TWO (2) STAND-BY GENSET

PRE-CONSTRUCTION PLAN
for
PROPOSED ADDITIONAL
TWO(2) UNITS STAND-BY
GENERATOR SET
3RS-08-WN-005

La Mesa North Booster Station, La Mesa Dam, Quezon City

JULY 16, 2008


1
TWO (2) STAND-BY GENSET
TABLE OF CONTENTS

2
TWO (2) STAND-BY GENSET
Vicinity Map

SITE

3
TWO (2) STAND-BY GENSET
Brief Description

The project involves the supply and labor, equipment and materials for the
completion of Proposed Two (2) Units Stand-by Generator Set for North
Pump Station, including acquisition of permits, license and clearance
acquisition, construction of new Generator House, rehabilitation works of
existing stand-by Generator Set and Pump Station Building, and other
related works as set out in the Contract Document
4
TWO (2) STAND-BY GENSET
Project Information
PROJECT NAME : PROPOSED ADDITIONAL TWO (2) UNITS STANDBY GENSET
FOR NORTH PUMP STATION, LA MESA NORTH BOOSTER STATION,
LA MESA DAM, QUEZON CITY
CONTRACT NO. :
LOCATION : La Mesa North Booster Station, La Mesa Dam, Quezon City
TYPE OF STRUCTURE : Warehouse Building
COVERERD FLOOR AREA : 144 m²
START DATE : July 1, 2008
END DATE : December 27, 2008
CONTRACT DURATION : 180 Days
180
OWNER/CLIENT : MAYNILAD WATER SERVICES INC.
OWNER REPRESENTATIVE : ALBEN Q. BUKUHAN
Manager South Caloocan, & Special Projects - North
PHILINO PUNO
Program Coordinator - PMG

5
TWO (2) STAND-BY GENSET
Contract Information
CONTRACT AMOUNT : Php 112,864,930.63
CONTRACT TYPE : Remeasurable
DOWN PAYMENT : 15% = 16,929,739.59 Php
TERMS OF PAYMENT : S-Curve Billing - if positive with respect to S-Curve Schedule
Progress Billing - if negative with respect to S-Curve Schedule
RETENTION : 10% = 11,286,493.06 Php
DURATION : 180 days
START DATE : July 1, 2008
END DATE : December 27, 2008
DEFECTS AND LIABILITY : 365 days
PERIOD
MINIMUM AMOUNT OF : 10%
INTERIM PAYMENT
CERTIFICATE

6
TWO (2) STAND-BY GENSET
General Conditions

BANK GUARANTEE : 10% of the Contract Amount


SURETY BOND : 30% of the Contract Amount
LIQUIDATED DAMAGES : 1/10 of 1% of the total Approved Contract Amount,
as revised minus the value of the completed usable
portion of the project
CARI : 100% of the Contract Amount
DEFECTS AND LIABILITY PERIOD : 365 days
DEFECTS AND LIABILITY PERIOD

7
TWO (2) STAND-BY GENSET
Scope of Work
I. GENERAL REQUIREMENTS
A. Mobilization
B. Permits, License, & Clearance Acquisition
C. On-going Cost
D. Service Vehicle
E. Demobilization

II. CONSTRUCTION OF NEW GENERATOR HOUSE


A. Civil Works
A.1 Site Cleaning/Preparation
A.2 Earthworks
A.2.1 Top Soil Stripping
A.2.2 Excavation
A.2.3 Subgrade Preparation
A.2.3.1 Subbase Course (Not Applicable)
A.2.3.2 Base Course (Not Applicable)
A.2.3.3 Backfilling and Compaction
A.2.4 Hauling and Disposal of Unsuitable/Excess Excavated Materials
8
TWO (2) STAND-BY GENSET
Scope of Work

A.3 Concrete Works


A.3.1 24Mpa Concrete
A.3.1.1 Concrete Columns, Wall and Column Footings, Beams,
Roof & Floor Slabs, Genset Foundations, Ramps, Canopy
Parapet, Scupper Drains & etc.

B. Architectural Works
B.1 Masonry Walls
B.2 Doors and Windows
B.3 Finishes
B.3.1 Plain Cement Plaster Wall Finish
B.3.2 Plain Cement Floor Finish
B.3.3 Smooth Surface Finish
B.3.4 Waterproofing
B.3.5 Painting

9
TWO (2) STAND-BY GENSET
Scope of Work

C. Metal Works
C.1 Supply & Installation of 6mm thk. Checkered Plate Cover for Electrical Trench

D. Mechanical Works
D.1 Overhead Monorail Crane
D.1.1 Design, Supply & Installation of Two (2) Units 10-Tons Lifting Capacity
Overhead Monorail Crane
D.2 Stand-by Genset
D.2.1 Supply, Delivery & Installation (On a "Design and Built" Basis) of Two (2)
Units 1750KW Stand-by Generator Set Assembly Complete with Exhaust
Ventillation/Cooling System, Controller, Switch Gear and Base Tank

D.2.2 Design, Supply and Installation of Two (2) Units Stand-by Genset's Fuel
Day Tank including Foundation Mounting Supports, Fuel Transfer Pump,
Fuel Lines, Valve and Piping Systems

10
TWO (2) STAND-BY GENSET
Scope of Work
E. ELECTRICAL WORKS
E.1 Panel Board, Lighting and Power System
E.1.1 Roughing-ins, Wiring and Cabling Including Circuit Termination
to Existing 230V, Single Phase, 60Hz Power Supply Panel
E.1.2 Supply and Installation of Lighting and Power Panelboard (LP)
Complete with the Necessary Circuit Bus/ Wiring/ Protection such
as Circuit Breakers
E.1.3 Supply, Installation & Termination of Lighting & Power Fixtures

E.2 Stand-by Genset


E.2.1 Roughing-ins, Wiring and Cabling (From Genset's Controller
/Switch Gear to Synchronizing/ Paralleling System Panel)

E.2.2 Grounding System


E.2.3 Testing and Commissioning of Completely Assembled Units
E.2.4 Tools, Spare Parts and Manuals

11
TWO (2) STAND-BY GENSET
Scope of Work
III. REHABILITATION WORKS AT EXISTING STANDBY GENSET AND
PUMP STATION BUILDING

A. At Existing Stand-by Genset Building


A.1 Dismantling/Removal & Disconnecting Existing Two(2) Units
800KW Stand-by Genset's Auto Load Sharing/ Synchronizing
& Control/ Switch Gear Panel Including Electrical Power &
Control Cables, Bus Bars, Conduits and Appertenances

A.2 Stand-by Genset


A.2.1 Supply and Installation (On a " Design and Built Basis)
of Synchronizing/Paralleling System Panel, Control
& Monitoring Panels, Switch Gear, Protection and
Control Relays
A.2.2 Grounding System
A.2.3 Testing and Commissioning of Completely Assembled Units
Tools Spare Parts and Manuals
12
TWO (2) STAND-BY GENSET
Scope of Work

IV. SYSTEM & FUNCTIONAL TESTING & COMMISSIONING OF COMPLETELY


ASSEMBLED UNITS

V. SEMINARS AND TRAININGS

13
TWO (2) STAND-BY GENSET
Summary of Quantities

14
TWO (2) STAND-BY GENSET
General Schedule - Summary
DATE JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER
ITEM NO. WORK DESCRIPTION START END DAYS 10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30 7 14 21 28
I GENERAL REQUIREMENTS 17-Jul-08 28-Dec-08 165.00

II CONSTRUCTION OF NEW GENERATOR HOUSE


A Structural Works
1 Site Development Works 01-Aug-08 23-Aug-08 23.00
2 Concreting 24-Aug-08 16-Oct-08 54.00

B Waterproofing 10-Oct-08 16-Oct-08 7.00

C Architectural works
1 Masonry Works 10-Oct-08 23-Oct-08 14.00
2 Finsihing 17-Oct-08 30-Oct-08 14.00
3 Doors and Windows 01-Nov-08 09-Nov-08 9.00
4 Painting Works 10-Nov-08 30-Nov-08 21.00

D Mechanical Works 11-Oct-08 07-Dec-08 58.00

E Electrical Works 01-Sep-08 21-Dec-08 112.00

III REHABILITATION WORKS AT EXISTING STANDBY 01-Sep-08 28-Dec-08 119.00


GENSET AND PUMP STATION BUILDING

Milestone Dates
ITEM DATE DESCRIPTION
1 July 1, 2008 Project Start
2 October 16, 2008 Completion of Structural Works
3 October 16, 2008 Waterproofing
3 November 30, 2008 Completion of Architectural Works
4 November 16, 2008 Delivery of Genset
5 December 14, 2008 Power Interruption
6 December 28, 2008 Project End
15
TWO (2) STAND-BY GENSET
General Schedule
DATE JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER
ITEM NO. WORK DESCRIPTION START END DAYS 10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30 7 14 21 28
I GENERAL REQUIREMENTS
A Mobilization 17-Jul-08 30-Jul-08 14.00 ## 4.2
B Permits, Licenses & clearance acquisition 17-Jul-08 30-Aug-08 45.00 ## ## ## ## ## ##
C On-Going Cost 17-Jul-08 28-Dec-08 165.00 ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
D Supply of Cell Card
E Service Vehicle 17-Jul-08 28-Dec-08 165.00 ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##
F Demobilization 14-Dec-08 28-Dec-08 15.00 ## ##

SUB-TOTAL FOR ITEM I


Sourcing Contract Awarding
II CONSTRUCTION OF NEW GENERATOR HOUSE
A Civil works
A.1 Site Clearing/Preparation 01-Aug-08 06-Aug-08 6.00 ##
A.2 Earthworks
Evaluation
A.2.1 Top Soil Stripping 10-Aug-08 16-Aug-08 7.00 ##
A.2.2 Excavation 17-Aug-08 23-Aug-08 7.00 ##

A.2.3 Subgrade Preparation


A.2.3.1 Subbase Course
Purchas
A.2.3.2 Base Course
ing
A.2.3.3 Backfilling & Compaction
A.2.3.3.1 Ordinary Backfill 11-Sep-08 17-Sep-08 7.00 ##
A.2.3.3.2 Imported Backfill
A.2.3.3.2a Common fill 11-Sep-08 17-Sep-08 7.00 ##
A.2.3.3.2b Structural Fill 11-Sep-08 17-Sep-08 7.00 ##
A.2.3.3.3 Gravel Bedding 11-Sep-08 17-Sep-08 7.00 ##
A.2.4 Hauling & Disposal of Unsuitable/Excess 18-Sep-08 30-Sep-08 13.00 ## ##
A.3 Concrete Materials
A.3.1 24 Mpa Concrete
A.3.1.1 Concrete Columns, Wall & column footings, 24-Aug-08 16-Oct-08 54.00 ## ## ## ## ## ## ##
Beams, Roof & Floor slab, Genset
Foundations, Ramps, Canopy, Parapet,
Scupper Drains, etc
PROCUREMENT
1 Cement
2 Sand
3 Rebar
4 Formworks

OPERATION
1 Footing 24-Aug-08 30-Aug-08 7.00
2 Footing tie beams 24-Aug-08 30-Aug-08 7.00
3 Columns
1st lift 01-Sep-08 10-Sep-08 10.00
2nd lift 18-Sep-08 24-Sep-08 7.00
4 Slab on Grade 11-Sep-08 17-Sep-08 7.00
5 Beams 25-Sep-08 09-Oct-08 15.00
6 Roof Slab 25-Sep-08 09-Oct-08 15.00
7 Parapet Walls 25-Sep-08 09-Oct-08 15.00
8 Scupper Drain 25-Sep-08 09-Oct-08 15.00 Sourcing Contract Awarding
9 Ramp 10-Oct-08 16-Oct-08 7.00

16
TWO (2) STAND-BY GENSET
General Schedule
DATE JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER
ITEM NO. WORK DESCRIPTION START END DAYS 10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30 7 14 21 28
8 Scupper Drain 25-Sep-08 09-Oct-08 15.00 Sourcing Contract Awarding
9 Ramp 10-Oct-08 16-Oct-08 7.00

B Architectural works
B.1 Masonry Walls
B.1.1 150mm CHB 10-Oct-08 23-Oct-08 14.00 Evaluation ## ##
B.2 Doors and Windows
B.2.1 Doors
B.2.1.1 D/1 ( Roll-Up Door, 3.50m x 4.80m) 01-Nov-08 09-Nov-08 9.00 ##
B.2.1.2 D/2 (Metal Louver Door, 0.90m x 2.10m) 01-Nov-08 09-Nov-08 9.00 ##
B.2.2 Windows
B.2.2.1 W/1 (Fixed Metal Louver, 2.50m x 5.50m) 01-Nov-08 09-Nov-08 9.00 ##
B.2.2.2 W/2 (Fixed Metal Louver, 5.20m x 5.50m) 01-Nov-08 09-Nov-08 9.00 ##

B.3 Finishes
B.3.1 Plain Cement Plaster Wall Finish 17-Oct-08 30-Oct-08 14.00 ## ##
B.3.2 Plain Cement Floor Finish 24-Oct-08 30-Oct-08 7.00 ##
B.3.3 Smooth Surface Finish 17-Oct-08 30-Oct-08 14.00 ## ##
B.3.4 Waterproofing
B.3.4.1 Three (3) Ply Waterproofing Membrane 10-Oct-08 16-Oct-08 7.00 ##
B.3.5 Painting
B.3.5.1 Metal Surface 24-Nov-08 30-Nov-08 7.00 ##
B.3.5.2 Concrete Surface 10-Nov-08 30-Nov-08 21.00 ## ## ##

C Metal works
C.1 Supply and Installation of 6mm thk. Checkered Plate 17-Nov-08 23-Nov-08 7.00 ##
Cover for electrical trench

D Mechanical Works
D.1 Overhead Monorail Crane
D.1.1 Design, Supply & Installation of Two (2) Units 10- 09-Oct-08 23-Nov-08 46.00 ## ##
tons Lifting Capacity Overhead Monorail Crane

D.2 Stand-By Genset


D.2.1 Supply, Delivery & Installation (On-a "Design & 24-Nov-08 07-Dec-08 14.00 ## ##
Build" Basis) of Two (2) Units 1750 KW Stand -By
Generator Set Assembly complete with Exhaust /
Ventilation / Cooling system, controller/Switchgear
and Base Tank
D.2.2 Design, Supply & Installation of Two (2) Units 10-Nov-08 07-Dec-08 28.00 ## ## ## ##
Stand-By Genset's fuel Day Tank including
Foundation Mounting Supports, fuel Transfer
Pump, Fuel Lines, Valves & Piping system

17
TWO (2) STAND-BY GENSET
General Schedule
DATE JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER
ITEM NO. WORK DESCRIPTION START END DAYS 10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30 7 14 21 28
E Electrical Works
E.1 Panelboard, Lighting & Power System
E.1.1 Roughing-ins, Wiring and Cabling including 01-Sep-08 30-Oct-08 60.00 ## ## ## ## ## ## ## ##
Circuit Termination to Existing 230V, Single
Phase, 60 Hz Power Supply Panel
E.1.2 Supply and Installation of Lighting & Power 01-Nov-08 16-Nov-08 16.00 ## ##
Panelboard (LP) complete with the necessary
Circuit Bus/Wiring/Protection such as Circuit
Breakers
E.1.3 Supply, Installation & Termination of Lighting of 17-Nov-08 23-Nov-08 7.00
Lighting & Power Fixtures
E.2 Stand-By Gensdet
E.2.1 Roughing-ins, Wiring and Cabling (From Genset 01-Sep-08 07-Dec-08 98.00 ## ## ## ## ## ## ## ## ## ## ## ## ##
Controller/Switchgear to Synchronizing/Paralleling
System Panel)
E.2.2 Grounding System ##
E.2.3 Testing and Commissioning of Completely 08-Dec-08 21-Dec-08 14.00 ## ##
Assembled Units
E.2.4 Tools, Spare Parts & Manuals 08-Dec-08 21-Dec-08 14.00 ## ##

SUB-TOTAL FOR ITEM II

III REHABILITATION WORKS AT EXISTING STANDBY


GENSET AND PUMP STATION BUILDING

A At Existing Stand-by- Genset Building


A.1 Dismantling/Removal & Disconnect Existing Two (2) 01-Sep-08 24-Sep-08 24.00 ## ## ## ## ## ##
Units 800 KW Stand-by Genset's auto Load
Sharing/Synchronizing & Control/Switchgear Panel
including Electrical Power & control Cables, Bus
Bars, Conduits & appurtenances
A.2 Supply and Installation ( On a "Design & Build" 25-Sep-08 14-Dec-08 81.00 ## ## ## ## ## ## ## ##
Basis) of Synchronizing/Paralleling System Panel,
Control & Monitoring Panels, Switchgear, Protection
& Control Relays, Load Shading control &
Communication Devices, and other Required
Appurtenances
A.3 Roughing-ins, Wiring & Cabling (From 01-Sep-08 24-Sep-08 24.00 ## ## ## ## ## ##
Synchronizing/Paralleling System Panel to Proposed
Automatic Transfer Switch)
B At Existing Pump Station Building Electrical (EE/MCP)
B.1 Dismantling/Removal & Disconnect Existing Manual 01-Sep-08 24-Sep-08 24.00 ## ## ##
Transfer Switch (MTS) Assembly
B.2 Supply & Installation of New Automatic Transfer 01-Dec-08 14-Dec-08 14.00 ## ##
Switch (ATS) including Switchgear, and Other
required Appurtenances

SUB-TOTAL FOR ITEM III

18
TWO (2) STAND-BY GENSET
General Schedule

DATE JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER


ITEM NO. WORK DESCRIPTION START END DAYS 10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30 7 14 21 28

IV SYSTEM & FUNCTIONAL TESTING & 15-Dec-08 28-Dec-08 14.00 ## ##


COMMISSIONING OF COMPLETELY ASSEMBLED
UNITS

SUB-TOTAL FOR ITEM IV

V SEMINARS AND TRAINING 15-Dec-08 28-Dec-08 14.00 ## ##

SUB-TOTAL FOR ITEM V

TOTAL AMOUNT (Php)

19
TWO (2) STAND-BY GENSET
S-Curve
Item No. Description of Work Contract Week 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Amount Wt % Month July-08 August-08 September-08 October-08 November-08 December-08
Date 8 15 22 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 27

I General Requirement 10,334,940.42 9.16% Original - - - 8.45 0.14 0.11 0.11 0.11 0.02 0.01 0.01 0.01 0.02 0.01 0.01 0.01 0.02 0.01 0.01 0.01 0.01 0.01 0.02 0.02 100.00
Actual
Installation of ATS and
II Construction of New Generator Synchronizing Panel
House
A Civil Works 5,661,204.89 5.02% Original - - - - 0.41 0.02 0.10 0.63 0.31 0.40 0.32 1.26 1.25 0.31 - - - - - - - - - -
80.00
Actual
B Architectural Works 2,158,440.35 1.91% Original - - - - - - - - - - - - - 0.25 0.37 0.42 0.57 0.06 0.06 0.18 - - - -
Actual
C Metal Works 55,925.90 0.05% Original - - - - - - - - - - - - - - 0.05 - - - - - - - - -
Actual
60.00
D Mechanical Works 69,756,364.39 61.81% Original - - - - - - - - - - - - - 1.06 1.06 - - 0.30 0.30 29.55 29.55 - - -
Actual
E Electrical Works 11,968,367.76 10.60% Original - - - - - - - - 0.95 0.66 0.66 0.66 0.85 0.66 0.66 0.66 1.01 0.67 0.99 0.64 0.64 0.43 0.43 -
Actual
III Rehabilitation Works at Existing Arrival of Generator Set
Stand-by Genset and Pump
40.00
Station Building
A At Existing Stand-by- Genset 7,264,037.83 6.44% Original - - - - - - - - 0.19 0.14 0.14 0.14 0.18 0.14 0.67 0.67 0.86 0.67 0.67 0.67 0.67 0.67 - -
Building
Actual
B At Existing Pump Station Building 5,345,025.96 4.74% Original - - - - - - - - 0.01 0.01 0.01 - - - - - - - - - 2.35 2.35 - -
Electrical (EE/MCP) Room
Actual
16.01% 20.00
IV SYSTEM & FUNCTIONAL 187,534.09 0.17% Original - - - - - - - - - - - - - - - - - - - - - - 0.08 0.08
TESTING & COMMISSIONING OF
COMPLETELY ASSEMBLED Actual
UNITS
V SEMINARS AND TRAINING 133,089.04 0.12% Original - - - - - - - - - - - - - - - - - - - - - - 0.06 0.06
Actual

TOTAL CONTRACT AMOUNT 112,864,930.63 100.00%

START

20
TWO (2) STAND-BY GENSET
Equipment Schedule
2008
ITEM DESCRIPTION July August September October November December
10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30
1 Cargo Truck 1 1 1 1 1 1
2 Service Vehicle (Kia) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Backhoe 1 1 1
4 Dump Truck 1 1 1
5 Plate Compactor/1 Ton Road Roller 1 1 1 1
6 One Bagger Mixer (Optional) 1 1 1 1 1 1 1

Office Equipment Schedule


2008
ITEM DESCRIPTION July August September October November December
10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30
I DMCI
1 Office Convan 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 Warehouse 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3 Computer 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
4 Printer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
5 Fax Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Office Tables 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
7 Seats 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
8 Office Supplies 1
9 White Board 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

I MWSI
1 Office Convan 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 Computer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Printer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Fax Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Office Tables 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 Seats 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

21
TWO (2) STAND-BY GENSET
Procurement Schedule
ITEM DESCRIPTION UNIT QTY 2008
July August September October November December
10 17 24 31 9 16 23 30 9 16 23 30 10 17 24 31 9 16 23 30 9 16 23 30
I EARTHWORKS
1 Backfill Materials

II STRUCTURAL
1 Reinforcement Bars
2 Cement
3 Sand
4 Gravel

III ARCHITECTURAL
1 CHB Wall with Plaster Finish
1.1 Concrete Hollow Blocks
1.2 Cement
1.3 Sand
1.4 Backer Rod
1.5 Silicone Sealant
Note: Reinforcement bar requirement
is included in structural requirements

2 Door and Windows


2.1 Metal Louver Doors
2.2 Metal Louver Windows
2.3 Roll-up Doors

IV MECHANICAL
1 1750KW Generator Set
2 10Ton Lifting Capacity Overhead
Monorail Crane

V ELECTRICAL
1 Electrical Conduits
2 Electrical Cables
3 60Hz Power Supply Panel
4 Lighting and Power Panel Board (LP)
5 Lighting and Power Fixtures

Legend

PRS
Procurement

Delivery Period
22
TWO (2) STAND-BY GENSET
Work Methodology
ITEM STRUCTURE EARTHWORKS REBAR FORMWORKS CONCRETING OTHERS
I Earthworks
1 Site Clearing/Preparation
1.1 Relocation of Trees All obstructing small trees (Malunggay, etc.) N/A N/A N/A N/A
will be manually excavated to expose the
outer limits of the roots. Once the outer limit
of the roots are exposed, the trees will be
manually lifted and the roots will be
temporarily placed inside a sack of moistured
soil. Afterwhich, the small trees will be
relocated to it's new designated location.
(Note: on the moment of the relocation, the
new location of the trees should be already
prepared and ready for planting). The activity
for every tree must be accomplished within
one (1) day to assure the life of the trees.

1.2 Top Soil Stripping After the clearing of trees, the area of the N/A N/A N/A N/A
New Generator House will be subject to Soil
Stripping in preparation for the elevation of
the Finish Floor Level. Soil Stripping will be
carried out using Backhoe while the Plate
Compactor will be used for the leveling and
compaction of the soil.

II Structural
1 Footings Manual Excavation will be conducted for the Reinforcement Bars for footings will be Footings will be cast in place, so formworks Concrete Mix will be done on-site with the N/A
eight (8) footings of the Generator House. fabricated and assembled on site with the use are no longer required use of one (1) bagger mixer
Note: Excavation should be well trimmed in of bar cutter and bar bender.
preparation for the "cast in place" of concrete.

2 Footing Tie Beams Manual Excavation will be conducted for the Reinforcement Bars for the footing tie beams Footings will be cast in place, so formworks Concrete Mix will be done on-site with the N/A
footing tie beams of the Generator House. will be fabricated and assembled on site with are no longer required use of one (1) bagger mixer
Note: Excavation should be well trimmed in the use of bar cutter and bar bender.
preparation for the "cast in place" of concrete.

3 Columns N/A Reinforcement Bars for the columns will be Pre-fabricated form panels will be used for the Concrete Mix will be done on-site with the N/A
fabricated and assembled on site with the use construction of column formworks. The use of one (1) bagger mixer
of bar cutter and bar bender. There will be aforesaid column formworks consists of
one splice zone for each column for the Aluma beams, 3/4 phenolic plywood and
connection of the Concrete Lifts other accessories to complete the assemlbly.
Also, Form Lumber will be used as supports
to fix and stabilize the prefabrcated panels.
The height of the colums will be in
accordance to the two (2) lifts of the columns

4 Slab on Grade N/A Reinforcement Bars for the Slab on Grade Pre-fabricated side panel forms will be used Ready Mixed Concrete will be used for this N/A
will be fabricated and assembled on site with for the construction of Slab on Grade structure, Concrete Requirement is around
the use of bar cutter and bar bender. formworks. 3/4 phenolic plywood, Form 14.4m³.
Lumber and accessories will be used.

23
TWO (2) STAND-BY GENSET
Work Methodology
ITEM STRUCTURE EARTHWORKS REBAR FORMWORKS CONCRETING OTHERS
II Structural
5 Beams N/A Reinforcement Bars for the Beams will be Pre-fabricated form panels will be used for the N/A
fabricated and assembled on site with the use construction of beam formworks, The
of bar cutter and bar bender. aforesaid panel consists of Aluma beams, 3/4
phenolic plywood, A-Frame, End Frame and
other necessary accessories to complete the
assembly. The construction of formworks for
these structure is simultaneous with that of
the Roof Slab
6 Roof Slab N/A Reinforcement Bars for the Concrete Roof Pre-fabricated slab panel forms will be used N/A
Slab will be fabricated and assembled on site for the construction of the Roof Slab
with the use of bar cutter and bar bender. formworks, The aforesaid panel consists of Concrete Pouring for these three structures
Aluma beams, 3/4 phenolic plywood, A- will be simultaneous (monolithic). Ready Mix
Frame, End Frame and other necessary Concrete will be used for these three (3)
accessories to complete the assembly. The structures. The Concrete Requirement for the
construction of formworks for this structure is above mentione is XXm³
simultaneous with that of the beams
7 Parapet Walls N/A Reinforcement Bars for the Parapet Walls will Pre-fabricated panel forms will be used for the N/A
be fabricated and assembled on site with the construction of the Parapet Wall formworks,
use of bar cutter and bar bender. The aforesaid panel consists of Aluma beams,
3/4 phenolic plywood, Form Lumbers and
other necessary accessories to complete the
assembly. The construction of formworks for
this structure is simultaneous with that of the
Beams and Concrete Roof Slab

8 Genset Pad N/A Reinforcement Bars for the Genset Pad will Pre-fabricated panel forms will be used for the Ready Mixed Concrete will be used for this N/A
be fabricated and assembled on site with the construction of the Genset Pad Side Panel structure, Concrete Requirement is around
use of bar cutter and bar bender. formworks, The aforesaid panel consists of 63.375m³.
Aluma beams, 3/4 phenolic plywood, Form
Lumbers and other necessary accessories to
complete the assembly.

III Architectural
1 CHB Walls N/A Vertical and Horizontal Bars will be N/A Voids of the concrete Hollow Blocks will be CHB Walls cosnsists of Concrete Hollow
strategiacally incorporated within the CHB filled with cement mortar to provide adhesion Blocks, Cement Mortar and Reinforcement
Wall to provide support for the walls and additional strength Bars. The Concrete Hollow Blocks will be
manually stacked (staggered arrangement),
reinforced with Reinforcement Bars and
bonded with mortar mix.
2 Finishes
2.1 Plain Cement Plaster Finish N/A N/A N/A N/A This is the finish that will be applied to the
Concrete Hollow Block Walls that consists of
a mortar mix with cement and sand ratio of
1:4. The thickness for the Cement Plaster
Finish will be 25mm.
2.2 Plain Cement Floor Finsih N/A N/A N/A N/A This is the finish that will be applied to the
Concrete Hollow Block Walls that consists of
a mortar mix with cement and sand ratio of
1:4. The thickness for the Cement Plaster
Finish will be 25mm.

24
TWO (2) STAND-BY GENSET
Work Methodology
ITEM STRUCTURE EARTHWORKS REBAR FORMWORKS CONCRETING OTHERS
III Architectural
2.3 Smooth Surface Finish N/A N/A N/A N/A This is the finish that will be applied to the
Concrete Roof underslab, which consists of a
mortar mix with cement and sand ratio of 1:4.
The thickness for the Cement Plaster Finish
will be 25mm.
3 Doors and Windows
3.1 Metal Louvered Doors N/A N/A N/A N/A The Metal Louvered Doors will be a
subcontracted work which will be
prefabricated offsite in accordance to the
designed measurement and delivered on-site
for installation.
3.2 Metal Lovered Windows N/A N/A N/A N/A The Metal Louvered Windows will be a
subcontracted work which will be
prefabricated offsite in accordance to the
designed measurement and delivered on-site
for installation.
3.3 Roll-up Doors N/A N/A N/A N/A The Roll-up door will be manufactured and
installed by the MWSI Approved Supplier.

IV Thermal and Moisture


1 Waterproofing N/A N/A N/A N/A This is a subcontracted work of which the
material specification is duly approved by
MWSI

V Mechanical Works
1 Overhead Monorail Crane N/A N/A N/A N/A This item will be supplied and installed by the
approved manufacturer of MWSI. The unit
will be delivered onsite and incorporated with
the steel monorail which is fabricated and
assembled on-site
2 Stand-by Genset N/A N/A N/A N/A The two (2) Genset is an imported item which
will arrive within three (3) to four (4) months.
Testing of the aforesaid units should be
conducted before turn over to MWSI
3 Fuel Day Tank N/A N/A N/A N/A The two (2) Fuel Day Tank is a subcontracted
work which will be supplied and fabricated on
and off-site. Testing for the aforesaid
assembly should be conducted before turn-
over to MWSI

VI Electrical Works Roughing-ins, cabling and wire termination


are subcontracted works.

25
TWO (2) STAND-BY GENSET
Work Methodology – Construction Strategy

SUBCON SHORT LIST


ITEMS DESCRIPTION ENTITY SUBCON 1 SUBCON 2 SUBCON 3 SUBCON 4 SUBCON 5
I SITE WORKS (Clearing) SUBCON Adnyl Const. REMC n/a n/a
II STRUCTURAL WORKS SUBCON Adnyl Const. REMC n/a n/a
III ARCHITECTURAL WORKS SUBCON Adnyl Const. REMC n/a n/a
IV MECHANICAL WORKS
1 Generator Set SUBCON Frontier Indentrade MHI Faustino Philman
2 Intrumentation Works SUBCON Danfoss Control House n/a n/a
3 10 Ton Monorail Crane (Supply & Install) SUBCON Ken Tool Pan Oriental MHE Demag n/a
4 Fuel Day Tank and Ducting Works SUBCON Borja Aristocrat n/a n/a

IV ELECTIRCAL WOKRS SUBCON BETA Specmaster Active Power n/a

26
TWO (2) STAND-BY GENSET
Organizational Chart

DAVID R. VILLAVIRAY
Project Director
Head Office

JUAN JOSE C. LARAGAN


Site
Project Manager

GARETH JOHN G. GALANG


Project-in-charge

MANUEL E. VILLON TBN


Consultant Safety Officer

ROMEO A. MARCOS JR. CYNTHIA FERRER TBN LEO MAGSAYSAY


MEP Coordinator Office Engineer Field Engineer Admin Officer

MARLON ACOSTA TBN JUN RABANAL


CADD Operator Field Supervisor Stock Clerk/TK

27
TWO (2) STAND-BY GENSET
Submittal Checklist
SUBMITTALS
ITEM DESCRIPTION MATERIALS MATERIALS SHOP DRAWING WORKING AS-BUILT
SPECIFICATIONS TESTING DRAWING DRAWINGS
I STRUCTURAL
1 Sand
2 Gravel
3 Cement
4 Reinforcement Bars R
5 Concrete Mix Design for 24MPa R R

II ARCHITECTURAL
1 Concrete Hollow Block R
2 Doors and Windows
2.1 Metal Louvered Doors R R
2.2 Metal Louvered Windows R R
2.3 Roll-up Doors R R
3 Checkered Plate R R
4

III MECHANICAL WORKS


1 10Ton Lifting Capacity R
Overhead Monorail Crane
2 10Ton Lifting Capacity R R
Overhead Monorail Crane
Assembly
3 1750KW Stand-by Generator R
Set
4 Fuel Day Tank R R
5 Synchronizing Panel R
6 Automatic Transfer Switch R

IV ELECTRICAL WORKS
1 Electrical Conduits R
2 Electrical Cables R
3 60Hz Power Supply Panel R
4 Lighting and Power Panel Board R
(LP)
5 Lighting and Power Fixtures R

28
TWO (2) STAND-BY GENSET
Permit Monitoring

ITEM DESCRIPTION STATUS REMARKS


1 Building Permit for preparation of Locational Permit
2 Electrical Works
3 Mechanical Works
4 DENR - ECC
5 Occupancy

29
TWO (2) STAND-BY GENSET
MRF Monitoring

30
TWO (2) STAND-BY GENSET
TRS Monitoring

31
TWO (2) STAND-BY GENSET
PRS Monitoring

32
TWO (2) STAND-BY GENSET
PRFS Monitoring

33
TWO (2) STAND-BY GENSET
Site Facility Layout
Legend
1. Engineering Office
2. Conference Rm

7 PM Office
3. Warehouse
4. Staging Area
5. Locker Area
6. Portalet

4
5
3
6

34
TWO (2) STAND-BY GENSET

Project Concerns
ITEM PARTICULARS ENTITY ACTION
1 Strategy, Preparation and Schedule of Power DMCI/Subcon & Subcon to submit methodology of
Interruption for the Installation of the MWSI installation/assembly. Methodology to be
Automatic Transfer Switch strategized by DMCI, subject for the approval
of MWSI
2 Approval of Lump Sum breakdown for the DMCI & MWSI Submit cost breakdown for all Lump Sum
recognition of Physical Accomplishments items
3 Delivery date of 1750KW Genset DMCI & Supplier Site Investigation

35
TWO (2) STAND-BY GENSET

Safety

36