Professional Documents
Culture Documents
Lecturer
Miodrag Ivkovi, MScE, PMP
Head of Wireless Access Network Planning & Development Department
Joint Stock Telecommunications Company Telekom Srbija Technical Division Planning & Development Function
miodragiv@telekom.rs
28.4.2012
Agenda
Time Management Tips and tricks Q&A
28.4.2012
Koriena dokumentacija: Andy Crow The PMP Examp Fourth Edition Frank T Anbary Q & As for the PMBOK Fourth Edition Rita Mulcahy PMP Exam Prep Sixth Edition PMI - A Guide to the Project Management Body of Knowledge (PMBOK Guide) 4ed
28.4.2012
Project Time Management is concerned primarily with resources, activities, scheduling and schedule management. PM should be in control of the schedule and not vice versa. The schedule is managed throughout the life of the project.
The process is all about analyzing the project s schedule activities to determine the resource requirements (number of resources, resources availability).
Expert Judgment Alternative Analysis Alternatives may be helpful (outsourcing, purchasing rather than building one, using totally different approach to completely activity ..) Published Estimating Data Extensive data available through published Bottom-UP Estimating If activity cannot be estimated due to it is too complex or it has not been broken down enough than activities have to break down further into progressive smaller pieces of work until these pieces may be estimated for their resources requirements. Once these estimations have been performed, the pieces may be summed up from the bottom up to an activity level. Project Management Software Help to store and organize information, experiments with an alternatives, routine calculations
Each activity in the activity list is analyzed to estimate how long it will take. Manu factors could influence duration of an activity: who will be doing the work, when they are available, how many resources will be assigned to this activity, amount of work contained in the activity.
B. Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule Results and Control Schedule.
C. Identify Activities, Develop Schedule, Execute Activities, Control Activities and Monitor Schedule Result. D. Determine Activities, Estimate Activity Durations, Develop Schedules, Implement Activities and Report Activity Results.
28.4.2012
46
C. The work far in the future is planned in detail for WBS components that are at a low level of the WBS.
D. A wave of detailed activities is planned during strategic planning to ensure that WBS deliverables and project milestones are achived.
28.4.2012 48
28.4.2012
49
28.4.2012
51
28.4.2012
52
28.4.2012
53
28.4.2012
54
28.4.2012
55
28.4.2012
58
28.4.2012
59
28.4.2012
60
28.4.2012
62
9. Answere: B Bar Chart shows activity start and end date with expected duration.
28.4.2012
64
28.4.2012
66
28.4.2012
68
C. An expert from each functional area of the project so that all questions may be answered.
D. Project status reports from you team members.
28.4.2012
72
14. Answer: A Milestone charts show the high level status, which would be appropriate given the audience and time allocated for this update.
28.4.2012
74
15.Ansver: C
Estimate Activity Resources Inputs 1.Activity List 2. Activity Attributes 3. Resource Calendars 4. Enterprise Environmental Factors 5. Organizational Process Assets
28.4.2012
76
16. Answer: A The critical chain method provides a buffer to be used by the project manager to protect the critical path. Typically, the team is not aware of this buffer.
28.4.2012
78
17. Answer: B What-if analysis can take on many forms but the form you are most likely to see on the exam is Monte Carlo analysis, which throws a large number of scenarios at the schedule to see what would happen if on or more bad scenarios occurred.
D. Bottom-up estimating.
28.4.2012
80
18. Answer: C In this example management is providing you with analogous estimates. These estimates use actual costs from previous projects (historical information or organizational process assets) to produce estimates for a similar project.
28.4.2012
82
A. The approach is erroneous. A milestones is a significant point with zero duration to highlight achievements. B. It is a good approach as long as the milestones reflect fixed or imposed dates during the project lifecycle only. C. It is a good approach if the milestones are used for reviews between consecutive project phases only. D. It is a good approach because it saves from progress measurement on activities and work packages.
28.4.2012
84