9
7 Project Status As Per Physical Progress 10
8 List of Manpower 11-12
9 List of Machinery 13
10 Site Status 14-19
11 Other Status of Project 20
12 Deployment Schedule 21
13 Material Stock Details 22
14 Critical Issues 23
15 Details of Safety Signboards installed at Site 24
16 Site Photographs 25-30

R-BLOCK - DIGHA 6-LANE 2


R Block to Digha Road Project
Project Start : Km 0+000
Project End : Km 6+300
Project Length : 6.30 Km

R-BLOCK - DIGHA 6-LANE 3


SL DESCRIPTION DETAILS.
No
01 Name Of Project Construction of Six/Four Lane Road from R’ Block - Digha (Phase-1)
including flyover/underpasses/ drains/ Service road etc. at Patna in
the State of Bihar Length (0.00Km to 6.300 Km) on Engineering,
Procurement & Construction (EPC) Mode.
02 Project Cost Rs 297.51 Crore (EPC).
03 Authority BIHAR STATE ROAD DEVELOPMENT CORPORATION LTD
04 EPC Contractor M/s LR-BLC-Gawar (Joint Venture).
05 Authority Engineer M/s Rodic Consultants Pvt.Ltd.in JV with SPECTRUM Techno
Consultants Pvt.Ltd.
06 EPC Agreement Date 01.03.2019
07 Appointed Date 08.03.2019

08 Financial Closure 09th Sep 2020


09 Construction Period 18 Months from Appointed Date

R-BLOCK - DIGHA 6-LANE 4


STRUCTURE/ HIGHWAY

Major Bridge : (03 Nos)


Over JLN Marg : 100m (1 x 25 + 1 x 50 + 1 x 25) : Extra Dose
Shivpuri : 40m (1 x 12 + 1 x 16 + 1 x 12) : RCC Br.
Rajiv Nagar : 40m (1 x 12 + 1 x 16 + 1 x 12) : RCC Br.

Minor Bridge :(03 Nos)


Punaichak : 16m (01 x 16)
Pani Tanki : 08m (01 x 08)
Kurji Nala 08m (01 x 08)
Serpentine Nala 08m (01 x 08)
Service Road (02 Nos)
:
2-Lane Both Sides : km 0.7 to 4.8
Single-Lane Both Sides : km 4.8 to 6.3

R-BLOCK - DIGHA 6-LANE 5


STRUCTURE/ HIGHWAY
 Entry & Exit Ramps : @ 10 Locations

 Major Intersections : @ 5 Locations

 Minor Intersections : @ 7 Locations

 RCC Culverts : @ 8 Locations + 1 converted to


Minor Bridge at Serpentine Nala

 Roadside Drainage / Sewage cum Utility Drains

 Traffic Control Devices & Road Safety Works

 Roadside Furniture; Full Width Overhead Signs, Cantilever Overhead Signs

 Rainwater Harvesting

R-BLOCK - DIGHA 6-LANE 6


0%
Date -08-Mar-2019
Appointed Date
i
15%
Date -05-Aug-2019
1st Mile Stone
(150 Days) ii
40%
Date -03-Jan-2020
2nd Mile Stone
(300 Days)
iii
70%
Date -02-June-2020
3rd Mile Stone
(450 Days)
iv
100%
Date -09-Sept-2020
Schedule
Completion
(548 Days)

R-BLOCK - DIGHA 6-LANE 7


i
15%
1ST
Mile Stone
44.63 Cr
Cuml. – 44.63 Cr ii
40%
2ndMile Stone
74.38 Cr
Cuml.– 119.00 Cr iii
70%
3rd
Mile Stone
89.25 Cr
iv
Cuml.– 208.26 Cr 100%
4th
Mile Stone
89.25 Cr
Cuml.– 297.51 Cr

R-BLOCK - DIGHA 6-LANE 8


41.74% Road works including culverts, widening
and repair of culverts`

1.42% Minor Bridge

37.19% 41.74%
Major Bridge (length> 60m) works and
19.65%
ROB/RUB/elelevated sections/Flyover
inclduing vaiducts,if any

37.19% Other Engineering works


19.65%
1.42%

9
R-BLOCK - DIGHA 6-LANE
Physical Progress

10.10%

Achieved upto date


Balance

89.900%

R-BLOCK - DIGHA 6-LANE 10


SL NO. NAME DESIGNATION REMARKS
ABHIJIT DEKA PROJECT MANAGER
AJAY KUMAR Astt. PROJECT MANAGER
1. STRUCTURE:-
A PRASHANT ANAND D.P.M STRUCTURE
B RAM KRISHNA PATHAK STRUCTURE ENGINEER
C SAROJ KUMAR STRUCTURE FORMEN
2. HIGHWAY:-
A IRFAN KHAN D.P.M HIGHWAY
B VIJAY KR PANDEY D.P.M HIGHWAY
C SANJEEV KUMAR HIGHWAY ENGINEER
3. SURVEY:-
A DHARMENDRA MISHRA SURVEY MANAGER
B DEVBRAT MISHRA SURVEYOR
C ARVIND KR MISHRA SURVEYOR
D MRITUNJAY TIWARI SURVEYOR
E CHANDAN SARKAR SURVEYOR
4. BILLING & PLANING:-
A PRAMEET KUMAR JHA PLANNING & SCHEDULING ENGINEER
B RAUSHAN KUMAR QUANTITY SURVEYOR
C KANHA PANDIT BILLING ASSISTANT

R-BLOCK - DIGHA 6-LANE 11


SL NO. NAME DESIGNATION REMARKS
5. LABORATORY:-
A SUNIL PATEL MATERIAL ENGINEER
B SHASHI BHUSHAN KUMAR Q.C.E
C RAM KUMAR Q.CE
6. PLANT & ADMIN MANAGER:-
A OM PRAKASH GADHWAL MANAGER
B SANTOSH KUMAR LIASIONAR
7.MECHANICAL:-
A RAHUL KUMAR MECHANICAL ENGINEER
8 .SAFETY:-
A ROHAN PRATAP SINGH SAFETY OFFICER
9. STORE:-
A SANJEET JHA STORE KEEPER

R-BLOCK - DIGHA 6-LANE 12


SL NO. DESCRIPTION Nos REMARKS
1 Excavator 7

2 Loader 1

3 Grader 2

4 Front End Loader 6

5 Dumper 45

6 Water Tanker 6

7 Transit Mixer 8

8 Soil Compactor 4

9 Trailer 2

10 Dozer 2
Commissioning in
11 Concrete Batching Plant 1
progress
12 Weigh Bridge 1

R-BLOCK - DIGHA 6-LANE 13


SL. No. DESCRIPTION SIDE LENGTH REMARKS
1 EXCAVATION LHS 4590
(MCW) RHS 4090
TOTAL 8680
2 EXCAVATION LHS 2160
(Service Road) RHS 1350
TOTAL 3510
3 EMBANKMENT TOP COMPLETED LHS 2660
(MCW) RHS 1930
TOTAL 4590
4 EMBANKMENT TOP COMPLETED LHS 1150
(Service Road) RHS 1870
TOTAL 2020
5 EMBANKMENT IN PROGRESS LHS 3020
(MCW) RHS 2660
TOTAL 5680
6 EMBANKMENT IN PROGRESS LHS 1260
(Service Road) RHS 1170
TOTAL 2430
7 LHS 2000
SUBGRADE TOP COMPLETED (MCW)
RHS 1870
TOTAL 3870
8 SUBGRADE TOP COMPLETED LHS 1140
(Service Road) RHS 870
TOTAL 2010
9 GSB TOP COMPLETED LHS 2000
(MCW) RHS 1570
TOTAL 3570
10 GSB TOP COMPLETED LHS 690
(Service Road) RHS 870
TOTAL 1560
11 CULVERT
0+232 BHS 1 Slab Done
3+300 RHS 1 Wall 1st Lift Done
3+900 RHS 1 PCC Done
5+200 LHS 1 Wall 2nd Lift Done
TOTAL 4
12 MINOR BRIDGE
0+990 LHS 1 PCC Done
5+000 LHS 1 Excavation is in Progress

R-BLOCK
13 - REDIGHA
PANEL CASTING 6-LANE
TOTAL 2
YARD 617 COMPLETED 14
R-BLOCK - DIGHA 6-LANE 15
SL. CHAINAGE
SIDE LENGTH REMARKS
No. FROM TO
16 DRAIN
1 0+800 0+940 LHS 140 PCC of Storm water Drain
2 0+800 0+940 LHS 140 Raft Of Storm water Drain
3 0+800 0+820 LHS 20 Wall Of Storm water Drain
4 1+030 1+130 LHS 100 PCC of Storm water Drain
5 1+030 1+130 LHS 100 Raft Of Storm water Drain
6 1+030 1+050 LHS 20 Wall Of Storm water Drain
7 4+390 4+460 LHS 70 PCC Of Utility Duct Done
8 4+650 4+920 LHS 270 PCC of Storm water Drain
TOTAL 860
1 3+000 3+180 RHS 180 PCC of Storm water Drain
2 3+000 3+080 RHS 80 Raft of Storm water Drain
3 3+000 3+040 RHS 40 Wall of Storm water Drain
4 4+350 4+920 RHS 570 PCC Of Utility Duct Done
5 4+350 4+920 RHS 570 Raft Of Utility Duct Done
6 4+350 4+530 RHS 180 Wall Of Utility Duct Done
7 4+610 4+710 RHS 100 Wall Of Utility Duct Done
8 4+750 4+920 RHS 170 PCC of Storm water Drain
9 4+750 4+800 RHS 50 Raft Of Storm water Drain
TOTAL 1940

R-BLOCK - DIGHA 6-LANE 16


MAIN CARRIAGEWAY MAIN CARRIAGEWAY
CHAINAGE CHAINAGE
SL. No. SIDE LENGTH REMARKS SL. No. SIDE LENGTH REMARKS
FROM TO FROM TO
1 0+020 0+100 LHS 80.00 Embankment Top Completed 1 0+100 0+220 LHS 120.00 Embankment in Progress
2 0+100 0+220 LHS 120.00 Embankment Top Completed 2 0+280 0+320 LHS 40.00 Embankment in Progress
3 0+240 0+680 LHS 440.00 Embankment Top Completed 3 0+580 0+680 LHS 100.00 Embankment in Progress
4 0+600 0+960 LHS 360.00 Embankment Top Completed 4 0+680 0+780 LHS 100.00 Embankment in Progress
5 1+800 1+890 LHS 90.00 5 0+780 0+900 LHS 120.00 Embankment in Progress
Embankment Top Completed
6 0+900 0+960 LHS 60.00 Embankment in Progress
6 1+910 1+980 LHS 70.00 Embankment Top Completed
7 1+350 1+890 LHS 540.00 Embankment in Progress
7 3+000 3+240 LHS 240.00 Embankment Top Completed
8 1+520 1+800 LHS 280.00 Embankment in Progress
8 3+320 3+590 LHS 270.00 Embankment Top Completed
9 2+000 2+510 LHS 510.00 Embankment in Progress
9 3+590 3+800 LHS 210.00 Embankment Top Completed
10 2+540 2+900 LHS 360.00 Embankment in Progress
10 4+830 4+950 LHS 120.00 Embankment Top Completed
11 3+590 3+900 LHS 310.00 Embankment in Progress
11 4+980 5+160 LHS 180.00 Embankment Top Completed 12 4+350 4+830 LHS 480.00 Embankment in Progress
12 5+220 5+700 LHS 480.00 Embankment Top Completed Total 3020
Total 2660
1 0+330 0+520 RHS 190.00 Embankment in Progress
1 0+020 0+100 RHS 80.00 Embankment Top Completed 2 0+680 0+800 RHS 120.00 Embankment in Progress
2 0+100 0+220 RHS 120.00 Embankment Top Completed 3 0+800 0+900 RHS 100.00 Embankment in Progress
3 0+240 0+330 RHS 90.00 Embankment Top Completed 4 0+900 0+960 RHS 60.00 Embankment in Progress
4 0+520 0+580 RHS 60.00 Embankment Top Completed 5 1+030 1+160 RHS 130.00 Embankment in Progress
5 0+900 0+960 RHS 60.00 Embankment Top Completed 6 2+140 2+500 RHS 360.00 Embankment in Progress
6 1+910 1+980 RHS 70.00 Embankment Top Completed 7 2+600 2+900 RHS 300.00 Embankment in Progress
7 3+000 3+590 RHS 590.00 Embankment Top Completed 8 3+700 3+900 RHS 200.00 Embankment in Progress
8 3+060 3+240 RHS 180.00 Embankment Top Completed 9 4+000 4+300 RHS 300.00 Embankment in Progress
9 4+960 5+160 RHS 200.00 Embankment Top Completed 10 4+350 4+950 RHS 600.00 Embankment in Progress
10 5+220 5+700 RHS 480.00 Embankment Top Completed 11 5+400 5+700 RHS 300.00 Embankment in Progress
Total 1930 Total 2660
Grand Total 4590 Grand Total 5680

R-BLOCK - DIGHA 6-LANE 17


SERVICE ROAD SERVICE ROAD

CHAINAGE SL. CHAINAGE


SL. No. SIDE LENGTH REMARKS SIDE LENGTH REMARKS
No.
FROM TO FROM TO
1 0+700 0+950 LHS 250.00 Emb Top Completed 1 0+680 0+780 LSR 100.00 Emb in Progress

2 4+680 4+800 LHS 120.00 Emb Top Completed 2 0+780 0+800 LSR 20.00 Emb in Progress

3 4+980 5+160 LHS 180.00 Emb Top Completed 3 0+940 0+960 LSR 20.00 Emb in Progress

4 4+350 4+800 LHS 450.00 Emb Top Completed 4 2+250 2+500 LSR 250.00 Emb in Progress

5 4+800 4+950 LHS 150.00 Emb Top Completed 5 2+540 2+900 LSR 360.00 Emb in Progress

Total 1150 6 4+350 4+680 LSR 330.00 Emb in Progress

1 4+350 4+950 RSR 600.00 Emb Top Completed 7 4+980 5+160 LSR 180.00 Emb in Progress

2 2+600 2+870 RSR 270.00 Emb Top Completed Total 1260

Total 870 1 2+230 2+500 RSR 270.00 Emb in Progress

Grand Total 2020 2 2+600 2+900 RSR 300.00 Emb in Progress

3 4+350 4+950 RSR 600.00

Total 1170

Grand Total 2430

R-BLOCK - DIGHA 6-LANE 18


MAIN CARRIAGEWAY MAIN CARRIAGEWAY
CHAINAGE CHAINAGE
SL. No. SIDE LENGTH REMARKS SL. No. SIDE LENGTH REMARKS
FROM TO
FROM TO
1 0+020 0+100 LHS 80.00 SG Top Completed
1 0+020 0+220 LHS 200.00 GSB Completed
2 0+100 0+220 LHS 120.00 SG Top Completed
3 0+240 0+580 LHS 340.00 2 0+240 0+580 LHS 340.00 GSB Completed
SG Top Completed
4 0+600 0+700 LHS 100.00 SG Top Completed 3 0+600 0+700 LHS 100.00 GSB Completed
5 1+910 1+980 LHS 70.00 SG Top Completed 4 1+910 1+980 LHS 70.00 GSB Completed
6 3+000 3+240 LHS 240.00 SG Top Completed 5 3+000 3+240 LHS 240.00 GSB Completed
7 3+320 3+590 LHS 270.00 SG Top Completed 6 3+320 3+590 LHS 270.00 GSB Completed
8 4+830 4+950 LHS 120.00 SG Top Completed 7 4+830 4+950 LHS 120.00 GSB Completed
9 4+980 5+160 LHS 180.00 SG Top Completed
8 4+980 5+160 LHS 180.00 GSB Completed
10 5+220 5+700 LHS 480.00 SG Top Completed
9 5+220 5+700 LHS 480.00 GSB Completed
Total 2000
1 0+020 0+100 RHS 80.00 Total 2000
SG Top Completed
2 0+100 0+220 RHS 120.00 SG Top Completed 1 0+020 0+220 RHS 200.00 GSB Completed
3 0+240 0+330 RHS 90.00 SG Top Completed 2 0+240 0+330 RHS 90.00 GSB Completed
4 0+520 0+580 RHS 60.00 SG Top Completed 3 0+520 0+580 RHS 60.00 GSB Completed
5 1+910 1+980 RHS 70.00 SG Top Completed 4 1+910 1+980 RHS 70.00 GSB Completed
6 3+000 3+590 RHS 590.00 SG Top Completed 5 3+060 3+240 RHS 180.00 GSB Completed
7 3+060 3+240 RHS 180.00 SG Top Completed
6 3+300 3+590 RHS 290.00 GSB Completed
8 4+960 5+160 RHS 200.00 SG Top Completed
7 4+960 5+160 RHS 200.00 GSB Completed
9 5+220 5+400 RHS 180.00 SG Top Completed
10 5+400 5+700 RHS 300.00 SG Top Completed 8 5+220 5+700 RHS 480.00 GSB Completed
Total 1870 Total 1570
Grand Total 3870 Grand Total 3570

R-BLOCK - DIGHA 6-LANE 19


SERVICE ROAD SERVICE ROAD

SL. CHAINAGE SL. CHAINAGE


SIDE LENGTH REMARKS SIDE LENGTH REMARKS
No. No.
FROM TO FROM TO

1 0+700 0+940 LSR 240.00 SG Top Completed 1 0+700 0+940 LSR 240.00 GSB Top Completed

2 4+680 4+800 LSR 120.00 SG Top Completed 2 4+350 4+800 LSR 450.00 GSB Top Completed

3 4+800 4+950 LSR 150.00 SG Top Completed Total 690

4 4+980 5+160 LSR 180.00 SG Top Completed 1 2+600 2+870 RSR 270.00 GSB Top Completed

5 4+350 4+800 LSR 450.00 SG Top Completed 2 4+350 4+950 RSR 600.00 GSB Top Completed

Total 1140 Total 870

1 4+350 4+950 RSR 600.00 Grand Total 1560


SG Top Completed

2 2+600 2+870 RSR 270.00


SG Top Completed

Total 870

Grand Total 2010

20
R-BLOCK - DIGHA 6-LANE
 Tree Cutting : 360 Nos. out of 585 Nos.

 Encroachment Removal
 From R-Block to Shivpuri (km 0 to 2.5, In Progress)
 From Digha towards Rajiv Nagar (km 6.3 to 5.5 In Progress)
 3 nos of temples to be removed.

 Electrical Utility Shifting


 Estimate from Vikash Bhawan to A.N College: Supervision Charge Deposited,
Work Order received.

 Utility Shifting from Vikash Bhawan to AN College has started.

 Estimate for Rest Portion prepared by EEE, Supervision charges deposited,


Work Order is yet to be received.

21
R-BLOCK - DIGHA 6-LANE
 Day Schedule
 04 No Excavator at site
 02 No Excavator at Ghat for uplifting of sand.
 01 No Excavator at Dumping Yard .
 01 No Dozer at site for grading of Sand.
 01 No Dozer at Dumping Yard
 04 No JCB at site.
 02 No JCB at Dumping Yard.
 02 No Grader at site for grading.
 02 No Soil Compactor for compaction of Bed.
 03 No Water Tanker for watering of Bed.
 35 No Tipper for loading and unloading of Debris and Sand.

 Night Schedule
 04 No Excavator at site
 02 No Excavator at Ghat for uplifting of sand.
 01 No Excavator at Dumping Yard .
 01 No Dozer at Dumping Yard
 01 No JCB at Site.
 02 No JCB at Dumping Yard.
 01 No Grader at site for grading of Bed.
 02 No Soil Compactor at site for compaction of Bed.

22
R-BLOCK - DIGHA 6-LANE
MATERIALS STOCK DETAILS
SL NO ITEMS UNIT QUANTITY IN STOCK REMARKS

1 AGGREGATE 10MM MT 2522.774

2 AGGREGATE 20MM MT 5163.99

3 AGGREGATE 40MM MT Nill

4 GSB MT 26550.1

5 DUST MT 1581.98

6 SAND MT 35087.172

7 CEMENT MT 249

8 BITUMEN MT Nill

9 STEEL MT 110.598

R-BLOCK - DIGHA 6-LANE 23


S. No. Issues Department Status as on 31.05.2019

1 Shifting of 03 Nos of Temples Patna Administration Yet to be Shifted

DFO has temporarily stop the


Sanctioned Estimate of Tree Cutting, Transport, Shifting,
2 Patna, DFO work of cutting and uplifting of
Relocation etc.
trees.

1. Sanctioned Estimate for Electrical Utility Shifting from


Vikash Bhawan to AN College has been received.
TS Amount - Rs. 2,25,43,903/- 1. Supervision charge
out of which Supervision Charges - Rs. 5,82,186/- deposited by Contractor,
Work Order Received.
2. Sanctioned Estimate for Electrical Utility Shifting from Pani SBPDCL
3 2. Work has started at site.
Tanki Raiwlay crossing to Digha ghat road crossing has PESU Area Patna
been received. 3. Supervision Charges
deposited. Work Order
TS Amount – Rs-3,84,18,372/- out of which yet to be received.
Supervision Charges – Rs-9,99,256/-

R-BLOCK - DIGHA 6-LANE 24


 10 Nos of Stop Signboards installed at site

 09 Nos of Cautionary Signboards installed at site

 13 Nos of Cautionary Signboards installed at site

 06 Nos of Solar Blinker installed at Crossing of


Digha Road, Rajiv Nagar & Shivpuri
`

 05 Nos of Safety Barrier installed at Km-1+800, 2+535


3+000, 3+600 & 4+300

 02 Nos of Coated Sheet installed at Baiely Road & R Block

 50 Nos of Street Light installed on RHS of Project Carriageway


R-BLOCK - DIGHA 6-LANE 25
Batching Plant is erected and functional Major Material Stock at Stock Yard

R-BLOCK - DIGHA 6-LANE 26


Safety Arrangement at Site

R-BLOCK - DIGHA 6-LANE 27


Utility Shifting in Progress Safety Arrangement at Site
R-BLOCK - DIGHA 6-LANE 28
Subgrade Work is in Progress GSB is in progress

R-BLOCK - DIGHA 6-LANE 29


Raft of Box Culvert is Completed Slab completed of Box Culvert

R-BLOCK - DIGHA 6-LANE 30


RE Pannel Casting is in Progress Storm Water Drain work is in progess

R-BLOCK - DIGHA 6-LANE 31


R-BLOCK - DIGHA 6-LANE 32