A project is an interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources. The three main goals of project management are
1. Complete the project on time or earlier. 2. Do not exceed the budget. 3. Meet the specifications to the satisfaction of the customer.
2007 Pearson Education
Project Management
Project management is a systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects.
A collection of projects is called a program, which is an interdependent set of projects with a common strategic purpose.
A cross-functional effort: Even though a project may be under the overall purview of a single department, other departments likely should be involved.
2007 Pearson Education
Project Team
Selecting the right project manager is critical and specific skills are needed.
Facilitator: Able to resolve conflicts, have leadership skills and a systems view. Communicator: Ability to keep senior management informed, communicate progress, and work with team members. Decision Maker: Able to organize members and make difficult decisions.
Team members need to be technically competent, dedicated, and able to work well with other team members.
2007 Pearson Education
Organizational Structure
The relationship of a project manager to the team is determined by the firms organizational structure. Functional Structure: The team is housed in a specific functional area. Assistance from other areas must be negotiated. Pure Project: Team members work exclusively for the project manager, which is best for large projects. Matrix Structure: A compromise between the functional and project structures. Members remain in various functional areas and the project manager coordinates across functional areas. Dual authority can cause problems.
2007 Pearson Education
Planning Projects
Planning projects involves five steps:
1. Defining the work breakdown structure -a statement of all work that has to be completed. 2. Diagramming the network -- a graphical network 3. Developing the schedule -- specifying start times for each activity 4. Analyzing cost-time trade-offs 5. Assessing risks
2007 Pearson Education
An Activity is the smallest unit of work effort consuming both the time and resources that the project manager can schedule and control. Task Ownership: Each activity must have an owner who is responsible for doing the work.
2007 Pearson Education
Precedence Relationships
Precedence relationships determine a sequence for undertaking activities, and specify that any given activity cannot start until a preceding activity has been completed.
Activity On Node approach
In the AON approach, the nodes (circles) represent activities, and the arcs represent the precedence relationships between them.
2007 Pearson Education
AON
Activity Relationships
Activity Relationships
U cannot begin until S & T have been completed. V cannot begin until T has been completed.
S U
Activity Relationships
T & U cannot begin until S has been completed; V cannot begin until both T & U have been completed.
S T V
G H I J K
Select administrative and medical staff. Select site and do site survey. Select equipment. Prepare final construction plans and layout. Bring utilities to the site. Interview applicants and fill positions in nursing, support staff, maintenance, and security. Purchase and take delivery of equipment. Construct the hospital. Develop an information system. Install the equipment. Train nurses and support staff.
G H I J K
Select administrative and medical staff. Select site and do site survey. Select equipment. A Prepare final construction plans and layout. B Bring utilities to the site. B Interview applicants and fill positions in A nursing, support staff, maintenance, and security. Purchase and take delivery of equipment. C Construct the hospital. D Develop an information system. A Install the equipment. E,G,H Train nurses and support staff. F,I,J
Start
Finish
E
2007 Pearson Education
Time (wks) 33 28 67 69 43
Start
Finish
Start
Finish
Application 3.1
Application 3.1
Solution
Slack
The earliest you can complete an activity -- determined by adding the activity time to the earliest start time.
Activity
Earliest Start Earliest Finish Latest Finish
Duration
The latest you can finish an activity without delaying the project completion date. It is the same as the Latest Start time of the next activity. If there are two or more subsequent activities, this time is the same as the earliest of those Latest Start times.
I 27 15
12 F 22
12
10 C 22 10 G 57 35
Start
12
22
Finish
B 9 9
D 19
10
19
H 59 40
59
J 63 4
Example 3.2
2007 Pearson Education
9 E 33
24
I 27 15
A 12
12
12 F 22
10 C 22 10 G 57 35
Start
12
22
Finish
Critical Path
B 9 9
D 19
10
19
H 59 40
59
J 63 4
Example 3.2
2007 Pearson Education
9 E 33
24
12
12 F 22 53 10 63
2 12 14
63 K 69 63 6 69
Start
12 22 14 10 24
35
B 9
0 9 9
9 19 9 10 19
19 19
H 59
59
J 63
40 59
59 4 63
Example 3.2
2007 Pearson Education
9 E 33 35 24 59
12 27 48 15 63
12
12 F 22 53 10 63
2 12 14
Start
12 22 14 10 24
22 G 57 24 59
35
Finish
B 9
0 9 9
9 19 9 10 19
19 59 19 40 59
59
J 63
59 4 63
Example 3.2
2007 Pearson Education
9 E 33 35 24 59
Project Schedule
A Gantt Chart is a project schedule, usually created by the project manager using computer software, that superimposes project activities, with their precedence relationships and estimated duration times, on a time line.
Activity slack is useful because it highlights activities that need close attention.
Free slack is the amount of time an activitys earliest finish time can be delayed without delaying the earliest start time of any activity that immediately follows.
Activities on the critical path have zero slack and cannot be delayed without delaying the project completion.
2007 Pearson Education
Node Duration
ES
LS
Slack
A B C D E F G H I J K
12 9 10 10 24 10 35 40 15 4 6
0 0 12 9 9 12 22 19 12 59 63
2 0 14 9 35 53 24 19 48 59 63
2 0 2 0 26 41 2 0 36 0 0
12
12 F 22 53 10 63
2 12 14
63 K 69 63 6 69
Start
12 22 14 10 24
22 G 57 24 59
35
Finish
B 9
0 9 9
9 19 9 10 19
19 59 19 40 59
59
J 63
59 4 63
Example 3.3
2007 Pearson Education
9 E 33 35 24 59
Application 3.2
Application 3.2
Critical Path and Project Duration
Crashing a project means expediting some activities to reduce overall project completion time and total project costs.
2007 Pearson Education
Project Costs
The total project costs are the sum of direct costs, indirect costs, and penalty costs. Direct costs include labor, materials, and any other costs directly related to project activities. Indirect costs include administration, depreciation, financial, and other variable overhead costs that can be avoided by reducing total project time. The shorter the duration of the project, the lower the indirect costs will be.
2007 Pearson Education
Cost to Crash
To assess the benefit of crashing certain activities, either from a cost or a schedule perspective, the project manager needs to know the following times and costs. Normal time (NT) is the time necessary to complete and activity under normal conditions. Normal cost (NC) is the activity cost associated with the normal time. Crash time (CT) is the shortest possible time to complete an activity. Crash cost (CC) is the activity cost associated with the crash time.
2007 Pearson Education
8000 Direct cost (dollars) 7000 Crash cost (CC) Linear cost assumption
(Crash time)
2007 Pearson Education
4. Repeat this procedure until the increase in direct costs is larger than the savings generated by shortening the project.
2007 Pearson Education
Direct Cost and Time Data for the St. Adolfs Hospital Project
Normal Time (NT) 12 9 10 10 24 10 35 40 15 4 6 Normal Cost (NC) $ 12,000 50,000 4,000 16,000 120,000 10,000 500,000 1,200,000 40,000 10,000 30,000 Crash Time (CT) 11 7 5 8 14 6 25 35 10 1 5 Crash Cost (CC) $ 13,000 64,000 7,000 20,000 200,000 16,000 530,000 1,260,000 52,500 13,000 34,000 Maximum Time Reduction (wk) 1 2 5 2 10 4 10 5 5 3 1 Cost of Crashing per Week (CC-NC) $ 1,000 7,000 600 2,000 8,000 1,500 3,000 12,000 2,500 1,000 4,000
Activity A B C D E F G H I J K
Shorten first
Totals
$1,992,000
$2,209,500
The project completion time is 69 weeks. The direct costs for that schedule are $1,992,000. The indirect costs are $8000 per week. Penalty costs after week 65 are $20,000 per week. Total cost is $2,624,000 for 69 weeks
($1,992,000 + 69($8000) + (69 65)($20,000)
Crashing by 3 weeks saves $81,000 for a new total cost of $2,543,000. Savings is 3 weeks of indirect costs (3 * $8000 = $24,000) plus 3 weeks of penalties (3 * $20,000 = $60,000) less the cost of crashing (3 * $1,000 = $3,000)
Step 1: The critical path is still B-D-H-J-K. Step 2: The cheapest activity to crash per week is now D at $2,000 a week. Step 3: Crash D by 2 weeks. The first week of reduction saves $28,000 by eliminating both the penalty and indirect costs (but $2,000 goes toward crashing costs.) The second week of reduction had no penalty, so it saves only the indirect costs of $8,000. Total cost is now $2,511,00 ($2,543,00 - $28,000 - $8,000 + $4,000)
I 15
Shortening D and J have created a second critical path, A-C-G-J-K. Both critical paths are 64 weeks. Both must now be shortened to realize any savings in indirect costs.
Start
A 12
F 10 C 10 G 35 H 40
K 6
Finish
B 9
D 8
J 1
E 24
2007 Pearson Education
combination of activities: A-B, A-H, C-B, C-H, G-B, G-H, or Crash activity K which is on both critical paths. (J and D have already been crashed.) The cheapest alternative is to crash activity K. It can only be crashed by one week at a cost of $4,000 The net savings are $8,000 $4,000 = $4,000 Total project cost now becomes $2,507,000
I 15 F 10 C 10 G 35 H 40 K 5
A 12
63 wks
Finish
Start
B 9
D 8
J 1
E 24
2007 Pearson Education
A B C D E F G H I J K
$ 1,000 7,000 600 2,000 8,000 1,500 3,000 12,000 2,500 1,000 4,000
B and C are the only remaining activities that can be crashed simultaneously without exceeding the potential savings of $8000 per week in indirect costs.
Summary
The minimum cost schedule is 61 weeks. Activities J, D, K, B, and C were crashed for a total savings of $117,800
Application 3.3
Application 3.3
Application 3.3
Application 3.3
Application 3.3
Application 3.3
Assessing Risks
Risk is a measure of the probability and consequence of not reaching a defined project goal. A major responsibility of the project manager at the start of a project is to develop a riskmanagement plan. A Risk-Management Plan identifies the key risks to a projects success and prescribes ways to circumvent them.
2007 Pearson Education
2. Project Team Capability: Involves risks from the project team itself such as poor selections and inexperience. 3. Operations Risk: Information accuracy, communications, and project timing.
2007 Pearson Education
Statistical Analysis
The Statistical Analysis approach requires that activity times be stated in terms of three reasonable time estimates for each activity.
1. Optimistic Time (a) is the shortest time in which a activity can be completed if all goes exceptionally well. 2. Most Likely Time (m) is the probable time for an activity. 3. Pessimistic Time (b) is the longest time required.
a
Optimistic
2007 Pearson Education
m Mean
b
Pessimistic
Time
a
2007 Pearson Education
3s
m Mean
3s
Time b
Mean a + 4m + b te = 6
Start
Finish
Variance
s2 =
ba 6
2
E
Start
Finish
7 + 4(8) + 15 te = = 9 weeks 6
s2 =
15 - 7 6
) = 1.78
Activity Statistics
Expected Variance Time (te ) (s 2 ) 12 9 10 10 24 10 35 40 15 4 6 0.11 1.78 2.78 1.78 7.11 4.00 7.11 2.78 9.00 5.44 0.11
11 7 5 8 14 6 25 35 10 1 5
Application 3.4
s2
= (variances of activities)
T TE z= s2
Pz = .8078 .81
69 72
s2
= (variances of activities)
T TE z= s2
Pz = .8980 .90
Application 3.5
Application 3.5
Resource-Related Problems
Excessive Activity Duration Estimates: Many time estimates come with a built-in cushion that management may not realize. Latest Date Mentality: The tendency for employees to procrastinate until the last moment before starting. Failure to Deliver Early, even if the work is completed before the latest finish date.
2007 Pearson Education
Resource-Related Problems
Path Mergers occur when two or more activity paths combine at a particular node. Both paths must be completed up to this point, which will eliminate any built-up slack. Multitasking is the performance of multiple project activities at the same time. Work on some activities is delayed for other work. Loss of Focus by a manager can happen if the critical path changes frequently.
2007 Pearson Education
Activity Duration ES C G J K D H E I F 10 35 4 6 10 40 24 15 10 16 26 61 65 10 20 10 16 16
Start
Finish
Resource requirements
Start
2007 Pearson Education
Time
Finish
Solved Problem 1
Solved Problem 1
Solved Problem 2
What is the probability of completing the project in 23 weeks?
Solved Problem 2
Solved Problem 2
4.0 8.0 0.0 4.0 A 4.0 8.0 D 12.0 16.0 20.0 9.0 9.0 E 15.5 15.5
Finish
4.0
6.5
Start
C 3.5
9.0 9.0 G
0.0 0.0
5.5 5.5
F 9.0
15.5 15.5
4.5
20.0 20.0
5.5 6.5
2007 Pearson Education
14.5 15.5
Solved Problem 2
Using the Normal Distribution appendix, we find that the probability of completing the project in 23 weeks or less is 0.9357.